LE SKYLARK

By KAKADE GREEN ESTATES PRIVATE LIMITED

RG-MH-17055 · RERA P52100027797 · Last updated on MahaRERA portal: 10 Aug 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 3 cases
  • 2 complaints at MahaRERA
  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 18 months from the original
7 of 33Construction stages doneacross 3 buildings; furthest along: Basement (if any), 95%
147 of 251Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 171 documents Report an error

LE SKYLARK is a Others project by KAKADE GREEN ESTATES PRIVATE LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100027797 on 3 Jan 2021. Possession is promised by 15 Dec 2026. The completion date has moved by 18 months from the original filing. 104 of the 251 units on this registration are recorded sold or booked, and 7 of 33 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameLE SKYLARK
  • TypeOthers
  • Location
    • -
    • KARVENAGAR
    • Karve Nagar
    • Haveli
    • Pune
    • 411052
  • Pincode411052
  • RERA no.P52100027797
  • ReraGenie IDRG-MH-17055

Builder

  • NameKAKADE GREEN ESTATES PRIVATE LIMITED
  • Entity typeCompany
  • DirectorsCHANDRAKANT KANKAYYA BODA, RAMESH SITARAM BHOSALE
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects1 →

Key dates

this monthRegisteredJan 2021First promiseJun 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on3 Jan 2021
  • Promised completion15 Dec 2026
  • Revised completionRevised to 15 Dec 2026 (originally 15 Jun 2025)
  • Buildings3 building records
  • Documents filed171 files

Current status

41%104 of 251 units booked
54.8%Work done, per cost certificate

Figures as on 10 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
COMMERCIALNA3206262
RESIDENTIAL WING ANA191397097
RESIDENTIAL WING BNA191392092

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 10 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Basement (if any), at 95%.

COMMERCIAL66%
ActivityProgress
Excavation100%
Basement (if any)90%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises73%
Sanitary Fittings within the flats / premises62%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks88%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
RESIDENTIAL WING A40%
ActivityProgress
Excavation100%
Basement (if any)95%
Podiums (if any)67%
Plinth100%
Stilt Floor0%
Slabs of Super Structure32%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises12%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.15%
RESIDENTIAL WING B53%
ActivityProgress
Excavation100%
Basement (if any)95%
Podiums (if any)90%
Plinth100%
Stilt Floor0%
Slabs of Super Structure79%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities15

As on 10 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes25%
Water SupplyYes35%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes25%
Landscaping & Tree PlantingYes25%
Street LightingYes10%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes40%
Solid Waste Management And DisposalYes25%
Water conservation /Rain water harvestingYes25%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes35%
Electrical meter room, sub-station, receiving stationYes45%
Aggregate area of recreational Open SpaceYes10%
Open ParkingYes0%

Parking filed968

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots968
Closed/Covered667
Open Space301
BuildingClosed/CoveredOpen SpaceTotal
COMMERCIAL442147589
RESIDENTIAL WING A11981200
RESIDENTIAL WING B10673179

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area11,270 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on7 Aug 2026

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI29364.67
Proposed, not sanctioned29,361 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR, DAHANUKAR REGENCY, DAHANUKAR CIRCLE,NEAR CUMMINS LTD.DAHANUKAR COLONY PUNEPIN :411029
Estimated costRs 150.00 cr
Cost incurredRs 82.20 cr
Work done54.8%
BuildingWingEstimatedIncurred
RESIDENTIAL WING ANARs 62.50 crRs 18.75 cr
RESIDENTIAL WING BNARs 62.50 crRs 40.45 cr
COMMERCIALNARs 25.00 crRs 23.00 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectManoj Tatooskar
EngineerSagar Madhukar Dhane
Chartered AccountantS J MULE AND CO
Chartered AccountantSAC & CO LLP.
PartnerRole in project
KAKADE GREEN ESTATES PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA21072502121Jun 2025 → Dec 2026

Reason as filed by the promoter1. Non Receipt of Environmental Clearance. Despite continuous follow-ups and compliance with all requested clarifications, the EC remained pending, which directly affected our ability to commence/continue vertical construction. 2. Non Active of EC Committee. This committee's inactivity, which is a government-administered body and beyond the control of private developers, became one of the most significant bottlenecks, leading to project stagnation and subsequent financial and planning setbacks. 3. External Administrative Constraints were the major reasons for delay.

Litigation declared3

CaseCourtStatus
135/2009BOMBAY HIGH COURT MUMBAIClosed
2737/2018BOMBAY HIGH COURT MUMBAIClosed
3534/2021DISTRICT COURT PUNEClosed

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC12400025Prasad Girish AdawadkarKAKADE GREEN ESTATES PRIVATE LIMITED04/09/2024
CC12401025Moreshwar Bhikaji DesaiKAKADE GREEN ESTATES PRIVATE LIMITED04/12/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 May 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Mar 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Oct 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Sep 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 15 Dec 2026

