Home / Browse projects / Pune, Maharashtra / KUMAR PURAB A3 BUILDING
KUMAR PURAB A3 BUILDING
RG-MH-58482 · RERA P52100047614 · Last updated on MahaRERA portal: 23 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 6 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
KUMAR PURAB A3 BUILDING is a Residential / Group Housing project by KUMAR & POTNIS ASSOCIATES in Pune, Maharashtra, registered with MahaRERA as P52100047614 on 14 Nov 2022. Possession is promised by 31 Dec 2027. 118 of the 134 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NameKUMAR PURAB A3 BUILDING
- TypeResidential / Group Housing
- Location
- SOLAPUR ROAD
- TILEKAR WASTI
- Hadapsar
- Haveli
- Pune
- 411028
- Pincode411028
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100047614
- ReraGenie IDRG-MH-58482
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on14 Nov 2022
- Promised completion31 Dec 2027
- Revised completionNone
- Buildings1 building record
- Documents filed117 files
Current status
Figures as on 23 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| KUMAR PURAB A3 BUILDING | NA | 21 | 16 | 128 | 6 | 134 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 23 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 85%.
KUMAR PURAB A3 BUILDING: 54% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 8% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 6% |
Progress on shared amenities15
As on 23 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 60% |
| Water Supply | Yes | 60% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 60% |
| Storm Water Drains | Yes | 60% |
| Landscaping & Tree Planting | Yes | 60% |
| Street Lighting | Yes | 60% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 60% |
| Solid Waste Management And Disposal | Yes | 60% |
| Water conservation /Rain water harvesting | Yes | 60% |
| Energy managemcnt | Yes | 60% |
| Fire protection and fire safety requirements | Yes | 60% |
| Electrical meter room, sub-station, receiving station | Yes | 60% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed128
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| KUMAR PURAB A3 BUILDING | NA | Rs 35.56 cr | Rs 26.94 cr |
| - | NA | Rs 3.50 cr | Rs 78.81 lakh |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ANISH AVINASH NAWATHE |
| Engineer | AKSHAY JAGTAP |
| Engineer | Mr Abhijeet Shekar |
| Chartered Accountant | SUPRIYA ABHIJIT MUNDADA |
| Chartered Accountant | SPAK & CO. |
| Partner | Role in project |
|---|---|
| KUMAR & POTNIS ASSOCIATES | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 2 Sep 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Sep 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 Feb 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed117
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 117 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 K.Purab A3 Bldg..PDF | 23 Apr 2026 |
| Withdrawal Update Form 2File: Purab A3 Engineering Certificate.pdf | 23 Apr 2026 |
| Withdrawal Update Form 3File: Form 1 K.Purab A3 Bldg..PDF | 23 Apr 2026 |
| Withdrawal Update Form 1File: HP SCANJET FLOW 7500.PDF | 3 Feb 2026 |
| Withdrawal Update Form 2File: Purab A3 Engineers Certificate.pdf | 3 Feb 2026 |
| Withdrawal Update Form 3File: Kumar Purab A3-CA Certificate.pdf | 3 Feb 2026 |
| Form 5 (FY 2022-2023)File: Form 5 - Purab A 3 - 2022-23.pdf | 17 Nov 2025 |
| Form 5 (FY 2023-2024)File: Form 5 - Kumar Purab A3 - 2023-24.pdf | 17 Nov 2025 |
| Withdrawal Update Form 1File: Kumar Purab A3 Bldg.PDF | 9 Nov 2025 |
| Withdrawal Update Form 2File: Purab A3 Engineeru0027s Certificate.pdf | 9 Nov 2025 |
| Withdrawal Update Form 3File: Form 3_Purab A3_Sep 25_RERA Site_Signed.pdf | 9 Nov 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KPA Kumar Purab A3.pdf | 20 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kumar Purab A3 Bldg.PDF | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Purab A3 Engineer's Certificate.pdf | 19 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: KUMAR PURAB A3 PLACIDA.PDF | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 K Palaash A2.PDF | 17 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 K Purab A3 Bldg.PDF | 17 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Palaash A2 Oct to Dec 2024.PDF | 17 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Kumar Purab A3.PDF | 17 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Palaash A2 Engineers Certificate.pdf | 17 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Purab A3 Engineers Certificate.pdf | 17 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: KUMAR PALAASH A2.PDF | 17 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: KUMAR PURAB A-3 PLACIDA.PDF | 17 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Kumar Purab A3_compressed.pdf | 22 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Purab A3 Bldg.PDF | 20 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kumar Periwinkle B3.pdf | 20 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kumar Purab A3.pdf | 20 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Kumar Purab A3.pdf | 15 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kumar Purab A3.pdf | 15 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold inventory - Kumar Purab A3.pdf | 15 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Kumar Purab A3 - 2023-24.pdf | 12 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Kumar Purab A3 - 2023-24.pdf | 7 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Purab A 3.pdf | 22 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - Purab A 3 - 2022-23.pdf | 22 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Kumar Purab A 3.pdf | 10 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kumar Purab A3.pdf | 8 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold - Purab A3.pdf | 8 Apr 2024 |
| Details of encumbrances concerned to FinanceFile: Purab A3 - Emcumbrance - Financial.pdf | 29 Mar 2024 |
| Details of encumbrances concerned to LegalFile: Purab A3 - Emcumbrance - Financial.pdf | 29 Mar 2024 |
| Building plan approvalFile: 1.pdf | 19 Feb 2024 |
| Building plan approvalFile: 2.pdf | 19 Feb 2024 |
| Building plan approvalFile: 3.pdf | 19 Feb 2024 |
| Building plan approvalFile: 4.pdf | 19 Feb 2024 |
| Building plan approvalFile: 5.pdf | 19 Feb 2024 |
| Building plan approvalFile: 6.pdf | 19 Feb 2024 |
| Building plan approvalFile: 7.pdf | 19 Feb 2024 |
| Building plan approvalFile: 8.pdf | 19 Feb 2024 |
| Building plan approvalFile: 9.pdf | 19 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 1.pdf | 19 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 2.pdf | 19 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 3.pdf | 19 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 4.pdf | 19 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 5.pdf | 19 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 6.pdf | 19 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 7.pdf | 19 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 8.pdf | 19 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 9.pdf | 19 Feb 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 19 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - Purab A3 - 2023.pdf | 20 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Kumar Purab A3.PDF | 18 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Purab_A3_Engineer's Certificate.pdf | 18 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory - Purab A3.pdf | 18 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Kumar Purab A3.pdf | 18 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Purab A3.PDF | 28 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 3 Purab A3.PDF | 20 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Purab A3.pdf | 12 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Purab_A3_Engineer's Certificate.pdf | 11 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory - Purab A3.PDF | 11 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Kumar Purab A3.PDF | 29 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Kumar Purab A3.pdf | 19 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Kumar Purab - Placida A3.PDF | 19 Jul 2023 |
| Building plan approvalFile: 1_compressed.pdf | 14 Jul 2023 |
| Building plan approvalFile: 2_compressed.pdf | 14 Jul 2023 |
| Building plan approvalFile: 5_compressed.pdf | 14 Jul 2023 |
| Building plan approvalFile: 7_compressed.pdf | 14 Jul 2023 |
| Building plan approvalFile: 8_compressed.pdf | 14 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 1_compressed.pdf | 14 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 2_compressed.pdf | 14 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 5_compressed.pdf | 14 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 7_compressed.pdf | 14 Jul 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| KUMAR PURAB | HADAPSAR | 86 | Completed | Mar 2017 | Mar 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 6 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 117 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep KUMAR PURAB A3 BUILDING on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near TILEKAR WASTI13,700+ in Pune
Filed coordinates, straight-line distance. 97 registered projects within 2 km.
Amanora Arbano Towers 73,74,75 and 76
City Corporation Limited
Astrana
Dilip Baburao Tupe
Leisure Town Phase 1
Sai Proviso Homes
ARV Newtown Phase III
Vedant Infracon
Kumar Parc Residences - A2
Kumar Properties Infratech Developers Pvt
Kumar Parc residences - A1
Kumar Properties Infratech Developers Pvt
Builder: KUMAR & POTNIS ASSOCIATES
KUMAR & POTNIS ASSOCIATES has 7 registrations on MahaRERA, including KUMAR PALAASH A and KUMAR PURVA COMMERCIAL. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if KUMAR PURAB A3 BUILDING is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of KUMAR PURAB A3 BUILDING?
The registered promoter entity is KUMAR & POTNIS ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in KUMAR PURAB A3 BUILDING?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for KUMAR PURAB A3 BUILDING?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at KUMAR PURAB A3 BUILDING?
The professionals named in the filing: Architect: ANISH AVINASH NAWATHE; Engineer: AKSHAY JAGTAP; Engineer: Mr Abhijeet Shekar; Chartered Accountant: SUPRIYA ABHIJIT MUNDADA; Chartered Accountant: SPAK & CO.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in KUMAR PURAB A3 BUILDING?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback