LAXMI GANGA HEIGHTS
By KRISHNA LEELA CONSTRUCTIONS
RG-MH-58984 · RERA P52100056109 · Last updated on MahaRERA portal: 29 Jan 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 7 months past the filed date
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
LAXMI GANGA HEIGHTS is a Others project by KRISHNA LEELA CONSTRUCTIONS in Pune, Maharashtra, registered with MahaRERA as P52100056109 on 10 May 2024. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 12 months from the original filing. 14 of the 22 units on this registration are recorded sold or booked, and 17 of 33 construction stages are filed complete.
At a glance
Project
- NameLAXMI GANGA HEIGHTS
- TypeOthers
- Location
- BANGLORE MUMBAI BYPASS
- S NO 4/1
- DANGAT PATIL BAUG
- Wadgaon Bk
- Haveli
- Pune
- 411041
- Pincode411041
- RERA no.P52100056109
- ReraGenie IDRG-MH-58984
Builder
- NameKRISHNA LEELA CONSTRUCTIONS
- Entity typePartnership
- PartnersPIYUSH MUKUND DANGAT, RANJIT DAULAT DANGAT, SOPAN LANKE, RUCHITA ROHAN DANGAT, Jaising Daulat Dangat, KAMLESH CHARWAD
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on10 May 2024
- Promised completion31 Mar 2026
- Revised completionRevised to 31 Mar 2026 (originally 31 Mar 2025)
- Buildings3 building records
- Documents filed80 files
Current status
Figures as on 29 Jan 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING A | NA | 8 | 7 | 10 | 0 | 10 |
| WING B | NA | 8 | 7 | 10 | 0 | 10 |
| WING C | NA | 3 | 0 | 0 | 2 | 2 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 29 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
17 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.
WING A82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 8% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING B82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 8% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING C27%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 29 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed20
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| WING A | 10 | 10 |
| WING B | 10 | 10 |
Land and ownership7
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| MUKTABAI SUDAM DANGAT | Vadgaon | Pune |
| CHITRA MUKUND DANGAT | Pune (M Corp.) | Pune |
| PIYUSH MUKUND DANGAT | Pune (M Corp.) | Pune |
| RUCHITA ROHAN DANGAT | Pune (M Corp.) | Pune |
| AARAV ROHAN DANGAT (MINOR) | Pune (M Corp.) | Pune |
| SUDAM GANGARAM DANGAT | Pune (M Corp.) | Pune |
| ROHAN MUKUND DANGAT | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | KHIRE BHIDE AND ASSOCIATES |
| Engineer | G A Bhilare Consultant Pvt. Ltd |
| Engineer | Girish Chandrakant Dhavale |
| Chartered Accountant | KHIVASARA AND CO LLP |
| Partner | Role in project |
|---|---|
| KRISHNA LEELA CONSTRUCTIONS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterConstruction of Wings A and B is completed and also some flats are sold. However, Wing C (commercial - 1 shop and 1 office) is still under construction and 30% work of Wing C is completed. Also, we are in the process of obtaining part completion from Pune Municipal corporation for Wing A and B. We will apply for completion of Wing C once construction of the same is completed. Hence, we need to extend the project timelines by 1 year.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 2 Jan 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 2 Jan 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 10 Apr 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 2 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed80
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1 KLC.pdf | 29 Jan 2026 |
| Form 2File: Form 2 KLC (2).pdf | 29 Jan 2026 |
| Form 3File: Krishnaleela form3 311225.pdf | 29 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold unsold dec.pdf | 29 Jan 2026 |
| Form 1File: Form 1 Sep-25.pdf | 18 Dec 2025 |
| Form 2File: Form 2 Sep-25.pdf | 18 Dec 2025 |
| Form 3File: Form 3 300925.pdf | 18 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold 300925.pdf | 18 Dec 2025 |
| Form 1File: Form 1.pdf | 2 Aug 2025 |
| Form 2File: Form 2 KLC.pdf | 2 Aug 2025 |
| Form 3File: Form 3 Krishnaleela Construction.pdf | 2 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Krishnaleela Const- Sold Unsold Units-30062025.pdf | 2 Aug 2025 |
| Form 1File: 1 Form-I Wing A_Laxmiganga Heights_Architects Cert.pdf | 29 Jul 2025 |
| Form 2File: Engineers Certificate.pdf | 29 Jul 2025 |
| Form 3File: 5 Form-III _Laxmiganga Heights_CA's Cert.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold june.pdf | 29 Jul 2025 |
| Form 1File: Form I_Wing A and B_Architect Certificate_merged.pdf | 29 Jul 2025 |
| Form 2File: Form II_Wing A and B_Engineers Certificate_merged.pdf | 29 Jul 2025 |
| Form 3File: Form III_CA CERTIFICATE.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Sep.pdf | 29 Jul 2025 |
| Form 1File: Form 1.pdf | 29 Jul 2025 |
| Form 2File: Engineers Certificate_31122024.pdf | 29 Jul 2025 |
| Form 3File: Form III_CA Cert_Laxmi Ganga.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec.pdf | 29 Jul 2025 |
| Form 1File: Form1_Artchitect's Cert_Laxmiganga_merged.pdf | 25 Jul 2025 |
| Form 2File: fORM 2_ Engg Certificate_merged.pdf | 25 Jul 2025 |
| Form 3File: Form 3_CA Cert_Krishnaleela_310325_Letterhead Signed.pdf | 25 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold _310325.pdf | 25 Jul 2025 |
| Form 2A (FY 2024-2025)File: Form 2A_Krishnaleela Const_31032025.pdf | 25 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_March 25.pdf | 22 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_March 25.pdf | 22 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_March 25.pdf | 22 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold _March 25.pdf | 22 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_Laxmiganga_Dec 24.pdf | 17 Apr 2025 |
| Other - TechnicalFile: Form 2A_24-25.pdf | 17 Apr 2025 |
| Declaration in FORM BFile: 2 Developers Form B- Notorised.pdf | 29 Mar 2025 |
| Other - TechnicalFile: 3 Architect's Certifcate of Work Updation Signed.pdf | 29 Mar 2025 |
| Disclosure for secured/unsecured finance availed for the projectFile: 5 Disclosure for secured unsecured finance availed for the project.pdf | 29 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 - Krishnaleela Constructions - converted.pdf | 11 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory - KL.pdf | 8 Mar 2025 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format-A Krishnaleela Const.pdf | 8 Mar 2025 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B.pdf | 8 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form I_Architect Certificate.pdf | 25 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form III_LAXMIGANGA_WING A-B FORM 1_31122024.pdf | 25 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form II_Engineers's Certificate_merged.pdf | 25 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form I_Wing A and B_Architect Certificate_merged.pdf | 2 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form III_CA CERTIFICATE.pdf | 2 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form II_Wing A and B_Engineers Certificate_merged.pdf | 2 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Engineers Certificate.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5 Form-III _Laxmiganga Heights_CA's Cert.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 KrishnaLeela Constructions.pdf | 30 Apr 2024 |
| Building plan approvalFile: 1-4_compressed-compressed.pdf | 10 Apr 2024 |
| Building plan approvalFile: 2-4_compressed-compressed.pdf | 10 Apr 2024 |
| Building plan approvalFile: 3-4_compressed-compressed.pdf | 10 Apr 2024 |
| Building plan approvalFile: 4-4_compressed-compressed.pdf | 10 Apr 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 1-4_compressed-compressed.pdf | 10 Apr 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 2-4_compressed-compressed.pdf | 10 Apr 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 3-4_compressed-compressed.pdf | 10 Apr 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 4-4_compressed-compressed.pdf | 10 Apr 2024 |
| Other - TechnicalFile: KLC_Declaration_merged.pdf | 7 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 STRUCTURAL CERTIFICATE.pdf | 27 Mar 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Interest in other entities_All Partners.pdf | 11 Mar 2024 |
| Details of encumbrances concerned to FinanceFile: ENCUMBRANCES CHARGES.pdf | 2 Feb 2024 |
| Details of encumbrances concerned to LegalFile: ENCUMBRANCES CHARGES.pdf | 2 Feb 2024 |
| CERSAI detailsFile: CERSAI CERTIFICATE.pdf | 2 Feb 2024 |
| Declaration about Commencement CertificateFile: DocScanner 04-Jan-2024 1-36 pm.pdf | 4 Jan 2024 |
| Layout approvalFile: 1-4 LAYOUT APPROVAL.pdf | 2 Jan 2024 |
| PAN CardFile: 1- KRISHNA LEELA CONSTRUCTIONS - PAN.pdf | 2 Jan 2024 |
| Copy of the legal title reportFile: LEGAL TITLE REPORT.pdf | 2 Jan 2024 |
| Copy of Layout Approval (in case of layout)File: 1-4 LAYOUT APPROVAL.pdf | 2 Jan 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf | 2 Jan 2024 |
| Declaration in FORM BFile: FORM B - DECLARATION DEVELOPER AND LANDOWNER.pdf | 2 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 ARCHITECT CERTIFICATE.pdf | 2 Jan 2024 |
| Proforma of Agreement for saleFile: RERA Agreement TO SALES.pdf | 2 Jan 2024 |
| Proforma of Allotment letterFile: Allotment Letter - Laxmiganga Heights.pdf | 2 Jan 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT ' A ' (1).pdf | 2 Jan 2024 |
| Deviation Report with respect to Allotment letterFile: DECLARATION OF DEVIATION.pdf | 2 Jan 2024 |
| Deviation Report with respect to model copy of AgreementFile: DECLARATION OF DEVIATION.pdf | 2 Jan 2024 |
| Other - LegalFile: DEVELOPMENT AGREEMENT.pdf | 2 Jan 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- All 80 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep LAXMI GANGA HEIGHTS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near S NO 4/1, DANGAT PATIL BAUG13,700+ in Pune
VYANA PHASE-I -T5, T6, T7
KOLTE-PATIL DEVELOPERS LIMITED
Pratham Vihar Phase I
LJR Constructions LLP
VYANA PHASE-I-T2,T3 AT THE RESERVE
KOLTE-PATIL DEVELOPERS LIMITED
MAITREE MEGA CITY
MAITREE INFRA
RAMANA MYRA
SAI AND SHANTISHOBHA VENTURE
Apple Regency
Sri Sidhievinayak associetes
Builder: KRISHNA LEELA CONSTRUCTIONS
KRISHNA LEELA CONSTRUCTIONS has 1 registration on MahaRERA, including LAXMI GANGA HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that LAXMI GANGA HEIGHTS shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if LAXMI GANGA HEIGHTS is delayed beyond 31 Mar 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of LAXMI GANGA HEIGHTS?
The registered promoter entity is KRISHNA LEELA CONSTRUCTIONS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in LAXMI GANGA HEIGHTS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for LAXMI GANGA HEIGHTS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at LAXMI GANGA HEIGHTS?
The professionals named in the filing: Architect: KHIRE BHIDE AND ASSOCIATES; Engineer: G A Bhilare Consultant Pvt. Ltd; Engineer: Girish Chandrakant Dhavale; Chartered Accountant: KHIVASARA AND CO LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in LAXMI GANGA HEIGHTS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback