Home / Browse projects / Pune, Maharashtra / Laxmi Bliss
Laxmi Bliss
RG-MH-65006 · RERA P52100052254 · Last updated on MahaRERA portal: 10 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 17 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Laxmi Bliss is a Residential / Group Housing project by SHREE MAHALAXMI ASSOCIATES in Pune, Maharashtra, registered with MahaRERA as P52100052254 on 2 Aug 2023. Possession is promised by 31 May 2027. The completion date has moved by 17 months from the original filing. 9 of the 28 units on this registration are recorded sold or booked, and 4 of 22 construction stages are filed complete.
At a glance
Project
- NameLaxmi Bliss
- TypeResidential / Group Housing
- Location
- Wakad
- Santosh Nagar
- Mulshi
- Pune
- 411057
- Pincode411057
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100052254
- ReraGenie IDRG-MH-65006
Builder
- NameSHREE MAHALAXMI ASSOCIATES
- Entity typePartnership
- PartnersAJIT SHAMARAO JADHAV, NILESH JAYWANT NAVALE, KASHINATH BHIKU SHINDE, RANJIT SHAMRAO JADHAV
- Other registrations2 more →
- Completed1 of 3
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on2 Aug 2023
- Promised completion31 May 2027
- Revised completionRevised to 31 May 2027 (originally 31 Dec 2025)
- Buildings2 building records
- Documents filed93 files
Current status
Figures as on 10 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building A | NA | 8 | 7 | 14 | 0 | 14 |
| Building B | NA | 8 | 7 | 14 | 0 | 14 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 10 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 80%.
Building A25%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | - |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building B25%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 10 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed40
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Building A | 20 | 20 |
| Building B | 20 | 20 |
Land and ownership7
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Sahebrao Narayan Ambhore | - | Pune |
| BabaSaheb Bhau Kamble | Pimpri Chinchawad (M Corp.) | Pune |
| Vijaya Shivaji Londhe | Pune (M Corp.) | Pune |
| Nagesh RaghunathTitar | Pimpri Chinchawad (M Corp.) | Pune |
| Vikash Keshav Gore | Pimpri Chinchawad (M Corp.) | Pune |
| Dilip Khandu Hadap | Pimpri Chinchawad (M Corp.) | Pune |
| Ganesh Purshottam Wadgaonkar | Pimpri Chinchawad (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Building B | NA | Rs 2.17 cr | Rs 1.08 cr |
| Building A | NA | Rs 1.45 cr | Rs 72.07 lakh |
| - | NA | Rs 45.18 lakh | - |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Vastu Shaili |
| Engineer | Rohinee Engineers |
| Engineer | Rohinee Kailas Badgujar |
| Engineer | Ajit Jadhav |
| Chartered Accountant | Vijay Jain And Associates |
| Chartered Accountant | CA Sujay Bogawat |
| Chartered Accountant | CA Sagar S Bhalerao |
| Partner | Role in project |
|---|---|
| SHREE MAHALAXMI ASSOCIATES | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterCorrection Project status 19/08/2026 1.Platinum Square Bhugon - Desk 1 - Last Submiited 04/02/2026 2.A R Mirador - Desk 1 - Last Submitted 08/07/2026 3.Skyvista- Desk 1 Submitted 29/07/2026 4.Ostia G1 - Desk 1 - last submited 07/08/2026 5.Visoka KEystone A Bldg-Desk 1 Submitted on 01/08/2026 6.Shaneshwar Smaruddhi- Desk 1 Submitted on 04/08/2026 7.Shree labsons Apartment - Desk 1 - last submitted 17/07/2026 8.Opulent properties Wing A - Desk 1 - last submitted 06/06/2026 9.Gulmohar 24 -Desk 1 - Last submitted - 02/07/2026 10.Sai Serenity - Desk 1 Last Submited 10/07/2026 11.Park 59 - Desk 1 -
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 15 Jun 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 10 Sep 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 10 Sep 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 May 2027
Documents filed93
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 93 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Layout approvalFile: Main Layout_11zon.pdf | 10 Sep 2026 |
| Building plan approvalFile: Building Plan 2-3_11zon.pdf | 10 Sep 2026 |
| Building plan approvalFile: Building Plan 3-3_11zon.pdf | 10 Sep 2026 |
| Layout approvalFile: 29-5-24-1-3.PDF | 31 Aug 2026 |
| Layout approvalFile: Main Layout_compressed.pdf | 31 Aug 2026 |
| Building plan approvalFile: 29-5-24-2-3.PDF | 31 Aug 2026 |
| Building plan approvalFile: 29-05-24 3-3.PDF | 31 Aug 2026 |
| Building plan approvalFile: Wakad planP2_11zon.pdf | 31 Aug 2026 |
| Building plan approvalFile: Wakad plan P3_11zon.pdf | 31 Aug 2026 |
| Withdrawal Update Form 1File: Laxmi Bliss - form 1 March 26.pdf | 31 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 (30).pdf | 31 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 mar 26 s.pdf | 31 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 (17) (1).pdf | 31 Aug 2026 |
| Withdrawal Update Form 3File: Form 3 Final.pdf | 31 Aug 2026 |
| Withdrawal Update Form 3File: Form 3 (31).pdf | 31 Aug 2026 |
| Form 1File: Form 1 Sep 2024.pdf | 15 Jul 2026 |
| Form 2File: Form 2.pdf | 15 Jul 2026 |
| Form 3File: Form 3.pdf | 15 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 15 Jul 2026 |
| Form 1File: Form 1 Jun 2024.pdf | 14 Jul 2026 |
| Form 2File: Form 2 Jun 24.pdf | 14 Jul 2026 |
| Form 3File: Form 3.pdf | 14 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 14 Jul 2026 |
| Form 1File: Form 1 Dec 2024.pdf | 14 Jul 2026 |
| Form 2File: Form 2 Dec 24 s.pdf | 14 Jul 2026 |
| Form 3File: Form 3.pdf | 14 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 14 Jul 2026 |
| Form 1File: Form 1 March 2025.pdf | 14 Jul 2026 |
| Form 2File: Form 2 March 25 s.pdf | 14 Jul 2026 |
| Form 3File: Form 3.pdf | 14 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 14 Jul 2026 |
| Form 1File: Form 1 Jun 2025.pdf | 14 Jul 2026 |
| Form 2File: Form 2 Jun 25 s.pdf | 14 Jul 2026 |
| Form 3File: Form 3.pdf | 14 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 14 Jul 2026 |
| Form 1File: Form 1 Sep 2025.pdf | 14 Jul 2026 |
| Form 2File: Form 2 Sep 25 s.pdf | 14 Jul 2026 |
| Form 3File: Form 3.pdf | 14 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 14 Jul 2026 |
| Form 1File: Laxmi Bliss - Form 1 Dec 25.pdf | 14 Jul 2026 |
| Form 2File: Form 2 Dec 25 s.pdf | 14 Jul 2026 |
| Form 3File: Form 3.pdf | 14 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 14 Jul 2026 |
| Form 1File: Form 1 Dec 2023.pdf | 14 Jul 2026 |
| Form 2File: Form 2 Dec 23 s.pdf | 14 Jul 2026 |
| Form 3File: Form 3_Dec 23.pdf | 14 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 14 Jul 2026 |
| Form 1File: Form 1 March 2024.pdf | 14 Jul 2026 |
| Form 2File: Form 2 March 24 s.pdf | 14 Jul 2026 |
| Form 3File: Form_3_March 24.pdf | 14 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 14 Jul 2026 |
| Form 2A (FY 2023-2024)File: laxmi bliss (1).pdf | 13 Jul 2026 |
| Form 2A (FY 2024-2025)File: laxmi bliss 25 (1) (1).pdf | 13 Jul 2026 |
| Form 2A (FY 2025-2026)File: Form 2A FY 2025-2026.pdf | 13 Jul 2026 |
| Form 5 (FY 2023-2024)File: 2023-24_SUJOY_UDIN (1).pdf | 10 Jul 2026 |
| Form 5 (FY 2024-2025)File: 2024-25_SUJOY_UDIN (1) (1).pdf | 10 Jul 2026 |
| Form 5 (FY 2025-2026)File: 2025-26_SUJOY_UDIN (1).pdf | 10 Jul 2026 |
| Layout approvalFile: Layout.PDF | 30 Jul 2024 |
| Building plan approvalFile: Floor Plan.PDF | 30 Jul 2024 |
| Building plan approvalFile: Elevation.PDF | 30 Jul 2024 |
| Copy of Layout Approval (in case of layout)File: Layout.PDF | 30 Jul 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Floor Plan.PDF | 30 Jul 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Elevation.PDF | 30 Jul 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Revised CC.pdf | 30 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_LAXMI BLISS_2023-24_Q3_compressed.pdf | 6 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf | 6 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1.pdf | 3 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 (1).pdf | 3 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Laxmi Bliss Form 2A.pdf | 3 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: sold unsold Declaration Laxmi bliss.pdf | 3 Jan 2024 |
| Copy of the legal title reportFile: Legal Report Flow.pdf | 15 Jun 2023 |
| CERSAI detailsFile: CERSAI.pdf | 13 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A CERTIFICATE 10 6 2023 (1)_compressed.pdf | 13 Jun 2023 |
| Proforma of Allotment letterFile: Model Form of Allotment Letter.pdf | 13 Jun 2023 |
| Layout approvalFile: Layout Main Highlighted.pdf | 10 Jun 2023 |
| Building plan approvalFile: Layout Section, Elevation, Floor Plan.pdf | 10 Jun 2023 |
| PAN CardFile: PAN Card.pdf | 10 Jun 2023 |
| Copy of the legal title reportFile: Search A.pdf | 10 Jun 2023 |
| Details of encumbrances concerned to FinanceFile: Encumbrance declared.pdf | 10 Jun 2023 |
| Details of encumbrances concerned to LegalFile: Encumbrance declared.pdf | 10 Jun 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 14,000+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 93 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Laxmi Bliss on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Santosh Nagar14,000+ in Pune
Filed coordinates, straight-line distance. 232 registered projects within 2 km.
Godrej Evergreen Square
Godrej Projects Development Limited
The Aqua Retreat at Godrej Park World
Maan-Hinje Township Developers Private Lim
The Gale at Godrej Park World
Maan-Hinje Township Developers Private Lim
VTP BELLISSIMO PHASE 1
MAGNITE DEVELOPERS PRIVATE LIMITED
Life Republic Sector R1 - 1st Avenue
KOLTE-PATIL DEVELOPERS LIMITED
The Greenfront at Godrej Park World
Maan Hinje Township Developers Private Lim
Builder: SHREE MAHALAXMI ASSOCIATES
SHREE MAHALAXMI ASSOCIATES has 3 registrations on MahaRERA, including SAINATH MALAD SRA CHS and Laxmi Bliss. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Laxmi Bliss is delayed beyond 31 May 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Laxmi Bliss?
The registered promoter entity is SHREE MAHALAXMI ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Laxmi Bliss?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Laxmi Bliss?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Laxmi Bliss?
The professionals named in the filing: Architect: Vastu Shaili; Engineer: Rohinee Engineers; Engineer: Rohinee Kailas Badgujar; Engineer: Ajit Jadhav; Chartered Accountant: Vijay Jain And Associates; Chartered Accountant: CA Sujay Bogawat. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Laxmi Bliss?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback