ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Kulkarni wada

Registered No litigation declared Others project

Kulkarni wada

By Jagdish Universal Superbiz Developers and Construction

RG-MH-27509 · RERA P52100034429 · Last updated on MahaRERA portal: 3 May 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 24 months from the original
4 of 11Construction stages donefurthest along: Internal walls, 80%
40 of 49Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 27 documents Report an error

Kulkarni wada is a Others project by Jagdish Universal Superbiz Developers and Construction in Pune, Maharashtra, registered with MahaRERA as P52100034429 on 5 Apr 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 9 of the 49 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameKulkarni wada
  • TypeOthers
  • Location
    • Kumthekar Road
    • Sadashiv Peth
    • Peth
    • Haveli
    • Pune
    • 411030
  • Pincode411030
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100034429
  • ReraGenie IDRG-MH-27509

Builder

  • NameJagdish Universal Superbiz Developers and Construction
  • Entity typePartnership
  • PartnersVijay Jaysing Pawar, Bhakti Makrand Chitale, Jitendra Madhukar Jadhav

Key dates

this monthRegisteredApr 2022First promiseDec 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on5 Apr 2022
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed27 files

Current status

18%9 of 49 units booked

Figures as on 3 May 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Kulkarni wadaNA9642749

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 80%.

Kulkarni wada: 51% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 3 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership4

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,827 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on22 Jan 2026
LandownerVillageDistrict
Jyoti KulkarniKothrudPune
Vrinda Dnyaneshwar KulkarniPethPune
Deepak Dnyaneshwar KulkarniPune (M Corp.)Pune
Tejal Bhushan ModakPethPune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI1766.77
Proposed, not sanctioned1,767 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNew Radhika Road, near Kadam Petrol Pump, Satara

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSayali Ritesh Kulkarni
EngineerJitendra Madhukar JAdhav
EngineerNIKHIL NIKAM
Chartered AccountantRaksha Ashwin Dongare
Chartered AccountantOMKAR SANJEEV GHANEKAR
Chartered AccountantNIKHIL ASHOK SAWANT
PartnerRole in project
Jagdish Universal Superbiz Developers and Construction-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100024957Dec 2024 → Dec 2026

Reason as filed by the promoterBackground and Reason for Extension Request:- During the course of our project development, it became necessary to make modifications to the sanctioned plan to address structural considerations. These modifications were approved by planning authority on 18/07/2022. To support changes in plan Firm needs to introduce new pile foundation as per Revised Sanction plan by PMC, this leads to additional delay in the completion of Project. Due to revised sanction plan the construction itself started after 8 months from it’s the original date. This lead to the project to exceed the original time line by

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Mar 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed27

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 DEC 2024 signed_250503_124632.pdf3 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 MAR 2025 signed_250503_124545.pdf3 May 2025
Declaration in FORM BFile: FormB jyotiK 2024.pdf18 Dec 2024
Declaration in FORM BFile: DOC-20241212-WA0012_241212_154011_compressed.pdf18 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 New after changes.pdf17 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Ceritificate Aneexure B Kulkarni Wada-1_2_241119_160236.pdf17 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate - 281124_241128_161729.pdf2 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Kulkarni wada_Nov 24_241125_120809.pdf28 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Ceritificate Aneexure B Kulkarni Wada-1_2_241119_160236.pdf28 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 RERA FY 2023-24 Signed-1.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_CA Certificate_Kulkarni Wada with Sign.pdf8 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 JAGDISH.pdf10 Jan 2024
Copy of the legal title reportFile: Format A TSR 24-03-22compressed.pdf24 Mar 2022
CERSAI detailsFile: CERSAI_Search_Report_200233251691_For_Asset_Based_Search_24_03_2022_11_05_46_535.pdf24 Mar 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Adobe Scan 24 Mar 2022.pdf24 Mar 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch certificate final.pdf21 Mar 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Scan 21 Mar 22 · 03·36·46.pdf21 Mar 2022
Declaration in FORM BFile: Form B Affidavit.pdf16 Mar 2022
Building plan approvalFile: BUILDING_PERMISSION_-CC-_KUMTHEKAR_ROAD__PUNE.pdf15 Mar 2022
Layout approvalFile: layout to be uploaded final-converted.pdf15 Mar 2022
PAN CardFile: Firm PAN Card.pdf15 Mar 2022
Details of encumbrancesFile: Non encumbrance t.pdf15 Mar 2022
Copy of Layout Approval (in case of layout)File: layout to be uploaded final-converted.pdf15 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: BUILDING_PERMISSION_-CC-_KUMTHEKAR_ROAD__PUNE.pdf15 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: BUILDING_PERMISSION_-CC-_KUMTHEKAR_ROAD__PUNE.pdf15 Mar 2022
Declaration about Commencement CertificateFile: Declaration for CC.pdf15 Mar 2022
Proforma of Allotment letterFile: agreement sale format.pdf15 Mar 2022

How this compares with Pune

18%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Kulkarni wada on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Sadashiv Peth13,700+ in Pune

2 kmKulkarni wadaCompleted 180Lapsed / revoked 132Other 180Dot size: filed unitsN

Filed coordinates, straight-line distance. 492 registered projects within 2 km.

Builder: Jagdish Universal Superbiz Developers and Construction

Jagdish Universal Superbiz Developers and Construction has 1 registration on MahaRERA, including Kulkarni wada. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Kulkarni wada is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Kulkarni wada?

The registered promoter entity is Jagdish Universal Superbiz Developers and Construction, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Kulkarni wada?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Kulkarni wada?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Kulkarni wada?

The professionals named in the filing: Architect: Sayali Ritesh Kulkarni; Engineer: Jitendra Madhukar JAdhav; Engineer: NIKHIL NIKAM; Chartered Accountant: Raksha Ashwin Dongare; Chartered Accountant: OMKAR SANJEEV GHANEKAR; Chartered Accountant: NIKHIL ASHOK SAWANT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Kulkarni wada?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Kulkarni wada. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Kulkarni wada to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.