ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / La Commercia

Registered No litigation declared Others project

La Commercia

By AUM HOUSING

RG-MH-51599 · RERA P52100019443 · Last updated on MahaRERA portal: 1 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 54 months
  • 6 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 54 months from the original
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
14 of 52Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 121 documents Report an error

La Commercia is a Others project by AUM HOUSING in Pune, Maharashtra, registered with MahaRERA as P52100019443 on 30 Jan 2019. Possession is promised by 31 Mar 2027. The completion date has moved by 54 months from the original filing. 38 of the 52 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameLa Commercia
  • TypeOthers
  • Location
    • Baner Mhalunge Road
    • Baner
    • Haveli
    • Pune
    • 411045
  • Pincode411045
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100019443
  • ReraGenie IDRG-MH-51599

Builder

  • NameAUM HOUSING
  • Entity typePartnership
  • PartnersRASHMI KETAN VEERA, AJIT ZUMBERLAL KARNAVAT, ALPESH JASHUBHAI PATEL
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects9 →

Key dates

this monthRegisteredJan 2019First promiseSep 2022Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on30 Jan 2019
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 30 Sep 2022)
  • Buildings1 building record
  • Documents filed121 files

Current status

73%38 of 52 units booked
100.0%Work done, per cost certificate

Figures as on 1 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
La CommerciaNA6605252

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 1 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

La Commercia: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 1 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed90

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots90
Closed/Covered80
Open Space10

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,800 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on25 Sep 2025

Approvals and building plan

Sanctioning authorityPune Municipal Corporation Building Development Department
Permissible FSI11183.0
Proposed, not sanctioned4,948 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKalyani Nagar Pune
Estimated costRs 16.81 cr
Cost incurredRs 16.81 cr
Work done100.0%
BuildingWingEstimatedIncurred
La CommerciaNARs 16.81 crRs 16.81 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMangesh Bhandekar
EngineerKalpesh Zabak
Chartered AccountantPriyanka Chordiya
Chartered AccountantSAC & CO LLP
PartnerRole in project
AUM HOUSING-

Extensions applied for6

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100012585Sep 2022 → Mar 2024

Reason as filed by the promoterDue to lack of funds and Covid Pandemic

EXT52100024522Sep 2022 → Mar 2025

Reason as filed by the promoterThe project is almost completed some additional above-floor work is going on as well as the time required to take the completion certificate from the authority. The form -2 as per the actual work completed is attached herewith as there is some dispute with the major contractor hence cost was not added in the books form-3 shows the lesser cost incurred.

EXT52100028069Sep 2022 → Sep 2025

Reason as filed by the promoterConstruction of the project is almost completed. The actual site photos as on the date is attached for your reference. Due to combined offices into single office for two floors for which need to revised sanction plan. We are actively coordinating with the concerned departments to get the revised plan sanction expedite the necessary approvals and complete the formalities. for getting the approval from the concerned department (NOC) time required which is almost 2-3 months.

EA30092517985Sep 2022 → Mar 2026

Reason as filed by the promoterDue to delays in receiving certain mandatory government approvals, including but not limited to [mention specific approvals if known, e.g., environmental clearance, building plan approval, etc.], the progress of the project has been impacted. These approvals are beyond our control, and we have been actively following up with the respective departments to expedite the process. In light of the above, we kindly request an extension of the project registration under RERA to accommodate the delay caused by these pending approvals. We are committed to ensuring compliance with all applicable laws and

EA30032620458Sep 2022 → Jun 2026

Reason as filed by the promoterThis is to inform that the project has substantially progressed and a *Part Completion Certificate* has already been obtained from the competent authority for a portion of the project. Further, the application for issuance of the *Completion Certificate for the balance units* has already been duly submitted to the concerned authority. However, the same is currently under process and is yet to be received. In view of the above, the delay in obtaining the final Completion Certificate is procedural and beyond the our control . Accordingly, an application for *extension of the project registration

EA30062621636Sep 2022 → Mar 2027

Reason as filed by the promoterThe Promoter respectfully submits that the construction and development work of the project has been substantially completed in all material respects. The Project has reached the final stage of completion, and all statutory compliances and approvals required from the concerned Government Authorities and Local Bodies have been obtained. The Promoter has received the requisite No Objection Certificates (NOCs) and clearances from all the concerned departments, including the statutory authorities whose approvals are mandatory for issuance of the Occupancy Certificate (OC). Consequently, the applic

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Jan 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Nov 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jan 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Jan 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed121

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 121 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A La Commercia 2025-2026.pdf1 Aug 2026
Withdrawal Update Form 1File: FORM 1 la commercia as on 30 06 2026.pdf23 Jul 2026
Withdrawal Update Form 2File: Form 2 La Commercia 30 03 26.pdf23 Jul 2026
Withdrawal Update Form 3File: Form 3 La Commercia 30 06 2026 sign.pdf23 Jul 2026
Withdrawal Update Form 1File: FORM 1 la commercia.pdf13 Apr 2026
Withdrawal Update Form 2File: Form 2 La commercia 31032026 sign.pdf13 Apr 2026
Withdrawal Update Form 3File: Form 3 La Commercia 31032026 sign_compressed.pdf13 Apr 2026
Withdrawal Update Form 1File: Form 1 sign 31122025.pdf16 Feb 2026
Withdrawal Update Form 2File: Form -2La Commercia sign 31122025.pdf16 Feb 2026
Withdrawal Update Form 3File: Form 3 La Commercia 31122025 sign_compressed.pdf16 Feb 2026
Withdrawal Update Form 1File: FORM 1 la commercia as on 30092025.pdf13 Oct 2025
Withdrawal Update Form 2File: AUM HOUSING FORM-2.pdf13 Oct 2025
Withdrawal Update Form 3File: Form 3 La Commercia 30092025_final.pdf13 Oct 2025
Form 2A (FY 2024-2025)File: La Commercia_FORM 2A_2024-25.pdf30 Sep 2025
Form 5 (FY 2024-2025)File: La commercia 31-03-2025_Sign copy.pdf30 Sep 2025
Withdrawal Update Form 1File: FORM 1 la commercia as on 30062025.pdf25 Sep 2025
Withdrawal Update Form 2File: FORM 2 La Commercia-30062025SCAN.pdf25 Sep 2025
Withdrawal Update Form 3File: Form 3 La Commercia 30062025 sign_compressed.pdf25 Sep 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 la commercia as on 30062025.pdf24 Jul 2025
Certificates of CA (Form 3)File: Form 3 La Commercia 30062025 sign_compressed.pdf24 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 La Commercia-30062025SCAN.pdf24 Jul 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold 30062025SCAN.pdf24 Jul 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2024-25).pdf24 Jul 2025
Disclosure for secured/unsecured finance availed for the projectFile: secured-unsecured Finance La Commercia.pdf24 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 la commercia as on 31032025.pdf16 Apr 2025
Certificates of CA (Form 3)File: Form 3 La Commercia 31032025 Sign_compressed.pdf16 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 La Commercia 31032025 sign.pdf16 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold 31032025 sign.pdf16 Apr 2025
Declaration in FORM BFile: NEW FORM B AUM HOUSING LA COMMERCIA.pdf18 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 FORM 2_La Commercia_05012025_additional incurred cost include.pdf3 Feb 2025
Declaration in FORM BFile: Form b Aum Housing.pdf1 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 La Commercia 31122024.pdf15 Jan 2025
Certificates of CA (Form 3)File: form 3 La Commerci 31122024_Compress.pdf15 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 La Commercia.pdf15 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold La Commercia Sign.pdf15 Jan 2025
Layout approvalFile: 1-21_Red.pdf5 Nov 2024
Layout approvalFile: Ground Floor Plan.pdf5 Nov 2024
Layout approvalFile: Frist Floor Plan.pdf5 Nov 2024
Layout approvalFile: Second Floor Plan.pdf5 Nov 2024
Layout approvalFile: Third Floor Plan.pdf5 Nov 2024
Layout approvalFile: Fourth Floor Plan.pdf5 Nov 2024
Copy of Layout Approval (in case of layout)File: Ground Floor Plan.pdf5 Nov 2024
Copy of Layout Approval (in case of layout)File: Frist Floor Plan.pdf5 Nov 2024
Copy of Layout Approval (in case of layout)File: Second Floor Plan.pdf5 Nov 2024
Copy of Layout Approval (in case of layout)File: Third Floor Plan.pdf5 Nov 2024
Copy of Layout Approval (in case of layout)File: Fourth Floor Plan.pdf5 Nov 2024
Copy of Layout Approval (in case of layout)File: 1-21_Red.pdf5 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 la commercia as on 30092024.pdf16 Oct 2024
Certificates of CA (Form 3)File: Form 3 La Commercia 30092024_sign_compres.pdf16 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MAHA RERA FORM 2 La Commercia_30092024.pdf16 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold 30092024.pdf16 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 La commercia 31032024_compress.pdf11 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 La Commercia 30-06-2024.pdf18 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 La commercia 30-06-2024.pdf18 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold 30062024.pdf18 Jul 2024
Certificates of CA (Form 3)File: form 3 La commercia 30-06-2024_compressed.pdf18 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2a la commercia.pdf29 May 2024
Disclosure of sold/ booked inventoryFile: LA COMMERIA Sold Unsold Inventory 31032024.pdf29 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1.pdf29 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_compressed.pdf29 Apr 2024
Certificates of CA (Form 3)File: Form 3_compressed (1).pdf29 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: la commercia (1) (1).pdf29 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1LA-COMMERCIA 31122023.pdf11 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2a la commercia fy 22 23.pdf7 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: AUM HOUSING ENGINEER la commercia form 2 31122023.pdf3 Feb 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold 31122023 la commercia.pdf2 Feb 2024
Certificates of CA (Form 3)File: form 3 La Commercia 31122023 BOTH SIGN_compressed.pdf2 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 La Commercia_compressed.pdf1 Dec 2023
Disclosure of sold/ booked inventoryFile: La commercia disclosure sold unsold.pdf1 Dec 2023
Certificates of CA (Form 3)File: Form 3 la commercia 30092023 both signed.pdf1 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_La Commercia_FY 22_23.pdf31 Oct 2023
Disclosure of sold/ booked inventoryFile: La Commercia_sold unsold_30032023.pdf24 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other real estate organisations - Sharad Narayan Mogale.pdf24 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other real estate organisations-Ajit Zumbarlal Karnawat.pdf24 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 LA COMMERCIA 30032023.pdf16 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 La Commercia_30062023.pdf16 Aug 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold 30062023_sign.pdf16 Aug 2023
Certificates of CA (Form 3)File: Form 3 La Commercia 30032023 Both sign_Compressed.pdf16 Aug 2023
Certificates of CA (Form 3)File: Form 3 La Commercia 30062023 BOTH SIGN_Reduce.pdf16 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 La Commercia 30062022 - sign_Red.pdf16 Jun 2023

