Home / Browse projects / Nashik, Maharashtra / KRUSHNA VIJAY HEIGHTS
KRUSHNA VIJAY HEIGHTS
By Shree Sarvadnya Builders and Developers
RG-MH-18916 · RERA P51600077867 · Last updated on MahaRERA portal: 26 Mar 2026
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
KRUSHNA VIJAY HEIGHTS is a Residential / Group Housing project by Shree Sarvadnya Builders and Developers in Nashik, Maharashtra, registered with MahaRERA as P51600077867 on 7 Nov 2024. The registration is recorded completed; possession was promised by 22 Feb 2028. 7 of the 28 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NameKRUSHNA VIJAY HEIGHTS
- TypeResidential / Group Housing
- Location
- NASHIK SHIWAR
- NASHIK
- Nashik (M Corp.)
- 422009
- Pincode422009
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600077867
- ReraGenie IDRG-MH-18916
Builder
- NameShree Sarvadnya Builders and Developers
- Entity typePartnership
- GSTIN27AFBFS3147L1ZQ
- PartnersSachin Dashrath Patil, Prakash Khanderao Kale
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on7 Nov 2024
- Promised completion22 Feb 2028
- Revised completionNone
- Buildings1 building record
- Documents filed54 files
Current status
Figures as on 26 Mar 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| KRUSHNA VIJAY HEIGHTS | NA | 7 | 7 | 28 | 0 | 28 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 26 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.
KRUSHNA VIJAY HEIGHTS: 67% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 10% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Progress on shared amenities15
As on 26 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed28
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership3
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SHOBHANA VIJAY CHAUDHARI | Nashik (M Corp.) | Nashik |
| ASHOK ANKAT BHARAMBE | Nashik (M Corp.) | Nashik |
| PRAKASH MURLIDHAR PATIL | Nashik (M Corp.) | Nashik |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| KRUSHNA VIJAY HEIGHTS | NA | Rs 2.70 cr | Rs 2.40 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ashok Jamdar |
| Engineer | Lab Associates |
| Chartered Accountant | RSPH & Associates |
| Chartered Accountant | M/s P N Sabadra & Associates |
| Chartered Accountant | Anand Kabra & Co |
| Chartered Accountant | KRISHNAMURTHY JAIN AND SURYAWANSHI |
| Partner | Role in project |
|---|---|
| Shree Sarvadnya Builders and Developers | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 18 Jun 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Jun 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Jun 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 18 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed54
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupational CertificateFile: COMPLETION CERTIFICATE.pdf | 26 Mar 2026 |
| Withdrawal Update Form 1File: MR PRAKASH KALE - RERA FROM -1.pdf | 3 Mar 2026 |
| Withdrawal Update Form 2File: FORM-2.pdf | 3 Mar 2026 |
| Withdrawal Update Form 3File: Form 3 Q3.pdf | 3 Mar 2026 |
| Form 5 (FY 2024-2025)File: FORM 5-F.pdf | 24 Feb 2026 |
| Withdrawal Update Form 1File: Form-1-Q1-25-26.pdf | 7 Jan 2026 |
| Withdrawal Update Form 1File: Form-1-Q1-25-26.pdf | 7 Jan 2026 |
| Withdrawal Update Form 2File: Form-2-Q2-25-26.pdf | 7 Jan 2026 |
| Withdrawal Update Form 2File: Form-2-Q2-25-26.pdf | 7 Jan 2026 |
| Withdrawal Update Form 3File: FORM 3 q2 25-26.pdf | 7 Jan 2026 |
| Withdrawal Update Form 3File: FORM 3 q2 25-26.pdf | 7 Jan 2026 |
| Withdrawal Update Form 1File: Form-1-Q1-25-26.pdf | 6 Aug 2025 |
| Withdrawal Update Form 2File: Form-2-Q2-25-26.pdf | 6 Aug 2025 |
| Withdrawal Update Form 3File: Form 3 -Q1-25-26.pdf | 6 Aug 2025 |
| Form 1File: Form 1-Q4.pdf | 5 Aug 2025 |
| Form 2File: Form 2-Q4.pdf | 5 Aug 2025 |
| Form 3File: Form 3-Q4.pdf | 5 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Table C.pdf | 5 Aug 2025 |
| Form 1File: FORM-1.pdf | 1 Jul 2025 |
| Form 2File: FORM-2.pdf | 1 Jul 2025 |
| Form 3File: FORM-3.pdf | 1 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Table C.pdf | 1 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1-AR.pdf | 22 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3.pdf | 22 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM -2-ER.pdf | 22 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 5 Nov 2024 |
| Other - FinanceFile: Clarification Letter Land Cost.pdf | 5 Nov 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: REA51600163168.pdf | 18 Oct 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A (1).pdf | 10 Oct 2024 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B.pdf | 10 Oct 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: Disclosure of finance-To edit (1).pdf | 10 Oct 2024 |
| Proforma of Allotment letterFile: Model Form of Allotment letter_page-0001.pdf | 9 Oct 2024 |
| Other - LegalFile: One Plot One Registration-Final.pdf | 9 Oct 2024 |
| Deviation Report with respect to Allotment letterFile: Details of Deviations Revised.pdf | 9 Oct 2024 |
| Other - TechnicalFile: One Plot One Registration-Final.pdf | 9 Oct 2024 |
| Deviation Report with respect to model copy of AgreementFile: Deviation-AFS_page-0001.pdf | 9 Oct 2024 |
| Proforma of Agreement for saleFile: Shree Sarvadnya Builders and Developers_Agreement for sale-RERA.pdf | 9 Oct 2024 |
| Building plan approvalFile: BUILDING APPROVAL PLAN.pdf | 18 Jun 2024 |
| Copy of the legal title reportFile: Legal Title Report.pdf | 18 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 11FORM-1.pdf | 18 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1FORM 2.pdf | 18 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: BUILDING APPROVAL PLAN.pdf | 18 Jun 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf | 18 Jun 2024 |
| Layout approvalFile: Layout Approval.pdf | 12 Jun 2024 |
| Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Finance.pdf | 12 Jun 2024 |
| Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Legal.pdf | 12 Jun 2024 |
| Copy of Layout Approval (in case of layout)File: Layout Approval.pdf | 12 Jun 2024 |
| Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf | 12 Jun 2024 |
| CERSAI detailsFile: CERSAI details.pdf | 12 Jun 2024 |
| Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Finance.pdf | 12 Jun 2024 |
| Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Legal.pdf | 12 Jun 2024 |
| PAN CardFile: Pan Card of Firm .pdf | 11 Jun 2024 |
| Declaration in FORM BFile: Form B Builders.pdf | 11 Jun 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 11 Jun 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 54 filed documents as one ZIP, foldered, with a manifest
Keep KRUSHNA VIJAY HEIGHTS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NASHIK4,100+ in Nashik
STAR WORLD
DEEPAK KALYANJI CHANDE
VRAJ CENTRAL VISTA
DHAIRYA DEVELOPERS
ROONGTA TECHONE APARTMENT
SHREE TIRUMALA BUILDCON
VRAJ CAPITAL
KAPILAVASTU CREATORS
MAA BHAGWATI RESIDENCY APARTMENT
ROONGTA LANDMARKS LLP
THREE LEAVES PHASE ONE
DEEPAK INFRA AND HOMES PRIVATE LIMITED
See every Nashik project, with the district possession charts
Builder: Shree Sarvadnya Builders and Developers
Shree Sarvadnya Builders and Developers has 1 registration on MahaRERA, including KRUSHNA VIJAY HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if KRUSHNA VIJAY HEIGHTS is delayed beyond 22 Feb 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of KRUSHNA VIJAY HEIGHTS?
The registered promoter entity is Shree Sarvadnya Builders and Developers, a partnership as per the filing. Its GSTIN 27AFBFS3147L1ZQ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in KRUSHNA VIJAY HEIGHTS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for KRUSHNA VIJAY HEIGHTS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at KRUSHNA VIJAY HEIGHTS?
The professionals named in the filing: Architect: Ashok Jamdar; Engineer: Lab Associates; Chartered Accountant: RSPH & Associates; Chartered Accountant: M/s P N Sabadra & Associates; Chartered Accountant: Anand Kabra & Co; Chartered Accountant: KRISHNAMURTHY JAIN AND SURYAWANSHI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in KRUSHNA VIJAY HEIGHTS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback