Home / Browse projects / Thane, Maharashtra / KRISHNA SQUARE

Registered No litigation declared Others project

KRISHNA SQUARE

By GOPAL KRISHNA DEVELOPERS

RG-MH-34180 · RERA P51700013776 · Last updated on MahaRERA portal: 28 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 48 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jul 2027Possession promisedmoved 48 months from the original
31 of 33Construction stages doneacross 3 buildings; furthest along: Podiums (if any), 0%
93 of 254Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 114 documents Report an error

KRISHNA SQUARE is a Others project by GOPAL KRISHNA DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700013776 on 25 Oct 2017. Possession is promised by 31 Jul 2027. The completion date has moved by 48 months from the original filing. 161 of the 254 units on this registration are recorded sold or booked, and 31 of 33 construction stages are filed complete.

At a glance

Project

  • NameKRISHNA SQUARE
  • TypeOthers
  • Location
    • SHRI MALANG ROAD
    • KALYAN EAST
    • NETIVALI
    • Kalyan
    • Thane
    • 421306
  • Pincode421306
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700013776
  • ReraGenie IDRG-MH-34180

Builder

  • NameGOPAL KRISHNA DEVELOPERS
  • Entity typePartnership
  • PartnersSURESH SITARAM SONAWANE, ASHISH SURESH SONAWANE
  • Other registrations4 more →
  • Completed2 of 5
  • Declared earlier projects5 →

Key dates

this monthRegisteredOct 2017First promiseJul 2023Revised toJul 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Oct 2017
  • Promised completion31 Jul 2027
  • Revised completionRevised to 31 Jul 2027 (originally 31 Jul 2023)
  • Buildings3 building records
  • Documents filed114 files

Current status

63%161 of 254 units booked
98.5%Work done, per cost certificate

Figures as on 28 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA4314870218
WING BNA363036036
WING CNA65000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 28 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

31 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 0%.

WING A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING B100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 28 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed75

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots75
Closed/Covered75

Land and ownership25

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,850 sq m
Land owned byThe promoter, with other names on the file
Named landowners25
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 Apr 2026
LandownerVillageDistrict
SANDEEP TAWARETisgaonThane
DEEPAK J TAWARENETIVALIThane
PARWATI SHANKAR TAWARETisgaonThane
SUNITA S TAWAREPISAVALIThane
KISAN MAHADU TAWAREPISAVALIThane
KASHIBAI KALU MHATREPISAVALIThane
MANJULABAI B FULAWAREPISAVALIThane
LILABAI ANANT WAYLETisgaonThane
BANUBAI V PAWSHEPISAVALIThane
SULOCHANA KISAN SHELARPISAVALIThane
ANITA GAJANAN TAWAREPISAVALIThane
MEERA M TAWAREPISAVALIThane
NIKHIL M TAWAREPISAVALIThane
TEJASVINI TAWAREPISAVALIThane
GANESH WAKADEPISAVALIThane
GURUNATH VAKADEPISAVALIThane
NAVNATH N WAKADEPISAVALIThane
SHANKAR N WAKADEPISAVALIThane
SOMNATH N WAKADEPISAVALIThane
UJWALA NAMDEV MHATREPISAVALIThane
VANDAN A PATILPISAVALIThane
SUMAN JAGANNATH TAWAREPISAVALIThane
VASUDEV WAMAN BHOIRPISAVALIThane
TRIMBAK DHAMI BHOIRPISAVALIThane
ANJANA TRIMBAK BHOIRPISAVALIThane

Approvals and building plan

Sanctioning authorityKDMC
Permissible FSI9655.0
Proposed, not sanctioned2,965 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKalyan
Estimated costRs 50.00 cr
Cost incurredRs 49.25 cr
Work done98.5%
BuildingWingEstimatedIncurred
WING ANARs 15.17 crRs 14.96 cr
WING BNARs 15.17 crRs 14.96 cr
WING CNARs 15.17 crRs 14.96 cr
-NARs 4.50 crRs 4.37 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDILIP TAMBDAY AND ASSOCIATES
EngineerVINAYAK CHOPDEKAR
EngineerPradnya Ashok Ahire
Chartered AccountantPooja V Jain & Co
PartnerRole in project
GOPAL KRISHNA DEVELOPERS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700017202Jul 2023 → Jul 2024

Reason as filed by the promoterRespected Sir, We are applying for extension due to following reasons: a) Due to COVID-19 pandemic, the regular flow of work is hampered on account of unavailability of labour on regular basis. b) Construction of Wing A is completed and we have obtained completion certificate from Kalyan Dombivali Municipal Corporation dated 01.09.2018. Construction of Wing B is in process and we have obtained part occupancy certificate from Kalyan Dombivali Municipal Corporation dated 24.08.2022. c) Construction of Wing C is in process and will be handed over to Kalyan Dombivali Municipal Corporation. We requ

EXT51700025537Jul 2023 → Jul 2026

Reason as filed by the promoterThe delay was caused by unforeseen circumstances beyond our control. Despite our best efforts, we were unable to complete the project within the stipulated timeline. Therefore, we request an extension until 30 July 2026.

