Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Oct 2025Possession promisedregistration recorded completed
20 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
0 of 224Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 93 documents Report an error

KRYSTAL ONE PHASE I is a Residential / Group Housing project by RAMA SPACES in Pune, Maharashtra, registered with MahaRERA as P52100030567 on 1 Sep 2021. The registration is recorded completed; possession was promised by 30 Oct 2025. The completion date has moved by 12 months from the original filing. 224 of the 224 units on this registration are recorded sold or booked, and 20 of 22 construction stages are filed complete.

At a glance

Project

  • NameKRYSTAL ONE PHASE I
  • TypeResidential / Group Housing
  • Location
    • Dehu Alandi Road
    • Chikhali
    • Haveli
    • Pune
    • 412114
  • Pincode412114
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100030567
  • ReraGenie IDRG-MH-22199

Builder

  • NameRAMA SPACES
  • Entity typeOthers
  • ConstituentsRAM UDHARAM PANJABI Panjabi, JITENDRA SUNDERDAS PANJABI Panjabi, MOTI UDHARAM PANJABI Panjabi, GOVIND UDHARAM PANJABI Panjabi
  • Other registrations5 more →
  • Completed2 of 6
  • No longer live1 lapsed, de-registered or revoked
  • Past their filed date1
  • Declared earlier projects4 →

Key dates

this monthRegisteredSep 2021First promiseOct 2024Revised toOct 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on1 Sep 2021
  • Promised completion30 Oct 2025
  • Revised completionRevised to 30 Oct 2025 (originally 31 Oct 2024)
  • Buildings2 building records
  • Documents filed93 files

Current status

100%224 of 224 units booked
100.0%Work done, per cost certificate

Figures as on 16 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WingNA17141120112
B WingNA17141120112

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 16 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

A Wing91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B Wing91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 16 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes20%
Street LightingYes100%
Community BuildingsYes20%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes20%
Open ParkingYes100%

Parking filed157

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots157
Closed/Covered120
Open Space37
BuildingClosed/CoveredOpen SpaceTotal
A Wing44650
B Wing7631107

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,177 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on23 May 2025

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI20606.0
Proposed, not sanctioned19,625 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMaratha Chambers, Plot no 3, SDC, Sec 25, Bhel Chowk Road, Nigdi 411044
Estimated costRs 49.60 cr
Cost incurredRs 49.60 cr
Work done100.0%
BuildingWingEstimatedIncurred
B WingNARs 22.37 crRs 22.37 cr
A WingNARs 22.27 crRs 22.27 cr
-NARs 4.96 crRs 4.96 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectLandmark Design Group
EngineerNitin Gorakhe
EngineerAkshay Nigade
Chartered AccountantMadhusudan Jhanwar
Chartered AccountantL. B. Laddha & Co
PartnerRole in project
RAMA SPACES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100024862Oct 2024 → Oct 2025

Reason as filed by the promoterDue to the unavoidable circumstances beyond our control, we are few months behind the planned schedule for completion of the above said project

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Aug 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Jun 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Jun 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Jun 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed93

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 93 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Layout approvalFile: 1-Layout dt-16-05-2025_compressed.pdf16 Jun 2026
Building plan approvalFile: 5-A Wing and Gym-1_compressed.pdf16 Jun 2026
Building plan approvalFile: 6-A Wing-2_compressed.pdf16 Jun 2026
Building plan approvalFile: 7-A Wing-3.pdf16 Jun 2026
Building plan approvalFile: 8-B Wing-1.pdf16 Jun 2026
Building plan approvalFile: 9-B Wing-2_compressed.pdf16 Jun 2026
Building plan approvalFile: 10-B Wing-3.pdf16 Jun 2026
Commencement certificateFile: Commencement dt-16-05-2025_compressed.pdf16 Jun 2026
Occupational CertificateFile: Completion Certificate A and B wing Krystal one dt-24-07-2025.pdf16 Jun 2026
Withdrawal Update Form 1File: Krystal Ph-I - Form 1 (signed).pdf10 Jun 2026
Withdrawal Update Form 2File: Krystal Ph-I - Form 2 (signed).pdf10 Jun 2026
Withdrawal Update Form 3File: Krystal Ph-I - Form 3 (signed).pdf10 Jun 2026
Form 5 (FY 2024-2025)File: Form 5 - F Y 2024-25 - Krystal One Ph-I.pdf11 May 2026
Form 2A (FY 2025-2026)File: Krystal Ph-I - Form 2A (signed).pdf2 May 2026
Withdrawal Update Form 1File: Krystal Ph-I - Form 1 (signed).pdf19 Oct 2025
Withdrawal Update Form 2File: Krystal Ph-I - Form 2 (signed).pdf19 Oct 2025
Withdrawal Update Form 3File: Krystal Ph-I - Form 3 (signed).pdf19 Oct 2025
Layout approvalFile: 1-Layout dt-16-05-2025_compressed.pdf16 Sep 2025
Withdrawal Update Form 1File: Withdrawal Application Form1 - KO Ph-I (signed).pdf13 Sep 2025
Withdrawal Update Form 2File: Withdrawal Application Form2 - KO Ph-I (signed).pdf13 Sep 2025
Withdrawal Update Form 3File: Withdrawal Application Form3 - KO Ph-I (signed).pdf13 Sep 2025
Form 2A (FY 2024-2025)File: Krystal Ph-I - Form 2A (signed).pdf13 Sep 2025
Form 5 (FY 2023-2024)File: Form 5 - F Y 2023-24 - Krystal One Ph-I.pdf13 Sep 2025
Form 1File: Krystal Ph-I.pdf31 May 2025
Form 2File: Krystal Ph-I.pdf31 May 2025
Form 3File: Krystal Ph-I.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Krystal Ph-I.pdf31 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Krystal Ph-I.pdf15 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Krystal Ph-I.pdf14 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Krystal Ph-I.pdf11 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Krystal Ph-I.pdf17 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Krystal One Ph-I.pdf17 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Krystal Ph-I.pdf15 Jan 2025
Disclosure of sold/ booked inventoryFile: Krystal One Ph-I.pdf9 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - F Y 2023-24 - Krystal One Ph-I.pdf23 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Krystal Ph-I.pdf23 Oct 2024
Declaration in FORM BFile: Form B.pdf22 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Krystal Ph-I.pdf22 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Krystal Ph-I.pdf18 Oct 2024
Disclosure of sold/ booked inventoryFile: Krystal Ph-I.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Krystal One Ph-I.pdf19 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Krystal One Ph-I.pdf16 Jul 2024
Disclosure of sold/ booked inventoryFile: Krystal One Ph-I.pdf15 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Krystal One Ph-I.pdf13 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A KRYSTAL ONE PH-I.pdf13 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Krystal One Ph-I.pdf16 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Krystal Ph-I.pdf15 Apr 2024
Disclosure of sold/ booked inventoryFile: Krystal One Ph-I.pdf11 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Krystal One Ph-I.pdf10 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A KRYSTAL ONE PH-I.pdf5 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Krystal One Phase I.pdf24 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Krystal One Phase I.pdf23 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Krystal One Phase I.pdf22 Jan 2024
Disclosure of sold/ booked inventoryFile: Krystal One Ph-I.pdf19 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Krystal One Ph-I.pdf16 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 KRYSTAL ONE PH-I APRIL 2022 TO 31 MARCH 2023.pdf28 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 KRYSTAL ONE PH-I SEP-23 071023_11zon.pdf30 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Krystal One Ph-I SEPTEMBER-23.pdf18 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A Krystal One Phase One PH-I SEPTEMBER-23 SIGNED.pdf16 Oct 2023
Disclosure of sold/ booked inventoryFile: KRYSTAL ONE PH-I A B Inventory.pdf11 Oct 2023
Disclosure of sold/ booked inventoryFile: KRYSTAL ONE PH-I A B Inventory.pdf11 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Krystal One Ph-I.pdf8 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 KRYSTAL ONE PH-I 070723_11zon.pdf20 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 KRYSTAL ONE PH-I 070723_11zon.pdf20 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Krystal One Ph-I MAR-23.pdf18 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Krystal One Ph-I DEC-22_11zon.pdf16 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Krystal One Ph-I DEC-22_11zon.pdf16 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Krystal One Ph-I GE 205 Rama Spaces.pdf28 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 KRYSTAL ONE PH-I_11zon.pdf11 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Krystal One Phase-I_11zon 150722.pdf15 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Krystal One Ph-I_compressed (1).pdf14 Apr 2022
Disclosure of sold/ booked inventoryFile: Krystal One Ph I_DEC-21.pdf22 Jan 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3_Krystal One_05012022_compressed.pdf12 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Krystal One Ph-1 Form 2A DEC-21_compressed.pdf11 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KRYSTAL ONE PH-1 Arch Certificate form 1 DEC-21_11zon.pdf7 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KRYSTAL ONE PH-1 Arch Certificate form 1 DEC-21_11zon.pdf7 Jan 2022
Disclosure of sold/ booked inventoryFile: KRYSTAL ONE SEP-21 INVENTORY.pdf21 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Krystal One 10182021 1709.pdf19 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Krystal One - Form 1 REVISEDcompressed .pdf14 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Krystal One PH-I_compressed.pdf9 Oct 2021

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise2 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
PARADISE ONEP52100018033Chikhali, Pune200Oct 2018CompletedSep 2021Late, Apr 2023
KRYSTAL CITY - SAPPHIREGAT NO 98 AND 99 PLOT C DEHU ALANDI ROAD CHIKHALI PUNE 412114.188-CompletedApr 2017Apr 2017
KRYSTAL CITY - PEARLGAT NO 98 AND 99 PLOT NO D DEHU ALANDI ROAD CHIKHALI PUNE 412114.284-CompletedMar 2017Late, Apr 2017

How this compares with Pune

100%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KRYSTAL ONE PHASE I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chikhali13,700+ in Pune

2 kmKRYSTAL ONE PHASE ICompleted 67Lapsed / revoked 42Other 70Dot size: filed unitsN

Filed coordinates, straight-line distance. 179 registered projects within 2 km.

Builder: RAMA SPACES

RAMA SPACES has 6 registrations on MahaRERA, including PARADISE ONE and Krystal World Phase I. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if KRYSTAL ONE PHASE I is delayed beyond 30 Oct 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KRYSTAL ONE PHASE I?

The registered promoter entity is RAMA SPACES, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KRYSTAL ONE PHASE I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KRYSTAL ONE PHASE I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KRYSTAL ONE PHASE I?

The professionals named in the filing: Architect: Landmark Design Group; Engineer: Nitin Gorakhe; Engineer: Akshay Nigade; Chartered Accountant: Madhusudan Jhanwar; Chartered Accountant: L. B. Laddha & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KRYSTAL ONE PHASE I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KRYSTAL ONE PHASE I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KRYSTAL ONE PHASE I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.