Registration lapsed No litigation declared Residential / Group Housing project

Komal

By SRKD LANDMARK LLP

RG-MH-75174 · RERA P52100047236 · Last updated on MahaRERA portal: 16 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Completion date moved by 17 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
8 of 11Construction stages donefurthest along: Basement (if any), 0%
10 of 14Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 122 documents Report an error

Komal is a Residential / Group Housing project by SRKD LANDMARK LLP in Pune, Maharashtra, registered with MahaRERA as P52100047236 on 12 Oct 2022. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 17 months from the original filing. 4 of the 14 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • NameKomal
  • TypeResidential / Group Housing
  • Location
    • Near Rajaram Bridge
    • Karvenagar
    • Karve Nagar
    • Haveli
    • Pune
    • 411052
  • Pincode411052
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100047236
  • ReraGenie IDRG-MH-75174

Builder

  • NameSRKD LANDMARK LLP
  • Entity typePartnership
  • PartnerSanjay Ramchandra Kulkarni
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked
  • Past their filed date1

Key dates

4 months past promisethis monthRegisteredOct 2022First promiseJan 2025Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on12 Oct 2022
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 31 Jan 2025)
  • Buildings1 building record
  • Documents filed122 files

Current status

29%4 of 14 units booked
100.0%Work done, per cost certificate

Figures as on 16 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KomalNA5514014

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

Komal: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 16 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed9

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots9
Closed/Covered9

Land and ownership13

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area500 sq m
Land owned byThe promoter, with other names on the file
Named landowners13
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on29 Jul 2025
LandownerVillageDistrict
Yashwant DhavalikarKarve NagarPune
Mr. Ajit Shripad GadgilKarve NagarPune
Mrs. Shobhana Ajit GadgilKarve NagarPune
Nandkumar Shantaram SagvekarKarve NagarPune
Mr. Charudatta Bhalchandra sathayeKarve NagarPune
Mrs. Vasumati Charudatta SathayeKarve NagarPune
Mr. Sachin Vithalrao NaikKarve NagarPune
Mr. Shailesh Onkar PatilKarve NagarPune
Mrs. Manjusha Shailesh PatilKarve NagarPune
Mr. Vijay Sitaram RajaneKarve NagarPune
Mrs. Harshala Rajan NaikKarve NagarPune
Smt. Sheetal Shrikant BorgaonkarKarve NagarPune
Miss Isha Shrikant BorgaonkarKarve NagarPune

Approvals and building plan

Sanctioning authorityPune Muncipal Corporation
Permissible FSI909.16
Proposed, not sanctioned909 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDeccan Gymkhana
Estimated costRs 2.64 cr
Cost incurredRs 2.64 cr
Work done100.0%
BuildingWingEstimatedIncurred
KomalNARs 2.64 crRs 2.64 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDEVENDRA V. DHERE
EngineerSatish Marathe Consulting Engineers
EngineerSagar Rathod
Chartered AccountantCA Pushpa Bogati
Chartered AccountantS P A K & Co
PartnerRole in project
SRKD LANDMARK LLP-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100027364Jan 2025 → Jul 2025

Reason as filed by the promoterI was planning to expand the project, but there was a delay in receiving the sanction plan from the local authority. This setback has postponed our project timeline as we need the official approval to proceed with the expansion.

EA16082502384Jan 2025 → Dec 2025

Reason as filed by the promoter1. LACK OF LABOUR 2. NON AVAILIBILITY OF MATERIAL 3. DELAY IN REVISED SANCTION

EA16012619472Jan 2025 → Jun 2026

Reason as filed by the promoterWe have already applied for the Occupancy Certificate to the planning authority i.e. Pune Municipal Corporation in the month of September 2025 but we could not get the OC till now due to some unavoidable circumstances.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Aug 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Aug 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Aug 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed122

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 122 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2022-2023)File: Komal Form 2A 22-23_11zon.pdf16 May 2026
Form 2A (FY 2023-2024)File: Komal Form 2A 23-24_11zon.pdf16 May 2026
Form 2A (FY 2024-2025)File: Komal Form 2A 24 -25_11zon.pdf16 May 2026
Form 5 (FY 2022-2023)File: Komal Form 5 22-23_11zon.pdf16 May 2026
Form 5 (FY 2023-2024)File: Komal Form 5 23-24_11zon.pdf16 May 2026
Withdrawal Update Form 1File: form 1 _komal _mar 26.pdf22 Apr 2026
Withdrawal Update Form 2File: form 2 _komal _mar 26.pdf22 Apr 2026
Withdrawal Update Form 3File: form 3 _komal _mar 26.pdf22 Apr 2026
Withdrawal Update Form 1File: Form 1_Komal_Dec25.pdf9 Mar 2026
Withdrawal Update Form 2File: Form 2_Komal_Dec25.pdf9 Mar 2026
Withdrawal Update Form 3File: FORM 3 KOMAL_DEC25_compressed.pdf9 Mar 2026
Withdrawal Update Form 1File: Form 1 Qtr 2 2025 Komal.pdf17 Nov 2025
Withdrawal Update Form 2File: Form 2 Qtr 2 2025_2 Komal.pdf17 Nov 2025
Withdrawal Update Form 3File: Form 3 Qtr 2 2025 Komal.pdf17 Nov 2025
Form 5 (FY 2024-2025)File: Form 5 Y- 2025-26_Komal.pdf8 Oct 2025
Form 1File: Dec 22.pdf31 Jul 2025
Form 2File: Form 2 Komal Dec 22.pdf31 Jul 2025
Form 3File: Komal Dec-22.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: 1 Sold Disclosure Dec 22.pdf31 Jul 2025
Form 1File: Dec 22.pdf31 Jul 2025
Form 2File: Form 2 Komal Mar 23.pdf31 Jul 2025
Form 3File: Komal Mar-23.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: 2 Disclosure Komal Mar 23.pdf31 Jul 2025
Form 1File: Jun 23.pdf31 Jul 2025
Form 2File: Form 2 Komal Jun23.pdf31 Jul 2025
Form 3File: Komal Jun-23 n.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: 3 Disclosure Komal June 23.pdf31 Jul 2025
Form 1File: Sep 23.pdf31 Jul 2025
Form 2File: Form 2- Sep 2023.PDF31 Jul 2025
Form 3File: Form 3 - Sep 2023.PDF31 Jul 2025
Disclosure of Sold and Booked InventoryFile: 4 Disclosure Komal Sept 23.pdf31 Jul 2025
Form 1File: Form 1- Dec 2023.PDF31 Jul 2025
Form 2File: Form 2- Dec 2023.PDF31 Jul 2025
Form 3File: Komal Dec-23.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: 5 Disclosure Komal Dec23.pdf31 Jul 2025
Form 1File: Form 1- Mar 2024.PDF31 Jul 2025
Form 2File: Form 2- Mar 2024.PDF31 Jul 2025
Form 3File: 6 Disclosure Komal Mar 24.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: 6 Disclosure Komal Mar 24.pdf31 Jul 2025
Form 1File: Form-1 Komal-Jun-24.PDF31 Jul 2025
Form 2File: Form 2 - Jun 24.PDF31 Jul 2025
Form 3File: Komal Jun-24.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: 7 Disclosure Komal June 24.pdf31 Jul 2025
Form 1File: Form 1 -Sep 2024.PDF31 Jul 2025
Form 2File: Form 2 Komal Sep 24.pdf31 Jul 2025
Form 3File: Komal Sep-24.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: 8 Disclosure Komal Sep 24.pdf31 Jul 2025
Form 1File: FORM 1 - DEC 2024.PDF31 Jul 2025
Form 2File: Form 2_December 2024.PDF31 Jul 2025
Form 3File: Komal Dec-24.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: 9 Disclosure Komal Dec 24.pdf31 Jul 2025
Form 1File: Komal Form 1 Mar 25.pdf31 Jul 2025
Form 2File: Komal Form 2 Mar 25n.pdf31 Jul 2025
Form 3File: KOMAL F3 Mar-25 Signed.pdf31 Jul 2025
Disclosure of Sold and Booked InventoryFile: 10 Komal Disclosure March 2024-25.pdf31 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Komal form 3 march 25.pdf29 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Komal Form 2 Mar 25 compressed.pdf28 Apr 2025
Declaration in FORM BFile: FORM B Komal.pdf26 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Komal Form 1 Mar 25.pdf26 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KOMAL F3 Mar-25.pdf26 Apr 2025
Disclosure of sold/ booked inventoryFile: 10 Komal Disclosure March 2024-25.pdf26 Apr 2025
Disclosure of sold/ booked inventoryFile: 1 Sold Disclosure Dec 22.pdf21 Apr 2025
Disclosure of sold/ booked inventoryFile: 2 Disclosure Komal Mar 23.pdf21 Apr 2025
Disclosure of sold/ booked inventoryFile: 3 Disclosure Komal June 23.pdf21 Apr 2025
Disclosure of sold/ booked inventoryFile: 4 Disclosure Komal Sept 23.pdf21 Apr 2025
Disclosure of sold/ booked inventoryFile: 5 Disclosure Komal Dec23.pdf21 Apr 2025
Disclosure of sold/ booked inventoryFile: 6 Disclosure Komal Mar 24.pdf21 Apr 2025
Disclosure of sold/ booked inventoryFile: 7 Disclosure Komal June 24.pdf21 Apr 2025
Disclosure of sold/ booked inventoryFile: 8 Disclosure Komal Sep 24.pdf21 Apr 2025
Disclosure of sold/ booked inventoryFile: 9 Disclosure Komal Dec 24.pdf21 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Komal Form 2A 2023.pdf17 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Komal Form 5 2023.pdf17 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Komal Form 2A 2024.pdf17 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Komal Form 5 2024.pdf17 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Komal-Jun-24.PDF16 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Komal Dec-22.pdf16 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Komal Mar-23.pdf16 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Komal Dec-23.pdf16 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Komal Sep-24.pdf16 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Komal Jun-23_compressed.pdf16 Apr 2025

How this compares with Pune

29%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 17 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Komal on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Karvenagar13,700+ in Pune

2 kmKomalCompleted 52Lapsed / revoked 34Other 83Dot size: filed unitsN

Filed coordinates, straight-line distance. 169 registered projects within 2 km.

Builder: SRKD LANDMARK LLP

SRKD LANDMARK LLP has 2 registrations on MahaRERA, including Komal and Vallabh Co-op Housing Society. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Komal shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Komal is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Komal?

The registered promoter entity is SRKD LANDMARK LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Komal?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Komal?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Komal?

The professionals named in the filing: Architect: DEVENDRA V. DHERE; Engineer: Satish Marathe Consulting Engineers; Engineer: Sagar Rathod; Chartered Accountant: CA Pushpa Bogati; Chartered Accountant: S P A K & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Komal?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Komal. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Komal to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.