Home / Browse projects / Pune, Maharashtra / River Dale Residency
River Dale Residency
By Maha Anand Pinnac Associates
RG-MH-20181 · RERA P52100004952 · Last updated on MahaRERA portal: 9 Dec 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 14 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 38 months
- 5 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
River Dale Residency is a Residential / Group Housing project by Maha Anand Pinnac Associates in Pune, Maharashtra, registered with MahaRERA as P52100004952 on 9 Aug 2017. Possession was promised by 31 Aug 2025 and is now 14 months past that date. The completion date has moved by 38 months from the original filing. 147 of the 227 units on this registration are recorded sold or booked, and 37 of 55 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameRiver Dale Residency
- TypeResidential / Group Housing
- Location
- Rajaram Bridge to Cummins Collage Road
- Karvenagar
- Karve Nagar
- Haveli
- Pune
- 411052
- Pincode411052
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100004952
- ReraGenie IDRG-MH-20181
Builder
- NameMaha Anand Pinnac Associates
- Entity typePartnership
- PartnersVISHAL VILAS JAIN, DINESH VASANT CHANDRATRE
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on9 Aug 2017
- Promised completion31 Aug 2025
- Revised completionRevised to 31 Aug 2025 (originally 30 Jun 2022)
- Buildings5 building records
- Documents filed337 files
Current status
Figures as on 9 Dec 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing A | NA | 20 | 16 | 80 | 0 | 80 |
| Wing D | NA | 5 | 5 | 22 | 0 | 22 |
| Wing B | NA | 20 | 16 | 61 | 0 | 61 |
| Wing C | NA | 20 | 16 | 64 | 0 | 64 |
| Wing E | NA | 3 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 9 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
37 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is External plumbing and external plaster, at 100%.
Wing A100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 98% |
| Sanitary Fittings within the flats / premises | 98% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 99% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing D82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing B100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing C100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 98% |
| Sanitary Fittings within the flats / premises | 98% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing E16%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 75% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 9 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 80% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 0% |
Parking filed373
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Wing A | 144 | 5 | 149 |
| Wing D | 11 | 0 | 11 |
| Wing B | 67 | 4 | 71 |
| Wing C | 128 | 5 | 133 |
| Wing E | 9 | 0 | 9 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Wing A | NA | Rs 30.90 cr | Rs 24.72 cr |
| Wing C | NA | Rs 26.93 cr | Rs 24.24 cr |
| Wing B | NA | Rs 19.19 cr | Rs 18.23 cr |
| - | NA | Rs 5.47 cr | Rs 4.11 cr |
| Wing D | NA | Rs 4.02 cr | Rs 3.94 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Pinnac Consulting Pvt Ltd |
| Engineer | Sunil Mutalik and Associates |
| Engineer | NITIN SUDHAKAR PARGAONKAR |
| Chartered Accountant | PRAKASH WALGUDE AND ASSOCIATES |
| Chartered Accountant | KUMAR MULAY AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| Maha Anand Pinnac Associates | - |
Extensions applied for5
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe delay has been caused due to a) Due to delay in receipt of Aviation NOC. The application for Aviation NOC was made on the basis of the circular issued by the Ministry of Defence dated 11.04.2018 and Aviation NOC was received on 28.11.2019 b) Due to present COVID 19 Pandemic c) Due to shortage of migrant labour and d) Due to change in management structure
Reason as filed by the promoterThe project is getting completed and we are filing for Occupancy Certificate hence require Extension
Reason as filed by the promoterThe project is 95% completed and development work is in process. We have also applied for completion certificate, however we are not sure we will receive in time and need extension.
Reason as filed by the promoterDear Sir/Madam, We are pleased to inform you that our project name “River Dale Residency”, Karvenagar, Pune - 411052, is almost complete and we have received Part Completion for the project from the Pune Municipal Corporation vide No. OCC/0994/24 dated 22.11.2024 (A copy of the same is uploaded on the MahaRERA website). The balance construction activities are almost complete and we have applied for the Completion Certificate for the balance flats to the Pune Municipal Corporation. We also agree to do the quarterly compliance as and when required. Therefore, we request an extension for obtainin
Reason as filed by the promoterThe said project is almost completed and we have received part completion for the project from Pune Municipal Corporation vide no. OCC/0994/24 dated 22/11/2024 and OCC/1088/24 dated 24/12/2024. Out of 227 flats we have received Occupancy Certificate for 216 flats. Whereas remaining 11 flats are pending due to the the owner's Architect / interior designers. They are constructing the flats as per their requirement and hence the delay in getting full occupancy certificate. Request you to grant us the extension as soon as possible so that we can proceed for Final Occupancy Certificate once these 1
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000269625 | Mr. Gorakhnath Narayan Bhalekar | M/s Maha Anand Pinnac Associates through its Partners a)Dinesh Vasant Chandratre b)Vishal Vilas Jain | 20/10/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Mar 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Apr 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Apr 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 27 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 10 Feb 2025
Documents filed337
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 337 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2024-2025)File: Certificate 8 - Form 2A - RDR FY24-25.pdf | 9 Dec 2025 |
| Form 2A (FY 2017-2018)File: Certificate 1 - Form 2A - RDR FY17-18.pdf | 9 Dec 2025 |
| Form 2A (FY 2018-2019)File: Certificate 2 - Form 2A - RDR FY18-19.pdf | 9 Dec 2025 |
| Form 2A (FY 2019-2020)File: Certificate 3 - Form 2A - RDR FY19-20.pdf | 9 Dec 2025 |
| Form 2A (FY 2020-2021)File: Certificate 4 - Form 2A - RDR FY20-21.pdf | 9 Dec 2025 |
| Form 2A (FY 2021-2022)File: Certificate 5 - Form 2A - RDR FY21-22.pdf | 9 Dec 2025 |
| Form 2A (FY 2022-2023)File: Certificate 6 - Form 2A - RDR FY22-23.pdf | 9 Dec 2025 |
| Form 2A (FY 2023-2024)File: Certificate 7 - Form 2A - RDR FY23-24.pdf | 9 Dec 2025 |
| Withdrawal Update Form 1File: RDR - FORM 1 FY25-26 Q2.pdf | 8 Dec 2025 |
| Withdrawal Update Form 2File: RDR - FORM 2 FY25-26 Q2.pdf | 8 Dec 2025 |
| Withdrawal Update Form 3File: RDR - FORM 3 FY25-26 Q2.pdf | 8 Dec 2025 |
| Form 5 (FY 2023-2024)File: Form 5 RDR - 2023-24.pdf | 8 Dec 2025 |
| Form 5 (FY 2022-2023)File: Form 5 RDR - 2022-23.pdf | 8 Dec 2025 |
| Withdrawal Update Form 1File: RDR - FORM 1 FY25-26 Q2.pdf | 5 Nov 2025 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate -30062025.pdf | 5 Nov 2025 |
| Withdrawal Update Form 2File: RDR - FORM 2 FY25-26 Q2.pdf | 5 Nov 2025 |
| Withdrawal Update Form 2File: RDR - FORM 2 FY25-26 Q1.pdf | 5 Nov 2025 |
| Withdrawal Update Form 3File: RDR - FORM 3 FY25-26 Q2.pdf | 5 Nov 2025 |
| Withdrawal Update Form 3File: Form 3 CA Certificate 30062025.pdf | 5 Nov 2025 |
| Form 5 (FY 2024-2025)File: MAPA-From-5-2024-2025_0001.pdf | 5 Nov 2025 |
| Declaration in FORM BFile: EXT Form B Declaration - Affidavit cum Declaration - 30062025-1.pdf | 29 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate -31032025.pdf | 29 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate 31032025.pdf | 29 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 31032025.pdf | 29 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Declaration-Sold Unsold Inventory 31032025.pdf | 29 Apr 2025 |
| Certificates of CA (Form 3)File: Form-3- RDR Q3.pdf | 12 Mar 2025 |
| Declaration in FORM BFile: Form B 30042025.pdf | 3 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Declaration-Sold Unsold Inventory New-1.pdf | 3 Mar 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: COMPLETION 2nd Part.pdf | 10 Feb 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: From 4 Architect Certificate.pdf | 6 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate.pdf | 6 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 RDR - 2023-24.pdf | 6 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Architect Certitificate.pdf | 3 Feb 2025 |
| Certificates of CA (Form 3)File: Form-3-PPG.pdf | 3 Feb 2025 |
| Declaration in FORM BFile: 5-1.pdf | 27 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RDR - Form 1.pdf | 26 Dec 2024 |
