Home / Browse projects / Thane, Maharashtra / L AND T SEAWOODS - AMBER AT WEST SQUARE

Registered Litigation declared Residential / Group Housing project

L AND T SEAWOODS - AMBER AT WEST SQUARE

By L&T REALTY PROPERTIES LIMITED

RG-MH-95990 · RERA P51700045795 · Last updated on MahaRERA portal: 7 Jul 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases
  • Completion date moved by 5 months
  • 1 extension taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 3 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 5 months from the original
11 of 11Construction stages doneevery applicable stage filed complete
1 of 133Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 117 documents Report an error

L AND T SEAWOODS - AMBER AT WEST SQUARE is a Residential / Group Housing project by L&T REALTY PROPERTIES LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700045795 on 15 Jun 2022. Possession is promised by 31 Dec 2027. The completion date has moved by 5 months from the original filing. 132 of the 133 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete.

At a glance

Project

  • NameL AND T SEAWOODS - AMBER AT WEST SQUARE
  • TypeResidential / Group Housing
  • Location
    • Navi Mumbai
    • L&T Seawoods
    • Navi Mumbai (M Corp.)
    • Thane
    • 400706
  • Pincode400706
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700045795
  • ReraGenie IDRG-MH-95990

Builder

  • NameL&T REALTY PROPERTIES LIMITED
  • Entity typeCompany
  • CINU45203MH2008PLC180029
  • Other registrations5 more →
  • Completed1 of 6
  • Declared earlier projects5 →

Key dates

this monthRegisteredJun 2022First promiseJul 2027Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Jun 2022
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Jul 2027)
  • Buildings1 building record
  • Documents filed117 files

Current status

99%132 of 133 units booked
68.5%Work done, per cost certificate

Figures as on 7 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AMBER AT WEST SQUARE G01NA43171330133

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 7 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

AMBER AT WEST SQUARE G01: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 7 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed240

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots240
Closed/Covered240

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,125 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on15 Oct 2025

Approvals and building plan

Sanctioning authorityNavi Mumbai Municipal Corporation
Permissible FSI33019.58
Proposed, not sanctioned9,278 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMumbai
Estimated costRs 140.91 cr
Cost incurredRs 96.49 cr
Work done68.48%
BuildingWingEstimatedIncurred
AMBER AT WEST SQUARE G01NARs 119.49 crRs 85.65 cr
-NARs 21.42 crRs 10.84 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHiten Sethi
EngineerSwapnil Joshi Joshi
Chartered AccountantUrmit Shah
PartnerRole in project
L&T REALTY PROPERTIES LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700013074Jul 2027 → Dec 2027

Reason as filed by the promoterAdditional 10 floors proposed to be built

Litigation declared2

CaseCourtStatus
110/2021High CourtOngoing
110/2021High CourtOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Jun 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Jun 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Dec 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed117

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 117 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1_FY 25-26_Q4_West Square - Amber.pdf7 Jul 2026
Withdrawal Update Form 2File: Form-2-Amber.pdf7 Jul 2026
Withdrawal Update Form 3File: Form-3-Amber Q2 25.pdf7 Jul 2026
Withdrawal Update Form 1File: Form 1_FY 25-26_Q4_West Square - Amber.pdf20 Apr 2026
Withdrawal Update Form 1File: Form 1_FY 25-26_Q4_West Square - Amber.pdf20 Apr 2026
Withdrawal Update Form 1File: Form 1_FY 25-26_Q4_West Square - Amber.pdf20 Apr 2026
Withdrawal Update Form 2File: Form-2-Amber.pdf20 Apr 2026
Withdrawal Update Form 2File: Form-2-Amber.pdf20 Apr 2026
Withdrawal Update Form 2File: Form-2-Amber.pdf20 Apr 2026
Withdrawal Update Form 3File: Form-3-Amber.pdf20 Apr 2026
Withdrawal Update Form 3File: Form-3-Amber.pdf20 Apr 2026
Withdrawal Update Form 3File: Form-3-Amber.pdf20 Apr 2026
Form 2A (FY 2025-2026)File: Form-2A-FY-2024-25-Amber.pdf20 Apr 2026
Withdrawal Update Form 1File: Form-1-Amber.pdf17 Oct 2025
Withdrawal Update Form 2File: Form-2-Amber.pdf17 Oct 2025
Withdrawal Update Form 3File: Form-3-Amber.pdf17 Oct 2025
Form 2A (FY 2024-2025)File: Form-2A-FY-2024-25-Amber.pdf30 Sep 2025
Form 5 (FY 2024-2025)File: Form-5 Certification- Amber-signed.pdf29 Sep 2025
Withdrawal Update Form 1File: Form-1-Amber.pdf23 Jul 2025
Withdrawal Update Form 2File: Form-2-Amber.pdf23 Jul 2025
Withdrawal Update Form 3File: Form-3-Amber.pdf23 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Amber.pdf21 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-Amber.pdf20 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Amber.pdf20 Apr 2025
Disclosure of sold/ booked inventoryFile: Inventory-Amber.pdf20 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A-Amber.pdf20 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Amber.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-Amber.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Amber.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Inventory-Amber.pdf20 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A-Amber.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q2- 24-25 - Form 1 -Amber.pdf19 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: LTSW-Q2-24-25-Form 3-Amber.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: LTSW-Q2-24-25-Form 2-Amber.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: Seawoods-Amber.pdf19 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: LTSW-Q2-24-25-Form 2A-Amber.pdf19 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Certification - Amber.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q1- 24-25 - Form 1 -Amber.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q1- 24-25 - Form 2 -Amber.pdf20 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Q1- 24-25 - Form 2A-Amber.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure-Amber.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Q1_FY 24-25_Amber.pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architect Certificate_Q4_FY23-24_G1-Amber at West Square F.pdf29 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 Q4-23-24-Form 2-Amber.pdf29 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 4 Q4- 23-24 - Form 2 A Amber.pdf29 Apr 2024
Disclosure of sold/ booked inventoryFile: Amber 1.pdf29 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Amber.pdf29 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form I-Architect Certificate-Q3-FY2023-24-G1-Amber at West Square.pdf20 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q3- 23-24 - Form 2 -Amber-F.pdf20 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Q-3_23-24 end 31-12-23 - AmberF.pdf20 Feb 2024
Disclosure of sold/ booked inventoryFile: LTSW_Amber.pdf20 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 with Table C_Q3_FY 23-24_Amber.pdf20 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architect Certificate_Q2_FY23-24_G1-Amber at West Square.pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: LTSW_Amber.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q2_23-24 Form-2 Amber.pdf19 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Q2_23-24 Form-2A Amber.pdf19 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 with Table C_Q2_FY 23-24_Jasper.pdf19 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 with Table C_Q2_FY 23-24_Amber.pdf19 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: P51700045795-Amber.pdf30 Sep 2023
Disclosure of sold/ booked inventoryFile: Sold, Unsold-LTSW-Amber.pdf10 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 _Q1_FY23-24_G1-Amber.pdf20 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 -Amber.pdf20 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A Amber.pdf20 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 with Table C_Amber_Q1_FY 23-24.pdf20 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_Amber.pdf14 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 -Jasper.pdf14 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 -Amber.pdf14 May 2023
Disclosure of sold/ booked inventoryFile: Seawood Tower Amber.pdf14 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-Amber.pdf20 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: Master Plan- Rera.pdf15 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: Master Plan.pdf10 Feb 2023
Disclosure of sold/ booked inventoryFile: LTSW-Amber_compressed.pdf20 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_G1_amber_dec22.pdf19 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q3_22-23 Form 2-Amber.pdf19 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Q3_22-23 Form 2A- Amber.pdf19 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 with Table C_Q3_FY 22-23_Amber.pdf19 Jan 2023
Declaration about Commencement CertificateFile: dec22_Amber-Declration of CC.pdf9 Dec 2022
Disclosure of sold/ booked inventoryFile: FormC_Amber-Appl_correction.pdf9 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Rev_Form3_Amber_Q2.pdf9 Dec 2022
Building plan approvalFile: Overall Area Statement.pdf8 Dec 2022

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
L AND T SEAWOODS RESIDENCES - NORTH TOWERSR 1 Sector 40 Nerul Navi Mumbai Maharashtra241CompletedJun 2024Feb 2024
L AND T SEAWOODS RESIDENCES PHASE IR 1 Sector 40 Nerul Navi Mumbai Maharashtra507CompletedDec 2023Dec 2023
Seawoods Grand Central Integrated developmentR 1 Sector 40 Nerul Navi Mumbai Maharashtra732CompletedSep 2016Sep 2016

How this compares with Thane

99%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 5 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep L AND T SEAWOODS - AMBER AT WEST SQUARE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near L&T Seawoods7,600+ in Thane

2 kmL AND T SEAWOODS - AMBERCompleted 48Lapsed / revoked 18Other 54Dot size: filed unitsN

Filed coordinates, straight-line distance. 120 registered projects within 2 km.

Builder: L&T REALTY PROPERTIES LIMITED

L&T REALTY PROPERTIES LIMITED has 6 registrations on MahaRERA, including L AND T SEAWOODS - AMBER AT WEST SQUARE and L AND T SEAWOODS - OPAL AT WEST SQUARE. Its filings disclose 5 earlier MahaRERA projects: declares 5 of 5 past projects completed on time. Litigation is declared on 6 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if L AND T SEAWOODS - AMBER AT WEST SQUARE is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of L AND T SEAWOODS - AMBER AT WEST SQUARE?

The registered promoter entity is L&T REALTY PROPERTIES LIMITED, a company as per the filing. Its CIN U45203MH2008PLC180029 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in L AND T SEAWOODS - AMBER AT WEST SQUARE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for L AND T SEAWOODS - AMBER AT WEST SQUARE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at L AND T SEAWOODS - AMBER AT WEST SQUARE?

The professionals named in the filing: Architect: Hiten Sethi; Engineer: Swapnil Joshi Joshi; Chartered Accountant: Urmit Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in L AND T SEAWOODS - AMBER AT WEST SQUARE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About L AND T SEAWOODS - AMBER AT WEST SQUARE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save L AND T SEAWOODS - AMBER AT WEST SQUARE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.