Registration lapsed No litigation declared Plotted project

KRUSHNANKI-2

By OM SHIV INFRASTRUCTURE

RG-MH-41783 · RERA P50500053665 · Last updated on MahaRERA portal: 20 Apr 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 7 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Mar 2026Possession promised7 months past this date
38 of 38Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 82 documents Report an error

KRUSHNANKI-2 is a Plotted project by OM SHIV INFRASTRUCTURE in Nagpur, Maharashtra, registered with MahaRERA as P50500053665 on 21 Nov 2023. Possession was promised by 31 Mar 2026 and is now 7 months past that date. 0 of the 38 units on this registration are recorded sold or booked.

At a glance

Project

  • NameKRUSHNANKI-2
  • TypePlotted
  • Location
    • VIHIRGAON
    • Nagpur (Rural)
    • Nagpur
    • 441204
  • Pincode441204
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500053665
  • ReraGenie IDRG-MH-41783

Builder

  • NameOM SHIV INFRASTRUCTURE
  • Entity typePartnership
  • PartnersVIRENDRA SADASHIVRAO NIKHAR, PANKAJ MADHUKAR GAIKWAD, ASHISH BAPURAO SELOKAR, ARVIND PARVATLAL PANDE

Key dates

7 months past promisethis monthRegisteredNov 2023PromisedMar 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on21 Nov 2023
  • Promised completion31 Mar 2026
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed82 files

Current status

0%0 of 38 units booked

Figures as on 20 Apr 2026, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 20 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes65%
Water SupplyYes45%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes68%
Storm Water DrainsYes40%
Landscaping & Tree PlantingYes22%
Street LightingYes18%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes35%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes5%
Aggregate area of recreational Open SpaceYes35%
Open ParkingNoNot applicable

Land and ownership8

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,327 sq m
Land owned byThe promoter, with other names on the file
Named landowners8
LandownerVillageDistrict
LAXMAN BHIKAJI SHINDENagpur (M Corp.)Nagpur
RAM BHIKAJI SHINDENagpur (M Corp.)Gadchiroli
JYOTI BHARAT SHINDENagpur (M Corp.)Nagpur
ATHARVA BHARAT SHINDENagpur (M Corp.)Nagpur
HARIBHAU BHIKAJI SHINDENagpur (M Corp.)Nagpur
GAJANAN BHIKAJI SHINDENagpur (M Corp.)Nagpur
SHESHRAO BHIKAJI SHINDENagpur (M Corp.)Nagpur
KUSUM KAWDUJI GAWANDENagpur (M Corp.)Nagpur

Approvals and building plan

Sanctioning authorityNagpur Metropolitan Region Development Authority (NMRDA)

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMIDCORP FIN NAGPUR-440034

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectASHVIT V MANDPE
ArchitectAGRASEN ARCHITECTS
EngineerKAMAL SHAHU
EngineerSARANG AGRAWAL
Chartered AccountantCA ANKIT TALREJA
Chartered AccountantSUMIT SANTOSH AGRAWAL & ASSOCIATES
PartnerRole in project
OM SHIV INFRASTRUCTURE-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Sep 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Sep 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Sep 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Sep 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed82

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 82 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM-1 KRUSHNANKI-2 MAR-2026.pdf20 Apr 2026
Form 2File: FORM-2 KRUSHNANKI-2 MAR-2026.pdf20 Apr 2026
Form 3File: FORM-3 KRUSHNANKI-2 MAR-2026.pdf20 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD MAR-2026.pdf20 Apr 2026
Form 1File: KRUSHNANKI-2_Form-1- Architect Certificate mar-25.pdf2 Apr 2026
Form 2File: Krushnanki-2_Form-2-Engineers Certificate_Mar-25.pdf2 Apr 2026
Form 3File: FORM-3_MAR-25.pdf2 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD_MARCH-2025.pdf2 Apr 2026
Form 1File: KRUSHNANKI-2_Form-1- Architect Certificate june-25.pdf2 Apr 2026
Form 2File: Krushnanki-2_Form-2-Engineers Certificate_June-25.pdf2 Apr 2026
Form 3File: FORM-3_JUN-25.pdf2 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD_JUN-25.pdf2 Apr 2026
Form 1File: KRUSHNANKI-2_Form-1- Architect Certificate Sep-25.pdf2 Apr 2026
Form 2File: Krushnanki-2_Form-2-Engineers Certificate_Sep-25.pdf2 Apr 2026
Form 3File: FORM-3_SEPTEMBER-2025.pdf2 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD_SEPTEMBER-2025.pdf2 Apr 2026
Form 1File: KRUSHNANKI-2_Form-1- Architect Certificate Dec-25.pdf2 Apr 2026
Form 2File: Krushnanki-2_Form-2-Engineers Certificate_Dec-25.pdf2 Apr 2026
Form 3File: Krushnanki-2_Form-3-Dec-25.pdf2 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD-Dec-25.pdf2 Apr 2026
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Krushnanki-2 Dec-2023.pdf19 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Krushnanki-2 March-2024.pdf19 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Krushnanki-2 June-2024.pdf19 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Krushnanki-2 Sep-2024.pdf19 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Krushnanki-2 Dec-2024.pdf19 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Krushnanki-2_Jun-2024.pdf19 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Krushnanki-2_Dec-2024.pdf19 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Krushnanki-2_Sep-2024.pdf19 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Krushnanki-2_Jun-2024.pdf19 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Krushnanki-2_Mar-2024.pdf19 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Krushnanki-2_Dec-2023.pdf19 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold-Unsold_Dec-23.pdf19 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold-Unsold_Mar-24.pdf19 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold-Unsold_June-24.pdf19 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold-Unsold_Sep-24.pdf19 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold-Unsold_Dec-24.pdf19 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: KRUSHNANKI-2_Form-2A_MAR-24.pdf19 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 of Krushnanki-2_2023-24.pdf19 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 KRUSHNANKI-2_Sep-2024.pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 KRUSHNANKI-2_Dec-2024.pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 KRUSHNANKI-2_June-2024.pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: [see Regulation 3] (1).pdf26 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: [see Regulation 3].pdf26 Apr 2024
Other - TechnicalFile: SCN2023110122.pdf10 Nov 2023
Other - TechnicalFile: ilovepdf_merged (8)_11zon (3).pdf10 Nov 2023
Other - TechnicalFile: form dV1_Krushnanki-2.pdf2 Nov 2023
Layout approvalFile: Scan002-0079V1_compressed.pdf12 Sep 2023
Building plan approval or NA orderFile: Scan002-0079V1_compressed.pdf12 Sep 2023
PAN CardFile: PAN Card.pdf12 Sep 2023
Copy of the legal title reportFile: Search Report Virendra Nikhar (1).pdf12 Sep 2023
Details of encumbrances concerned to FinanceFile: ENCUM_FInance (1)_Krushnanki-2.pdf12 Sep 2023
Details of encumbrances concerned to FinanceFile: ENCUM_Legal (1)_Krushnanki-2.pdf12 Sep 2023
Details of encumbrances concerned to LegalFile: ENCUM_FInance (1)_Krushnanki-2.pdf12 Sep 2023
Details of encumbrances concerned to LegalFile: ENCUM_Legal (1)_Krushnanki-2.pdf12 Sep 2023
Copy of Layout Approval (in case of layout)File: Scan002-0079V1_compressed.pdf12 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: Scan002-0079V1_compressed.pdf12 Sep 2023
Commencement Certificates / NA Order for plotted developmentFile: NMRDA Gajanan Bhikaji Shinde30082023161042_compressed.pdf12 Sep 2023
Commencement Certificates / NA Order for plotted developmentFile: NA Order_compressed (2).pdf12 Sep 2023
Declaration about Commencement CertificateFile: form dV1_Krushnanki-2.pdf12 Sep 2023
Declaration in FORM BFile: FORM B LAND OWNER.pdf12 Sep 2023
Declaration in FORM BFile: fORM b pROMOTER.pdf12 Sep 2023
CERSAI detailsFile: CERSAI_Search_Report_200280054256_For_Asset_Based_Search_12_09_2023_11_29_31_391.pdf12 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3_compressed (1).pdf12 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: INTERES DEC_Arvind.pdf12 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: INTERES DEC_Ashish.pdf12 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: INTERES DEC_Pankaj.pdf12 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: INTERES DEC_Virendra.pdf12 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: INTERES DEC_Land Owner.pdf12 Sep 2023
Proforma of Agreement for saleFile: Agreement to Sale- Virendra Nikhar.pdf12 Sep 2023
Proforma of Allotment letterFile: Allotment Letter_Krushnanki-2.pdf12 Sep 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Account Disclosure_Bhakti Park.pdf12 Sep 2023
Deviation Report with respect to Allotment letterFile: Deviation Report _Allotment.pdf12 Sep 2023
Deviation Report with respect to model copy of AgreementFile: DEVIATION REPORT_ATS.pdf12 Sep 2023
Other - LegalFile: 1_OM SHIV INFRA VIHIRGAON-1-6.pdf12 Sep 2023
Other - LegalFile: 1_OM SHIV INFRA VIHIRGAON-7-12.pdf12 Sep 2023
Other - LegalFile: 3_OM SHIV INFRA VIHIRGAON.pdf12 Sep 2023
Other - LegalFile: 4_OM SHIV INFRA VIHIRGAON.pdf12 Sep 2023
Other - LegalFile: 5_OM SHIV INFRA VIHIRGAON NAGPUR-1-5.pdf12 Sep 2023
Other - LegalFile: 6_OM SHIV INFRA VIHIRGAON NAGPUR-6-10.pdf12 Sep 2023
Other - LegalFile: 7_OM SHIV INFRA VIHIRGAON NAGPUR.pdf12 Sep 2023

How this compares with Nagpur

0%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is among them

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KRUSHNANKI-2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VIHIRGAON2,800+ in Nagpur

2 kmKRUSHNANKI-2Completed 6Lapsed / revoked 2Other 14Dot size: filed unitsN

Filed coordinates, straight-line distance. 22 registered projects within 2 km.

Builder: OM SHIV INFRASTRUCTURE

OM SHIV INFRASTRUCTURE has 1 registration on MahaRERA, including KRUSHNANKI-2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What does it mean that KRUSHNANKI-2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if KRUSHNANKI-2 is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KRUSHNANKI-2?

The registered promoter entity is OM SHIV INFRASTRUCTURE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KRUSHNANKI-2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KRUSHNANKI-2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KRUSHNANKI-2?

The professionals named in the filing: Architect: ASHVIT V MANDPE; Architect: AGRASEN ARCHITECTS; Engineer: KAMAL SHAHU; Engineer: SARANG AGRAWAL; Chartered Accountant: CA ANKIT TALREJA; Chartered Accountant: SUMIT SANTOSH AGRAWAL & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KRUSHNANKI-2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KRUSHNANKI-2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KRUSHNANKI-2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.