EA28072621902Jul 2023 → Jul 2027

Reason as filed by the promoterThe project could not be completed within the originally registered timeline due to a combination of unforeseen and practical challenges encountered during the course of execution. The construction activities were adversely affected by fluctuations in the availability and cost of construction materials, shortage of skilled labour, and delays in the mobilization of contractors and other agencies involved in the project. These factors impacted the planned construction schedule and resulted in slower progress than originally anticipated. In addition, certain activities requiring coordination with

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Mar 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Sep 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jul 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 5 Nov 2024

Documents filed114

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 114 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf28 Jul 2026
Withdrawal Update Form 2File: Form 2.pdf28 Jul 2026
Withdrawal Update Form 3File: Form 3 (1)_compressed.pdf28 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A FY 25-26.pdf28 Jul 2026
Withdrawal Update Form 1File: SQUARE ARCHITECT CERFICATE 4TH QTR 2025-26.pdf27 Apr 2026
Withdrawal Update Form 2File: SQUARE ENGINEER CERFICATE 4TH QTR 2025-26.pdf27 Apr 2026
Withdrawal Update Form 3File: SQUARE CA CERFICATE 4TH QTR 2025-26.pdf27 Apr 2026
Withdrawal Update Form 1File: ks architect ceirtificate third qtr 25-26.pdf27 Jan 2026
Withdrawal Update Form 2File: KS - engineer certificte second qtr 25-26.pdf27 Jan 2026
Withdrawal Update Form 3File: ks ca ceirtificate third qtr 25-26.pdf27 Jan 2026
Form 5 (FY 2024-2025)File: Form 5 (24-25) KS.pdf22 Dec 2025
Withdrawal Update Form 1File: Form 1 Square.pdf4 Dec 2025
Withdrawal Update Form 1File: Form 1 Square.pdf4 Dec 2025
Withdrawal Update Form 1File: KS - architect certificte second qtr 25-26.pdf4 Dec 2025
Withdrawal Update Form 2File: Form 2 Square.pdf4 Dec 2025
Withdrawal Update Form 2File: Form 2 Square.pdf4 Dec 2025
Withdrawal Update Form 2File: KS - engineer certificte second qtr 25-26.pdf4 Dec 2025
Withdrawal Update Form 3File: Form 3 Square.pdf4 Dec 2025
Withdrawal Update Form 3File: Form 3 Square.pdf4 Dec 2025
Withdrawal Update Form 3File: KS - ca certificte second qtr 25-26.pdf4 Dec 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Square Mar 25 (1).pdf17 Apr 2025
Certificates of CA (Form 3)File: Form 3 Square Mar 25 (1).pdf17 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: krishna square engineer certificate.pdf17 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: From 1 Square Dec 24.pdf27 Jan 2025
Certificates of CA (Form 3)File: Form 3 Square Dec 24.pdf27 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Square Dec 24.pdf27 Jan 2025
Declaration in FORM BFile: Form B.pdf14 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 01.pdf14 Dec 2024
Certificates of CA (Form 3)File: Form 03.pdf14 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 02.pdf14 Dec 2024
Disclosure of sold/ booked inventoryFile: Sold Booked.pdf14 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf14 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 KS 23-24.pdf18 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Square Architect.pdf18 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Square.pdf18 Nov 2024
Certificates of CA (Form 3)File: Form 3 Square (1).pdf18 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Square Architect.pdf18 Nov 2024
Certificates of CA (Form 3)File: Form 3 Square (1).pdf18 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Square.pdf18 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 KS 23-24.pdf18 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: KRISHNA SQAURE OC.pdf5 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Square Architect.pdf26 Oct 2024
Certificates of CA (Form 3)File: Form 3 Square (1).pdf26 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Square.pdf26 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KS-ARCHITECT LATTER.pdf10 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KS-ENGINEERS CERTIFICATE.pdf10 May 2024
Certificates of CA (Form 3)File: KS-CA CERTIFICATE.pdf10 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Square 22-23.pdf2 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 KS.pdf21 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 KS.pdf21 Oct 2023
Certificates of CA (Form 3)File: Form 3 KS Sep 23.pdf21 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: KS REVISED FLAT CC.pdf25 Jul 2023
Declaration about Commencement CertificateFile: Form D-Krishna Square.pdf25 Jul 2023
Declaration in FORM BFile: Form B - Krishna Square_rotated.pdf25 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A- Krishna Square March 2020_rotated.pdf25 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A- Krishna Square March 2021_rotated.pdf25 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A- Krishna Square March 2022_rotated.pdf25 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A- Krishna Square March 2023_rotated.pdf25 Jul 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory- Krishna Square_rotated.pdf25 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 KS.pdf24 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: KS 17-18.pdf5 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: KS 18-19.pdf5 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: KS 19-20.pdf5 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: KS 20-21.pdf5 Mar 2022
Details of encumbrancesFile: Encumbrance Letter.pdf29 Dec 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Krishna Square Architect Certificate.pdf23 Oct 2021
Certificates of CA (Form 3)File: FORM_3__KS (1).pdf23 Oct 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: oc.pdf23 Oct 2021
Layout approvalFile: MYSCAN_20210326_0001.pdf27 Mar 2021
Layout approvalFile: MYSCAN_20210326_0002.pdf27 Mar 2021
Layout approvalFile: MYSCAN_20210326_0003.pdf27 Mar 2021
Layout approvalFile: MYSCAN_20210326_0004.pdf27 Mar 2021
Layout approvalFile: MYSCAN_20210326_0005.pdf27 Mar 2021
Copy of Layout Approval (in case of layout)File: MYSCAN_20210326_0001.pdf27 Mar 2021
Copy of Layout Approval (in case of layout)File: MYSCAN_20210326_0002.pdf27 Mar 2021
Copy of Layout Approval (in case of layout)File: MYSCAN_20210326_0003.pdf27 Mar 2021
Copy of Layout Approval (in case of layout)File: MYSCAN_20210326_0004.pdf27 Mar 2021
Copy of Layout Approval (in case of layout)File: MYSCAN_20210326_0005.pdf27 Mar 2021
Commencement Certificates / NA Order for plotted developmentFile: KS CC 29th Floor.pdf27 Mar 2021
Layout approvalFile: KS 24 Floor (1).pdf11 Jul 2019

