Home / Browse projects / Palghar, Maharashtra / LAXMI TOWER

Registered No litigation declared Others project

LAXMI TOWER

By SHREE CONSTRUCTION

RG-MH-83562 · RERA P99000045857 · Last updated on MahaRERA portal: 2 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 3 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 15 other registrations.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2030Possession promisedno revision filed
4 of 11Construction stages donefurthest along: Stilt Floor, 75%
0Complaints at MahaRERAon this registration
Jump to the 59 documents Report an error

LAXMI TOWER is a Others project by SHREE CONSTRUCTION in Palghar, Maharashtra, registered with MahaRERA as P99000045857 on 15 Jun 2022. Possession is promised by 31 Dec 2030.

At a glance

Project

  • NameLAXMI TOWER
  • TypeOthers
  • Location
    • NIRABAI PATIL MARGE
    • VIRAR EAST
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401305
  • Pincode401305
  • RERA no.P99000045857
  • ReraGenie IDRG-MH-83562

Builder

  • NameSHREE CONSTRUCTION
  • Entity typePartnership
  • PartnersSANTOSH MATAPRASAD TIWARI, MAHESH SANTOSH TIWARI
  • Other registrations15 more →
  • Completed5 of 16
  • No longer live8 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

this monthRegisteredJun 2022PromisedDec 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Jun 2022
  • Promised completion31 Dec 2030
  • Revised completionNone
  • Buildings1 building record
  • Documents filed59 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
LAXMI TOWERNA170000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 2 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 75%.

LAXMI TOWER: 56% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor75%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks55%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 2 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed65

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots65
Closed/Covered1
Open Space64

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,990 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI16594.25
Proposed, not sanctioned15,994 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 32 33 AGRAWAL RESIDECY OPP DMART YASHWANT VIVA TOWNSHIP ACHOLE TALUKA VASAI

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKULDEEP PATIL ARCHITECT
EngineerGR CONSULTANTS
Chartered AccountantKMA & CO
PartnerRole in project
SHREE CONSTRUCTION-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Jun 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Jun 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Jun 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2030

Documents filed59

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: QTR 4 Form 1 LT.pdf2 May 2026
Form 2File: QTR 4 Form 2 LT.pdf2 May 2026
Form 3File: QTR 4 Form 3 LT.pdf2 May 2026
Disclosure of Sold and Booked InventoryFile: Sold unsold LT.pdf2 May 2026
Form 1File: Form 1.pdf23 Jan 2026
Form 2File: Form 2.pdf23 Jan 2026
Form 3File: Form 3.pdf23 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold And Unsold LT.pdf23 Jan 2026
Form 1File: Form 1 Lt.pdf5 Oct 2025
Form 2File: Form 2 Lt.pdf5 Oct 2025
Form 3File: Form 3 Lt.pdf5 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold And Unsold LT.pdf5 Oct 2025
Form 1File: Form 1 Shree Construction.pdf16 Sep 2025
Form 2File: Form 2 Shree Construction.pdf16 Sep 2025
Form 3File: Form 3 Shree Construction.pdf16 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold And Unsold LT.pdf16 Sep 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Shree Construction.pdf10 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Shree Construction.pdf10 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Shree Construction.pdf10 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: Form 5 Shree Construction.pdf10 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1- Shree Construction.pdf8 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-Shree Construction.pdf8 Feb 2025
Other - TechnicalFile: Revised CC.pdf25 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - LAXMI - DEC24.pdf23 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - LAXMI - DEC24.pdf23 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect 1 Laxmi Tower.pdf1 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Laxmi Tower (2).pdf1 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Laxmi Tower (2).pdf1 Aug 2024
Disclosure of sold/ booked inventoryFile: Sold and booked Laxmi Tower.pdf1 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Laxmi Tower.pdf1 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Laxmi Tower.pdf18 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 LAXMI TOWER.pdf15 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 LAXMI TOWER.pdf15 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Laxmi tower.pdf12 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Laxmi tower.pdf12 Mar 2024
Disclosure of sold/ booked inventoryFile: Sold Laxmi tower.pdf12 Mar 2024
Building plan approvalFile: TYPICAL FLOOR PLAN 1.PDF10 Jun 2022
Building plan approvalFile: TYPICAL FLOOR PLAN 2.PDF10 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: TYPICAL FLOOR PLAN 1.PDF10 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: TYPICAL FLOOR PLAN 2.PDF10 Jun 2022
Copy of the legal title reportFile: Title certificate as per rera.pdf8 Jun 2022
Building plan approvalFile: SHEET 02 GROUND FLOOR.PDF1 Jun 2022
Building plan approvalFile: SHEET 03 FIRST FLOOR.PDF1 Jun 2022
Layout approvalFile: SHEET 01 LAYOUT.PDF1 Jun 2022
PAN CardFile: pan card.pdf1 Jun 2022
Copy of the legal title reportFile: TITLE CERIFICATE.pdf1 Jun 2022
Details of encumbrancesFile: letter of encumbrances.pdf1 Jun 2022
Copy of Layout Approval (in case of layout)File: SHEET 01 LAYOUT.PDF1 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: SHEET 02 GROUND FLOOR.PDF1 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: SHEET 03 FIRST FLOOR.PDF1 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: commencement certificate.pdf1 Jun 2022
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf1 Jun 2022
Declaration in FORM BFile: form b.pdf1 Jun 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf1 Jun 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate.pdf1 Jun 2022
CERSAI detailsFile: CERSAI_Search_Report_200238675270_For_Asset_Based_Search_01_06_2022_19_02_35_195.pdf1 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf1 Jun 2022
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf1 Jun 2022
Proforma of Allotment letterFile: AGREEMENT FOR SALE LAXMI TOWER.pdf1 Jun 2022

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise
ProjectLocationRegisteredStatusPromisedDelivered
SHARDA HEIGHTP99000028119VIRAR, PalgharFeb 2021CompletedJun 2028Nov 2023
SHARDA TOWER - IIP99000028403VIRAR EAST, PalgharMar 2021CompletedJun 2027Sep 2023
SHARDA TOWER - IP99000014523VIRAR EAST, PalgharDec 2017CompletedDec 2022Dec 2021

How this compares with Palghar

31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep LAXMI TOWER on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VIRAR EAST3,200+ in Palghar

Builder: SHREE CONSTRUCTION

SHREE CONSTRUCTION has 16 registrations on MahaRERA, including SHREE SEVAGIR BABA COMPLEX and SHREE PRATHAMESH PARK. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if LAXMI TOWER is delayed beyond 31 Dec 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LAXMI TOWER?

The registered promoter entity is SHREE CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LAXMI TOWER?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for LAXMI TOWER?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at LAXMI TOWER?

The professionals named in the filing: Architect: KULDEEP PATIL ARCHITECT; Engineer: GR CONSULTANTS; Chartered Accountant: KMA & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LAXMI TOWER?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LAXMI TOWER. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LAXMI TOWER to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.