ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / KRISHNAI VANI COMPLEX

Registration lapsed No litigation declared Others project

KRISHNAI VANI COMPLEX

By Stone House Developer

RG-MH-94691 · RERA P51700012982 · Last updated on MahaRERA portal: 6 Jan 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 3 complaints at MahaRERA
  • Completion date moved by 84 months
  • 5 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
5 of 11Construction stages donefurthest along: Internal walls, 98%
50 of 120Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 48 documents Report an error

KRISHNAI VANI COMPLEX is a Others project by Stone House Developer in Thane, Maharashtra, registered with MahaRERA as P51700012982 on 11 Sep 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 84 months from the original filing. 70 of the 120 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameKRISHNAI VANI COMPLEX
  • TypeOthers
  • Location
    • 91 2C 91 2D
    • Bhiwandi (M Corp.)
    • Bhiwandi
    • Thane
    • 421302
  • Pincode421302
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700012982
  • ReraGenie IDRG-MH-94691

Builder

  • NameStone House Developer
  • Entity typePartnership
  • PartnersZUBER ZAHEER QURESHI, ASLAM ZAHEER QURESHI, FIRDOSH MOHSIN QURESHI, ABDUL RAHIM ZAHIR QURESHI
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

10 months past promisethis monthRegisteredSep 2017First promiseDec 2018Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on11 Sep 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed48 files

Current status

58%70 of 120 units booked

Figures as on 6 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KRISHNA VANI COMPLEXNA14109228120

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 98%.

KRISHNA VANI COMPLEX: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%

Progress on shared amenities15

As on 6 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes10%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes90%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes1%
Aggregate area of recreational Open SpaceYes10%
Open ParkingYes10%

Parking filed30

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots30
Closed/Covered1
Open Space29

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,440 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
RAMAN SHANTARAM DIVEKARBhiwandi (M Corp.)Thane
PRAMOD AMRUT DIVEKARBhiwandi (M Corp.)Thane
PRABHAKAR AMRUT DIVEKARBhiwandi (M Corp.)Thane

Approvals and building plan

Sanctioning authorityBhiwandi M Corp
Permissible FSI88912.65
Proposed, not sanctioned88,913 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHIVAJI CHOWK KALYAN WEST

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectALIM ABDUL KADIR FOUZI
ArchitectFOUZI & ASSOCIATES
EngineerMAJID DHOKLE
EngineerFOUZI & ASSOCIATES
Chartered AccountantB M CHAUHAN CO
Chartered AccountantH.S. SHAH & ASSOCIATES
PartnerRole in project
Stone House Developer-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700012349Dec 2018 → Jul 2023

Reason as filed by the promoterDue to frequent lockdowns imposed by the authorities, the project was not completed on time and hence we hereby apply for one year extension i.e. 30/07/23 which is agreed and accepted by the allottees in the attached format.

EXT51700001025Dec 2018 → Dec 2019

Reason as filed by the promoterNon Availability Of Materials (Sea Sand)

EXT51700006204Dec 2018 → Dec 2021

Reason as filed by the promoterDELAY IS CAUSED DUE TO DELAY IN OBTAINING REVISED MUNICIPAL PERMISSIONS AND OBSTRUCTION OF WORK DUE TO OUTBREAK OF COVID-19 PANDEMIC

EXT51700017423Dec 2018 → Jul 2024

Reason as filed by the promoterConstruction is complete. Delay is in obtaining OC therefore extension is applied.

EXT51700028109Dec 2018 → Dec 2025

Reason as filed by the promoterchanges by authority

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC006000000055884M/s. Ketki Developers through its partner Mr. Deepak Vallabhaji DedhiaStone House Developer through its Partner Mr. Abdul Rahim Zaheer Ahmed Qureshi27/08/2018
CC006000000354519Ajit PaiAbdul Rahim Zheer Ahmed Qureshi27/02/2023
CC12604049ASHISH RANJEET JHAStone House Developer29/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Sep 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Sep 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Sep 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Sep 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed48

