ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / River Dale Residency

Registration lapsed No litigation declared Residential / Group Housing project

River Dale Residency

By Maha Anand Pinnac Associates

RG-MH-20181 · RERA P52100004952 · Last updated on MahaRERA portal: 9 Dec 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 14 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 38 months
  • 5 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Aug 2025Possession promised14 months past this date
37 of 55Construction stages doneacross 5 buildings; furthest along: External plumbing and external plaster, 100%
80 of 227Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 337 documents Report an error

River Dale Residency is a Residential / Group Housing project by Maha Anand Pinnac Associates in Pune, Maharashtra, registered with MahaRERA as P52100004952 on 9 Aug 2017. Possession was promised by 31 Aug 2025 and is now 14 months past that date. The completion date has moved by 38 months from the original filing. 147 of the 227 units on this registration are recorded sold or booked, and 37 of 55 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameRiver Dale Residency
  • TypeResidential / Group Housing
  • Location
    • Rajaram Bridge to Cummins Collage Road
    • Karvenagar
    • Karve Nagar
    • Haveli
    • Pune
    • 411052
  • Pincode411052
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100004952
  • ReraGenie IDRG-MH-20181

Builder

  • NameMaha Anand Pinnac Associates
  • Entity typePartnership
  • PartnersVISHAL VILAS JAIN, DINESH VASANT CHANDRATRE

Key dates

14 months past promisethis monthRegisteredAug 2017First promiseJun 2022Revised toAug 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Aug 2017
  • Promised completion31 Aug 2025
  • Revised completionRevised to 31 Aug 2025 (originally 30 Jun 2022)
  • Buildings5 building records
  • Documents filed337 files

Current status

65%147 of 227 units booked
87.0%Work done, per cost certificate

Figures as on 9 Dec 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing ANA201680080
Wing DNA5522022
Wing BNA201661061
Wing CNA201664064
Wing ENA30000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 9 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

37 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is External plumbing and external plaster, at 100%.

Wing A100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.99%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing D82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing B100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing C100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing E16%
ActivityProgress
Excavation100%
Basement (if any)75%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 9 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes80%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes0%

Parking filed373

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots373
Closed/Covered359
Open Space14
BuildingClosed/CoveredOpen SpaceTotal
Wing A1445149
Wing D11011
Wing B67471
Wing C1285133
Wing E909

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area7,458 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on24 Sep 2024

Approvals and building plan

Sanctioning authorityPUNE MUNICIPAL CORPORATION
Permissible FSI21076.37
Proposed, not sanctioned9,588 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAbhishek Complex Happy Colony Kothrud Pune 411029
Estimated costRs 86.50 cr
Cost incurredRs 75.23 cr
Work done86.97%
BuildingWingEstimatedIncurred
Wing ANARs 30.90 crRs 24.72 cr
Wing CNARs 26.93 crRs 24.24 cr
Wing BNARs 19.19 crRs 18.23 cr
-NARs 5.47 crRs 4.11 cr
Wing DNARs 4.02 crRs 3.94 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPinnac Consulting Pvt Ltd
EngineerSunil Mutalik and Associates
EngineerNITIN SUDHAKAR PARGAONKAR
Chartered AccountantPRAKASH WALGUDE AND ASSOCIATES
Chartered AccountantKUMAR MULAY AND ASSOCIATES
PartnerRole in project
Maha Anand Pinnac Associates-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100006333Jun 2022 → Dec 2023

Reason as filed by the promoterThe delay has been caused due to a) Due to delay in receipt of Aviation NOC. The application for Aviation NOC was made on the basis of the circular issued by the Ministry of Defence dated 11.04.2018 and Aviation NOC was received on 28.11.2019 b) Due to present COVID 19 Pandemic c) Due to shortage of migrant labour and d) Due to change in management structure

EXT52100023004Jun 2022 → Sep 2024

Reason as filed by the promoterThe project is getting completed and we are filing for Occupancy Certificate hence require Extension

EXT52100024790Jun 2022 → Dec 2024

Reason as filed by the promoterThe project is 95% completed and development work is in process. We have also applied for completion certificate, however we are not sure we will receive in time and need extension.

EXT52100025862Jun 2022 → Apr 2025

Reason as filed by the promoterDear Sir/Madam, We are pleased to inform you that our project name “River Dale Residency”, Karvenagar, Pune - 411052, is almost complete and we have received Part Completion for the project from the Pune Municipal Corporation vide No. OCC/0994/24 dated 22.11.2024 (A copy of the same is uploaded on the MahaRERA website). The balance construction activities are almost complete and we have applied for the Completion Certificate for the balance flats to the Pune Municipal Corporation. We also agree to do the quarterly compliance as and when required. Therefore, we request an extension for obtainin

EXT52100028308Jun 2022 → Aug 2025

Reason as filed by the promoterThe said project is almost completed and we have received part completion for the project from Pune Municipal Corporation vide no. OCC/0994/24 dated 22/11/2024 and OCC/1088/24 dated 24/12/2024. Out of 227 flats we have received Occupancy Certificate for 216 flats. Whereas remaining 11 flats are pending due to the the owner's Architect / interior designers. They are constructing the flats as per their requirement and hence the delay in getting full occupancy certificate. Request you to grant us the extension as soon as possible so that we can proceed for Final Occupancy Certificate once these 1

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000269625Mr. Gorakhnath Narayan BhalekarM/s Maha Anand Pinnac Associates through its Partners a)Dinesh Vasant Chandratre b)Vishal Vilas Jain20/10/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Mar 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Apr 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Apr 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 10 Feb 2025

Documents filed337

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 337 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2024-2025)File: Certificate 8 - Form 2A - RDR FY24-25.pdf9 Dec 2025
Form 2A (FY 2017-2018)File: Certificate 1 - Form 2A - RDR FY17-18.pdf9 Dec 2025
Form 2A (FY 2018-2019)File: Certificate 2 - Form 2A - RDR FY18-19.pdf9 Dec 2025
Form 2A (FY 2019-2020)File: Certificate 3 - Form 2A - RDR FY19-20.pdf9 Dec 2025
Form 2A (FY 2020-2021)File: Certificate 4 - Form 2A - RDR FY20-21.pdf9 Dec 2025
Form 2A (FY 2021-2022)File: Certificate 5 - Form 2A - RDR FY21-22.pdf9 Dec 2025
Form 2A (FY 2022-2023)File: Certificate 6 - Form 2A - RDR FY22-23.pdf9 Dec 2025
Form 2A (FY 2023-2024)File: Certificate 7 - Form 2A - RDR FY23-24.pdf9 Dec 2025
Withdrawal Update Form 1File: RDR - FORM 1 FY25-26 Q2.pdf8 Dec 2025
Withdrawal Update Form 2File: RDR - FORM 2 FY25-26 Q2.pdf8 Dec 2025
Withdrawal Update Form 3File: RDR - FORM 3 FY25-26 Q2.pdf8 Dec 2025
Form 5 (FY 2023-2024)File: Form 5 RDR - 2023-24.pdf8 Dec 2025
Form 5 (FY 2022-2023)File: Form 5 RDR - 2022-23.pdf8 Dec 2025
Withdrawal Update Form 1File: RDR - FORM 1 FY25-26 Q2.pdf5 Nov 2025
Withdrawal Update Form 1File: Form 1 Architect Certificate -30062025.pdf5 Nov 2025
Withdrawal Update Form 2File: RDR - FORM 2 FY25-26 Q2.pdf5 Nov 2025
Withdrawal Update Form 2File: RDR - FORM 2 FY25-26 Q1.pdf5 Nov 2025
Withdrawal Update Form 3File: RDR - FORM 3 FY25-26 Q2.pdf5 Nov 2025
Withdrawal Update Form 3File: Form 3 CA Certificate 30062025.pdf5 Nov 2025
Form 5 (FY 2024-2025)File: MAPA-From-5-2024-2025_0001.pdf5 Nov 2025
Declaration in FORM BFile: EXT Form B Declaration - Affidavit cum Declaration - 30062025-1.pdf29 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate -31032025.pdf29 Apr 2025
Certificates of CA (Form 3)File: Form 3 CA Certificate 31032025.pdf29 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 31032025.pdf29 Apr 2025
Disclosure of sold/ booked inventoryFile: Declaration-Sold Unsold Inventory 31032025.pdf29 Apr 2025
Certificates of CA (Form 3)File: Form-3- RDR Q3.pdf12 Mar 2025
Declaration in FORM BFile: Form B 30042025.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Declaration-Sold Unsold Inventory New-1.pdf3 Mar 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: COMPLETION 2nd Part.pdf10 Feb 2025
Architect’s Certificate on Completion of Project (Form 4)File: From 4 Architect Certificate.pdf6 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate.pdf6 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 RDR - 2023-24.pdf6 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Architect Certitificate.pdf3 Feb 2025
Certificates of CA (Form 3)File: Form-3-PPG.pdf3 Feb 2025
Declaration in FORM BFile: 5-1.pdf27 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RDR - Form 1.pdf26 Dec 2024
Certificates of CA (Form 3)File: RDR - Form 3 - Dec 2024.pdf26 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RDR - Form 2 - Dec 2024.pdf26 Dec 2024
Disclosure of sold/ booked inventoryFile: RDR - Sold Unsold.pdf26 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: RDR - Part Completion Certificate.pdf25 Dec 2024
Declaration in FORM BFile: River Dale Residency - Form B 30122024.pdf7 Nov 2024
Certificates of CA (Form 3)File: C A Certificate.pdf21 Oct 2024
Disclosure of sold/ booked inventoryFile: Booked Inventary.pdf21 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf18 Oct 2024
Certificates of CA (Form 3)File: Form 3.pdf18 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf18 Oct 2024
Declaration in FORM BFile: Form B.pdf7 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf20 Jun 2024
CERSAI detailsFile: 14 No Cersai report.pdf20 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: 24 Annexure A - Disclosure - VJ.pdf20 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - 23-24_compressed.pdf18 Jun 2024
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate (Format - D).pdf15 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A - Disclosure of Intrest in other Real Estate Organization_0001.pdf15 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 2A - 23-24_compressed.pdf15 Jun 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A - Declaration about Separate Bank Account for Real Estate Project_0001.pdf15 Jun 2024
Deviation Report with respect to Allotment letterFile: Deviation Report with Respect to Model Copy of Allotment Letter_0001.pdf15 Jun 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report with Respect to Model Copy of Agreement for Sale_0001.pdf15 Jun 2024
Declaration in FORM BFile: Form B - RDR - June 2024.pdf13 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf7 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 RDR - 2022-23.pdf6 May 2024
Building plan approvalFile: plan 03-25.pdf27 Apr 2024
Building plan approvalFile: plan 04-25.pdf27 Apr 2024
Building plan approvalFile: plan 05-25.pdf27 Apr 2024
Building plan approvalFile: plan 06-25.pdf27 Apr 2024
Building plan approvalFile: plan 07-25.pdf27 Apr 2024
Building plan approvalFile: plan 08-25.pdf27 Apr 2024
Building plan approvalFile: plan 09-25.pdf27 Apr 2024
Building plan approvalFile: plan 10-25.pdf27 Apr 2024
Building plan approvalFile: plan 11-25.pdf27 Apr 2024
Building plan approvalFile: plan 12-25.pdf27 Apr 2024
Building plan approvalFile: plan 13-25.pdf27 Apr 2024
Building plan approvalFile: plan 14-25.pdf27 Apr 2024
Building plan approvalFile: plan 15-25.pdf27 Apr 2024
Building plan approvalFile: plan 16-25.pdf27 Apr 2024
Building plan approvalFile: plan 17-25.pdf27 Apr 2024
Building plan approvalFile: plan 18-25.pdf27 Apr 2024
Building plan approvalFile: plan 19-25.pdf27 Apr 2024
Building plan approvalFile: plan 20-25.pdf27 Apr 2024
Building plan approvalFile: plan 21-25.pdf27 Apr 2024
Building plan approvalFile: plan 22-25.pdf27 Apr 2024

How this compares with Pune

65%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 38 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep River Dale Residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Karvenagar13,700+ in Pune

2 kmRiver Dale ResidencyCompleted 46Lapsed / revoked 34Other 67Dot size: filed unitsN

Filed coordinates, straight-line distance. 147 registered projects within 2 km.

Builder: Maha Anand Pinnac Associates

Maha Anand Pinnac Associates has 1 registration on MahaRERA, including River Dale Residency. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that River Dale Residency shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if River Dale Residency is delayed beyond 31 Aug 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of River Dale Residency?

The registered promoter entity is Maha Anand Pinnac Associates, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in River Dale Residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against River Dale Residency?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for River Dale Residency?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at River Dale Residency?

The professionals named in the filing: Architect: Pinnac Consulting Pvt Ltd; Engineer: Sunil Mutalik and Associates; Engineer: NITIN SUDHAKAR PARGAONKAR; Chartered Accountant: PRAKASH WALGUDE AND ASSOCIATES; Chartered Accountant: KUMAR MULAY AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in River Dale Residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About River Dale Residency. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save River Dale Residency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.