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise4 delivered late
ProjectLocationFlatsStatusPromisedDelivered
KRISHNA PARADISE PHASE I100 FT ROAD TISGAON KALYAN EAST236CompletedMay 2016Late, Jul 2017
KRISHNA HEIGHT100FT ROAD TISGAON KALYAN EAST154CompletedJan 2016Late, May 2016
GOPAL KRISHNA PARK PHASE IIHAJI MALANG ROAD KALYAN EAST83CompletedJun 2007Late, Jul 2008
GOPAL KRISHNA PARK PHASE I100 FT ROAD TISGAON KALYAN EAST196CompletedDec 2004Late, Dec 2004
RADHE KRISHNA PARKHAJI MALANG ROAD196CompletedApr 2004Apr 2004

How this compares with Thane

63%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 48 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KRISHNA SQUARE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KALYAN EAST7,600+ in Thane

2 kmKRISHNA SQUARECompleted 58Lapsed / revoked 41Other 100Dot size: filed unitsN

Filed coordinates, straight-line distance. 199 registered projects within 2 km.

Builder: GOPAL KRISHNA DEVELOPERS

GOPAL KRISHNA DEVELOPERS has 5 registrations on MahaRERA, including KRISHNA NISARGA and KRISHNA PARADISE. Its filings disclose 5 earlier MahaRERA projects: declares 1 of 5 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if KRISHNA SQUARE is delayed beyond 31 Jul 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KRISHNA SQUARE?

The registered promoter entity is GOPAL KRISHNA DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KRISHNA SQUARE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KRISHNA SQUARE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KRISHNA SQUARE?

The professionals named in the filing: Architect: DILIP TAMBDAY AND ASSOCIATES; Engineer: VINAYAK CHOPDEKAR; Engineer: Pradnya Ashok Ahire; Chartered Accountant: Pooja V Jain & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KRISHNA SQUARE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KRISHNA SQUARE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KRISHNA SQUARE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.