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2017-2018)File: FORM 5_Stonehouse_17-18.pdf6 Jan 2026
Form 5 (FY 2019-2020)File: Form 5 - 19-20 - Signed.pdf6 Jan 2026
Form 5 (FY 2021-2022)File: Form 5 - 20-21 - Signed.pdf6 Jan 2026
Form 5 (FY 2020-2021)File: Form 5 - 20-21 - Signed.pdf6 Jan 2026
Form 5 (FY 2022-2023)File: Form-5 22-23 signed.pdf6 Jan 2026
Form 5 (FY 2023-2024)File: Form-5 23-24 signed.pdf6 Jan 2026
Form 1File: Form-1 As on 30-06-24 Q1 24-25.pdf27 Sep 2025
Form 2File: Form 2 As on 30-06-24 Q1 24-25.pdf27 Sep 2025
Form 3File: FORM 3(Q 1 OF FY 2024-25).pdf27 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCOLURE OF SOLD-UNSOLD June.pdf27 Sep 2025
Form 1File: Form-1 As on 31-03-25 Q4 24-25.pdf27 Sep 2025
Form 2File: Form 2 As on 31-03-25 Q4 24-25.pdf27 Sep 2025
Form 3File: Form-3 As on 31-03-25 Q4 24-25.pdf27 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCOLURE OF SOLD AND UNSOLD Mar.pdf27 Sep 2025
Certificates of CA (Form 3)File: FORM 3.pdf1 Sep 2023
Declaration in FORM BFile: Form B.pdf31 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1.pdf31 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2.pdf31 Aug 2023
Disclosure of sold/ booked inventoryFile: Discolure of sold Inventory.pdf31 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf23 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf23 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A merged.pdf23 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form-5 21-22-Signed.pdf17 May 2023
Declaration about Commencement CertificateFile: Format - D 30-07-2022_compressed.pdf30 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_compressed.pdf30 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 2_compressed.pdf30 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 19-20_compressed.pdf30 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21_compressed.pdf30 Jul 2022
Disclosure of sold/ booked inventoryFile: Sold unsold 30-07-2022_compressed.pdf30 Jul 2022
Certificates of CA (Form 5)File: Form 5 - 19-20.pdf30 Jul 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - 19-20.pdf30 Jul 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - 20-21.pdf30 Jul 2022
CERSAI detailsFile: CERSAI Search Report.pdf8 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5_Stonehouse_18-19.pdf21 Mar 2020
Certificates of CA (Form 5)File: FORM 5_Stonehouse_17-18.pdf26 Jul 2019
Layout approvalFile: Corporation Plan Final.pdf2 Sep 2017
Building plan approvalFile: Building Plan.pdf2 Sep 2017
PAN CardFile: PAN Card.pdf2 Sep 2017
Copy of the legal title reportFile: Title Certificate.pdf2 Sep 2017
Details of encumbrancesFile: Opinion.pdf2 Sep 2017
Copy of Layout Approval (in case of layout)File: Corporation Plan Final.pdf2 Sep 2017
Building Plan Approval (IOD)File: Building Plan.pdf2 Sep 2017
Commencement Certificates / NA Order for plotted developmentFile: Bandhkam Parwana.pdf2 Sep 2017
Declaration in FORM BFile: Notary.pdf2 Sep 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate.pdf2 Sep 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate.pdf2 Sep 2017
Certificates of CA (Form 3)File: Chartered account Cerificate.pdf2 Sep 2017
Proforma of Allotment letterFile: Agreement For Sale.pdf2 Sep 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
AMRUTWANI COMPLEX TYPE A B WING A B CBHADWAD ROAD NEAR TALAV TEMGHAR BHIWANDI92CompletedNov 2014Nov 2014

How this compares with Thane

58%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 84 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KRISHNAI VANI COMPLEX on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bhiwandi (M Corp.)7,600+ in Thane

2 kmKRISHNAI VANI COMPLEXCompleted 9Lapsed / revoked 11Other 38Dot size: filed unitsN

Filed coordinates, straight-line distance. 58 registered projects within 2 km.

Builder: Stone House Developer

Stone House Developer has 2 registrations on MahaRERA, including AMRUTWANI COMPLEX D TYPE and KRISHNAI VANI COMPLEX. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that KRISHNAI VANI COMPLEX shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if KRISHNAI VANI COMPLEX is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KRISHNAI VANI COMPLEX?

The registered promoter entity is Stone House Developer, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KRISHNAI VANI COMPLEX?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against KRISHNAI VANI COMPLEX?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for KRISHNAI VANI COMPLEX?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KRISHNAI VANI COMPLEX?

The professionals named in the filing: Architect: ALIM ABDUL KADIR FOUZI; Architect: FOUZI & ASSOCIATES; Engineer: MAJID DHOKLE; Engineer: FOUZI & ASSOCIATES; Chartered Accountant: B M CHAUHAN CO; Chartered Accountant: H.S. SHAH & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KRISHNAI VANI COMPLEX?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KRISHNAI VANI COMPLEX. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KRISHNAI VANI COMPLEX to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.