Documents filed171

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 171 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM - 1.pdf10 Aug 2026
Withdrawal Update Form 2File: Form - 2.pdf10 Aug 2026
Withdrawal Update Form 3File: Form 3 Le Skylark sign UPDATED.pdf10 Aug 2026
Form 2A (FY 2025-2026)File: Form 2a.pdf10 Aug 2026
Withdrawal Update Form 1File: FORM - 1.pdf23 Jun 2026
Withdrawal Update Form 2File: Form - 2.pdf23 Jun 2026
Withdrawal Update Form 3File: Form 3 F le skylark.pdf23 Jun 2026
Layout approvalFile: Layout with area in highlight.pdf31 Mar 2026
Withdrawal Update Form 1File: Form 1- Architect Certificate.pdf31 Mar 2026
Withdrawal Update Form 2File: Form 2-Eng Certificate.pdf31 Mar 2026
Withdrawal Update Form 3File: Form 3 LE SKYLARK_compressed.pdf31 Mar 2026
Withdrawal Update Form 1File: Form 1.pdf18 Mar 2026
Withdrawal Update Form 2File: Form 2.pdf18 Mar 2026
Withdrawal Update Form 3File: Form 3-CA certificate.pdf18 Mar 2026
Building plan approvalFile: Amended Building Plan Layout.pdf10 Oct 2025
Building plan approvalFile: Amended B P Layout 2_compressed.pdf10 Oct 2025
Building plan approvalFile: 3.pdf10 Oct 2025
Building plan approvalFile: 4.pdf10 Oct 2025
Building plan approvalFile: 5.pdf10 Oct 2025
Building plan approvalFile: 6.pdf10 Oct 2025
Building plan approvalFile: 7.pdf10 Oct 2025
Building plan approvalFile: 8.pdf10 Oct 2025
Building plan approvalFile: 9.pdf10 Oct 2025
Building plan approvalFile: 10.pdf10 Oct 2025
Form 5 (FY 2022-2023)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23).pdf7 Oct 2025
Form 5 (FY 2023-2024)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24).pdf7 Oct 2025
Layout approvalFile: Layout with area in highlight.pdf6 Oct 2025
Form 2A (FY 2024-2025)File: Form 2A-Engineer's Certificate dt.30.06.2025.pdf6 Oct 2025
Form 5 (FY 2024-2025)File: Form 5 2024-2025.pdf6 Oct 2025
Layout approvalFile: Revised Layout Le Skylark.pdf18 Sep 2025
Layout approvalFile: Revised A and B.pdf18 Sep 2025
Layout approvalFile: Revised Basement and Parking Floor Plan.pdf18 Sep 2025
Layout approvalFile: Revised Lower ground and upper ground floor plan.pdf18 Sep 2025
Layout approvalFile: Revised First floor landscape amenities plan A tower.pdf18 Sep 2025
Layout approvalFile: Revsied Section and Elevation A tower.pdf18 Sep 2025
Layout approvalFile: Revised section and elevation B tower.pdf18 Sep 2025
Layout approvalFile: Revised Second to terrace plan A tower.pdf18 Sep 2025
Layout approvalFile: Revised B tower typical.pdf18 Sep 2025
Layout approvalFile: Revised B tower typical plan.pdf18 Sep 2025
Layout approvalFile: c plot revised commencement certificate.pdf18 Sep 2025
Form 1File: Form 1-Architect Certificate-Le Skylark.pdf9 Jul 2025
Form 2File: Form 2 31032025 Engineer's Certificate.pdf9 Jul 2025
Form 3File: Le-Skylark Form - 3 -CA Certificate- 1st jan 2025 to 31st march 2025..pdf9 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold unsold 31 03 2025.pdf9 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30092024 sign.PDF20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 31122024 sign.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30062024 sign.pdf20 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 fy 23-24 Le Skylark sign.pdf20 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31032024 sign_compressed.pdf15 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30062024 sign_compressed.pdf15 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30092024 sign_compressed.pdf15 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31122024 sign_compressed.pdf15 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30062024 sign.pdf15 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 31122024 sign.pdf15 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30092024 sign.pdf15 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 31032024 sign.pdf15 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Disclosure 31032024 sign.pdf15 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Disclosure 30062024 sign.pdf15 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Disclosure 30092024 sign.pdf15 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Disclosure 31122024 sign.pdf15 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A FY 23 -24.pdf15 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf21 Mar 2024
Details of encumbrances concerned to FinanceFile: ENCUMBRANCE MERGED.pdf11 Mar 2024
Details of encumbrances concerned to LegalFile: ENCUMBRANCE MERGED.pdf11 Mar 2024
Declaration about Commencement CertificateFile: Declaration about commencement Certificate.pdf11 Mar 2024
CERSAI detailsFile: No cersai certificate.pdf11 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEREST MERGED.pdf11 Mar 2024
Proforma of Allotment letterFile: Model Form of allotment letter.pdf11 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf11 Mar 2024
Deviation Report with respect to Allotment letterFile: No Deviation with respect to allotment letter.pdf11 Mar 2024
Deviation Report with respect to model copy of AgreementFile: No Deviation with respect to model copy of agreement.pdf11 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Form 2 31322.pdf5 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form 2 300622.pdf5 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 Form 2 30922.pdf5 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 Form 2 311222.pdf5 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5 Form 2 310323.pdf5 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6 Form 2 300623.pdf5 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7 Form 2 300923.pdf5 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8 Form 2 311223.pdf5 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2020 21 signed.pdf5 Mar 2024

How this compares with Pune

41%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 18 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep LE SKYLARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KARVENAGAR13,700+ in Pune

Builder: KAKADE GREEN ESTATES PRIVATE LIMITED

KAKADE GREEN ESTATES PRIVATE LIMITED has 2 registrations on MahaRERA, including SHADES OF TRADE and LE SKYLARK. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if LE SKYLARK is delayed beyond 15 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LE SKYLARK?

The registered promoter entity is KAKADE GREEN ESTATES PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LE SKYLARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against LE SKYLARK?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for LE SKYLARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at LE SKYLARK?

The professionals named in the filing: Architect: Manoj Tatooskar; Engineer: Sagar Madhukar Dhane; Chartered Accountant: S J MULE AND CO; Chartered Accountant: SAC & CO LLP.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LE SKYLARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LE SKYLARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LE SKYLARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.