Promoter's earlier projects9

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

8 delivered on promise1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
THE MINTBANER19CompletedDec 2016Dec 2016
QUADRABANER4CompletedDec 2016Dec 2016
ASHIYANASHIVAJI NAGAR58CompletedDec 2016Dec 2016
KESHAV SHRUSHTIRATNAGIRI73CompletedDec 2015Dec 2015
CASA IMPERIAWAKAD397CompletedDec 2015Dec 2015
SRA PROJECTBHAWANI PETH428CompletedDec 2012Dec 2012
COSMOS REGENCY83 AND 84 BANER172CompletedDec 2012Dec 2012
CASA POLIWAKAD112CompletedDec 2011Dec 2011
LA VALE CASASNO.20 BAVDHAN120CompletedDec 2008Late, Jan 2009

How this compares with Pune

73%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 54 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep La Commercia on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Baner13,700+ in Pune

2 kmLa CommerciaCompleted 188Lapsed / revoked 64Other 162Dot size: filed unitsN

Filed coordinates, straight-line distance. 414 registered projects within 2 km.

Builder: AUM HOUSING

AUM HOUSING has 2 registrations on MahaRERA, including La Commercia and La commercia 4-9. Its filings disclose 9 earlier MahaRERA projects: declares 8 of 9 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if La Commercia is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of La Commercia?

The registered promoter entity is AUM HOUSING, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in La Commercia?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for La Commercia?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at La Commercia?

The professionals named in the filing: Architect: Mangesh Bhandekar; Engineer: Kalpesh Zabak; Chartered Accountant: Priyanka Chordiya; Chartered Accountant: SAC & CO LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in La Commercia?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About La Commercia. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save La Commercia to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.