ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / KUMAR OMKAR SHREE

Registered No litigation declared Residential / Group Housing project

KUMAR OMKAR SHREE

By KUMAR ENTERPRISES

RG-MH-80964 · RERA P52100015579 · Last updated on MahaRERA portal: 27 Apr 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 36 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 36 months from the original
5 of 11Construction stages donefurthest along: Slabs of Super Structure, 50%
47 of 72Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 108 documents Report an error

KUMAR OMKAR SHREE is a Residential / Group Housing project by KUMAR ENTERPRISES in Pune, Maharashtra, registered with MahaRERA as P52100015579 on 8 Mar 2018. Possession is promised by 31 Dec 2027. The completion date has moved by 36 months from the original filing. 25 of the 72 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameKUMAR OMKAR SHREE
  • TypeResidential / Group Housing
  • Location
    • NARHE ROAD
    • NARHE
    • Haveli
    • Pune
    • 411041
  • Pincode411041
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100015579
  • ReraGenie IDRG-MH-80964

Builder

  • NameKUMAR ENTERPRISES
  • Entity typePartnership
  • PartnersPUSHPA RAJENDRA RAIKAR, PRANAV RAJENDRA RAIKAR, NIKHIL GOPAL KUMBHARKAR

Key dates

this monthRegisteredMar 2018First promiseDec 2024Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on8 Mar 2018
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Dec 2024)
  • Buildings1 building record
  • Documents filed108 files

Current status

35%25 of 72 units booked
61.2%Work done, per cost certificate

Figures as on 27 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Kumar Omkar Shree Building C1 and C2NA8672072

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 27 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 50%.

Kumar Omkar Shree Building C1 and C2: 50% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 27 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed144

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots144
Closed/Covered36
Open Space108

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,340 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on4 Jul 2025

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority, Pune
Permissible FSI6640.0
Proposed, not sanctioned4,471 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRUTUJA PALACE, S. NO. 50 7A, NARHE DHAYARI ROAD, TAL. HAVELI, DIST. PUNE ,PUNE ,MAHARASHTRA PIN 411041
Estimated costRs 17.98 cr
Cost incurredRs 11.00 cr
Work done61.19%
BuildingWingEstimatedIncurred
Kumar Omkar Shree Building C1 and C2NARs 17.98 crRs 11.00 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectD
EngineerShriram B Shinde
Chartered AccountantR H Pothiwal & Associates
Chartered AccountantAjay Lokhande and Associates
Chartered AccountantPravin Pise & Associates
Chartered AccountantVaibhav S Bhise & Associates
PartnerRole in project
KUMAR ENTERPRISES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100017081Dec 2024 → Dec 2027

Reason as filed by the promoterc Building plan revise

Litigation declared1

CaseCourtStatus
1060/2017/2017CIVIL JUDGE SENIOR DIVISION PUNEARGUMENT ON EXH UNREADY

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Feb 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 May 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 May 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed108

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 108 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: Form 5 2024-25 (1).pdf27 Apr 2026
Withdrawal Update Form 1File: Architect Certificate March 2026.pdf21 Apr 2026
Withdrawal Update Form 2File: Engineer Certificate March 2026.pdf21 Apr 2026
Withdrawal Update Form 3File: Form 3 With Table C - Signed March 2026.pdf21 Apr 2026
Withdrawal Update Form 1File: Architect certificate.pdf20 Jan 2026
Withdrawal Update Form 2File: Engineer certificate.pdf20 Jan 2026
Withdrawal Update Form 3File: FM_3_Dec_2025.pdf20 Jan 2026
Withdrawal Update Form 1File: Architect Certificate Sep 25.pdf19 Nov 2025
Withdrawal Update Form 2File: Engineer Certificate Sep 25.pdf19 Nov 2025
Withdrawal Update Form 3File: FORM 3 (3).pdf19 Nov 2025
Withdrawal Update Form 1File: Architect Certificate Sep 25.pdf29 Oct 2025
Withdrawal Update Form 2File: Engineer Certificate Sep 25.pdf29 Oct 2025
Withdrawal Update Form 3File: September 2025 Form 3.pdf29 Oct 2025
Withdrawal Update Form 1File: Architect Certificate.pdf13 Oct 2025
Withdrawal Update Form 2File: Engineer Certificate.pdf13 Oct 2025
Withdrawal Update Form 3File: Form 3 - March 2025.pdf13 Oct 2025
Form 1File: Form 1 - March 2025.pdf4 Sep 2025
Form 2File: Form 2 - March 2025.pdf4 Sep 2025
Form 3File: Form 3 - March 2025.pdf4 Sep 2025
Disclosure of Sold and Booked InventoryFile: Disclosure - March 2025.pdf4 Sep 2025
Withdrawal Update Form 1File: Form 1 - March 2025.pdf4 Sep 2025
Withdrawal Update Form 2File: Form 2 - March 2025.pdf4 Sep 2025
Withdrawal Update Form 3File: Form 3 - March 2025.pdf4 Sep 2025
Withdrawal Update Form 1File: Form 1.pdf18 Jul 2025
Withdrawal Update Form 2File: Form 2.pdf18 Jul 2025
Withdrawal Update Form 3File: Form 3.pdf18 Jul 2025
Form 5 (FY 2023-2024)File: Form 5.pdf18 Jul 2025
Declaration in FORM BFile: Form B.pdf8 Apr 2025
Declaration about Commencement CertificateFile: Format D.pdf8 Apr 2025
CERSAI detailsFile: CERSAI.pdf8 Apr 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: SEPRET BANK ACCOUNT.pdf8 Apr 2025
Other - TechnicalFile: Date -03042025_compressed.pdf8 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: REAL ESTATE ORGANIZATION.pdf8 Apr 2025
Disclosure for secured/unsecured finance availed for the projectFile: FINANCE.pdf8 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_March 19.pdf2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_March 20.pdf2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_March 21.pdf2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_March 22.pdf2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_March 23.pdf2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_March 24.pdf2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_June 24.pdf2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Sep 24.pdf2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Dec 24.pdf2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_March 18.pdf2 Apr 2025
Certificates of CA (Form 3)File: Form 3_March 21.pdf2 Apr 2025
Certificates of CA (Form 3)File: Form 3_Dec 24.pdf2 Apr 2025
Certificates of CA (Form 3)File: Form 3_Sep 24.pdf2 Apr 2025
Certificates of CA (Form 3)File: Form 3_June 24.pdf2 Apr 2025
Certificates of CA (Form 3)File: Form 3_March 24.pdf2 Apr 2025
Certificates of CA (Form 3)File: Form 3_March 23.pdf2 Apr 2025
Certificates of CA (Form 3)File: Form 3_March 22.pdf2 Apr 2025
Certificates of CA (Form 3)File: Form 3_March 20.pdf2 Apr 2025
Certificates of CA (Form 3)File: Form 3_March 19.pdf2 Apr 2025
Certificates of CA (Form 3)File: Form 3_March 18.pdf2 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5_FY 2017-18.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_March 20.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Dec 24.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Sep 24.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_June 24.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_March 24.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_March 22.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_March 21.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_March 19.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_March 18.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_March 23.pdf2 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A_FY 2019-20.pdf2 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5_FY 2018-19.pdf2 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5_FY 2019-20.pdf2 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5_FY 2020-21.pdf2 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A_FY 2020-21.pdf2 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure_March 24.pdf2 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure_Dec 24.pdf2 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure_Sep 24.pdf2 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure_June 24.pdf2 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_FY 2021-22.pdf2 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A_FY 2021-22.pdf2 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A_FY 2022-23.pdf2 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_FY 2022-23.pdf2 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_FY 2023-24.pdf2 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_FY 2023-24.pdf2 Apr 2025

How this compares with Pune

35%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 36 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KUMAR OMKAR SHREE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NARHE13,700+ in Pune

2 kmKUMAR OMKAR SHREECompleted 72Lapsed / revoked 39Other 90Dot size: filed unitsN

Filed coordinates, straight-line distance. 201 registered projects within 2 km.

Builder: KUMAR ENTERPRISES

KUMAR ENTERPRISES has 1 registration on MahaRERA, including KUMAR OMKAR SHREE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if KUMAR OMKAR SHREE is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KUMAR OMKAR SHREE?

The registered promoter entity is KUMAR ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KUMAR OMKAR SHREE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KUMAR OMKAR SHREE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KUMAR OMKAR SHREE?

The professionals named in the filing: Architect: D; Engineer: Shriram B Shinde; Chartered Accountant: R H Pothiwal & Associates; Chartered Accountant: Ajay Lokhande and Associates; Chartered Accountant: Pravin Pise & Associates; Chartered Accountant: Vaibhav S Bhise & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KUMAR OMKAR SHREE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KUMAR OMKAR SHREE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KUMAR OMKAR SHREE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.