| Certificates of CA (Form 3)File: RDR - Form 3 - Dec 2024.pdf | 26 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RDR - Form 2 - Dec 2024.pdf | 26 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: RDR - Sold Unsold.pdf | 26 Dec 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: RDR - Part Completion Certificate.pdf | 25 Dec 2024 |
| Declaration in FORM BFile: River Dale Residency - Form B 30122024.pdf | 7 Nov 2024 |
| Certificates of CA (Form 3)File: C A Certificate.pdf | 21 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Booked Inventary.pdf | 21 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 18 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3.pdf | 18 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 18 Oct 2024 |
| Declaration in FORM BFile: Form B.pdf | 7 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf | 20 Jun 2024 |
| CERSAI detailsFile: 14 No Cersai report.pdf | 20 Jun 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 24 Annexure A - Disclosure - VJ.pdf | 20 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - 23-24_compressed.pdf | 18 Jun 2024 |
| Declaration about Commencement CertificateFile: Declaration about Commencement Certificate (Format - D).pdf | 15 Jun 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A - Disclosure of Intrest in other Real Estate Organization_0001.pdf | 15 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 2A - 23-24_compressed.pdf | 15 Jun 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A - Declaration about Separate Bank Account for Real Estate Project_0001.pdf | 15 Jun 2024 |
| Deviation Report with respect to Allotment letterFile: Deviation Report with Respect to Model Copy of Allotment Letter_0001.pdf | 15 Jun 2024 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report with Respect to Model Copy of Agreement for Sale_0001.pdf | 15 Jun 2024 |
| Declaration in FORM BFile: Form B - RDR - June 2024.pdf | 13 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf | 7 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 RDR - 2022-23.pdf | 6 May 2024 |
| Building plan approvalFile: plan 03-25.pdf | 27 Apr 2024 |
| Building plan approvalFile: plan 04-25.pdf | 27 Apr 2024 |
| Building plan approvalFile: plan 05-25.pdf | 27 Apr 2024 |
| Building plan approvalFile: plan 06-25.pdf | 27 Apr 2024 |
| Building plan approvalFile: plan 07-25.pdf | 27 Apr 2024 |
| Building plan approvalFile: plan 08-25.pdf | 27 Apr 2024 |
| Building plan approvalFile: plan 09-25.pdf | 27 Apr 2024 |
| Building plan approvalFile: plan 10-25.pdf | 27 Apr 2024 |
| Building plan approvalFile: plan 11-25.pdf | 27 Apr 2024 |
| Building plan approvalFile: plan 12-25.pdf | 27 Apr 2024 |
| Building plan approvalFile: plan 13-25.pdf | 27 Apr 2024 |
| Building plan approvalFile: plan 14-25.pdf | 27 Apr 2024 |
| Building plan approvalFile: plan 15-25.pdf | 27 Apr 2024 |
| Building plan approvalFile: plan 16-25.pdf | 27 Apr 2024 |
| Building plan approvalFile: plan 17-25.pdf | 27 Apr 2024 |
| Building plan approvalFile: plan 18-25.pdf | 27 Apr 2024 |
| Building plan approvalFile: plan 19-25.pdf | 27 Apr 2024 |
| Building plan approvalFile: plan 20-25.pdf | 27 Apr 2024 |
| Building plan approvalFile: plan 21-25.pdf | 27 Apr 2024 |
| Building plan approvalFile: plan 22-25.pdf | 27 Apr 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 337 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep River Dale Residency on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Karvenagar13,700+ in Pune
Filed coordinates, straight-line distance. 147 registered projects within 2 km.
LE SKYLARK
KAKADE GREEN ESTATES PRIVATE LIMITED
Studio06
KARVENAGAR STUDIO LLP
1 GOLDLEAF
GOLDLEAF REALTORS
G M Mahika
G M DEVELOPERS
SIDDHIVINAYAK RESIDENCY
KELKAR PINNAC HOUSING LLP
GOMATI NARMADA CHSL
Kotibhaskar Infrastructures &Developers Pv
Builder: Maha Anand Pinnac Associates
Maha Anand Pinnac Associates has 1 registration on MahaRERA, including River Dale Residency. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that River Dale Residency shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if River Dale Residency is delayed beyond 31 Aug 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of River Dale Residency?
The registered promoter entity is Maha Anand Pinnac Associates, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in River Dale Residency?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against River Dale Residency?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for River Dale Residency?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at River Dale Residency?
The professionals named in the filing: Architect: Pinnac Consulting Pvt Ltd; Engineer: Sunil Mutalik and Associates; Engineer: NITIN SUDHAKAR PARGAONKAR; Chartered Accountant: PRAKASH WALGUDE AND ASSOCIATES; Chartered Accountant: KUMAR MULAY AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in River Dale Residency?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback