Home / Browse projects / Pune, Maharashtra / Kishor Kunj
Kishor Kunj
By GPL REALTY
RG-MH-97656 · RERA P52100046478 · Last updated on MahaRERA portal: 26 Aug 2025
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Kishor Kunj is a Residential / Group Housing project by GPL REALTY in Pune, Maharashtra, registered with MahaRERA as P52100046478 on 5 Aug 2022. The registration is recorded completed; possession was promised by 31 Dec 2024.
At a glance
Project
- NameKishor Kunj
- TypeResidential / Group Housing
- Location
- paud road
- kothrude
- Kothrud
- Haveli
- Pune
- 411038
- Pincode411038
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100046478
- ReraGenie IDRG-MH-97656
Builder
- NameGPL REALTY
- Entity typePartnership
- Partnersrahul ladhe, ganesh ladhe
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on5 Aug 2022
- Promised completion31 Dec 2024
- Revised completionNone
- Buildings1 building record
- Documents filed48 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Kishorkunj | NA | 6 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 26 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 90%.
Kishorkunj: 85% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 45% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Progress on shared amenities15
As on 26 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership3
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| kishor Shridhar Mahajan | Pune (M Corp.) | Pune |
| omkar Kishor mahajan | Pune (M Corp.) | Pune |
| Aarohi nikhil kulkarni | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Swapnil Nahar |
| Engineer | nilesh anpat |
| Chartered Accountant | R J Lahoti and co |
| Partner | Role in project |
|---|---|
| GPL REALTY | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 24 Jun 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 11 Jul 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 20 Jun 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 20 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed48
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupational CertificateFile: Completion Certificate Kishor Kunj.pdf | 26 Aug 2025 |
| Occupational CertificateFile: Form4 Kishor Kunj.pdf | 26 Aug 2025 |
| Occupational CertificateFile: Occupancy Certificate Verification.pdf | 26 Aug 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA 31-12-2023.pdf | 29 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate 31-12-2023.pdf | 27 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 31-12-2023.pdf | 27 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA 30-9-2023.pdf | 28 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Er Form 2 30-09-2023.pdf | 27 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 30-09-2023.pdf | 27 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate 30-9-2023.pdf | 26 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate 30-06-2023.pdf | 14 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate 30-06-2023.pdf | 14 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Quality Assurance 30-06-2023.pdf | 14 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate 30-06-2023.pdf | 14 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Kishor kunj Sold unsold inventory.pdf | 4 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate 30-09-2022.pdf | 3 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate 31-12-2022.pdf | 3 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate 31-03-2023.pdf | 3 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA cert 30-09-2022.pdf | 3 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA cert 31-12-2022.pdf | 3 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA cert 31-03-2023.pdf | 3 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Eng certificate 31-03-2023.pdf | 2 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Quality Assurance 31-03-2023.pdf | 2 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Kishor Kunj Form 2 30-09-22.pdf | 18 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Kishor Kunj Form 2 31-12-22.pdf | 18 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Kishor kunj Form 2 A 30-09-22.pdf | 18 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Kishor Kunj Form 2 A 31-12-22.pdf | 18 Apr 2023 |
| Declaration in FORM BFile: Affidavit cum Declaration Gpl Realty.pdf | 12 Jul 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architechs Certificate_compressed (1).pdf | 12 Jul 2022 |
| Proforma of Allotment letterFile: agreement to sale RERA draft _revised.pdf | 12 Jul 2022 |
| Deviation Report with respect to model copy of AgreementFile: deviation agreement to sale.pdf | 12 Jul 2022 |
| Deviation Report with respect to model copy of AgreementFile: Deviation to agreement.pdf | 12 Jul 2022 |
| Layout approvalFile: layout.pdf | 11 Jul 2022 |
| Copy of Layout Approval (in case of layout)File: layout.pdf | 11 Jul 2022 |
| Details of encumbrances concerned to LegalFile: Non Encumbrance Certificate for legal.pdf | 5 Jul 2022 |
| Proforma of Allotment letterFile: Allotment Letter_compressed.pdf | 5 Jul 2022 |
| Deviation Report with respect to Allotment letterFile: No Devation Declaration Allotment Letter.pdf | 5 Jul 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Account And No Encumbrance Certificate.pdf | 1 Jul 2022 |
| Copy of the legal title reportFile: Legal format A.pdf | 24 Jun 2022 |
| Copy of the legal title reportFile: Title Search.pdf | 24 Jun 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_compressed.pdf | 24 Jun 2022 |
| Building plan approvalFile: N A Order.pdf | 20 Jun 2022 |
| PAN CardFile: Gpl Realty Pan.pdf | 20 Jun 2022 |
| Details of encumbrancesFile: Non Encumbrance certificate.pdf | 20 Jun 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: N A Order.pdf | 20 Jun 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement final_compressed (2).pdf | 20 Jun 2022 |
| Declaration about Commencement CertificateFile: Declaration commencement certificate.pdf | 20 Jun 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200240196576_For_Asset_Based_Search_20_06_2022_18_37_14_356.pdf | 20 Jun 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 48 filed documents as one ZIP, foldered, with a manifest
Keep Kishor Kunj on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near kothrude13,700+ in Pune
Filed coordinates, straight-line distance. 310 registered projects within 2 km.
Pratik Nagar Palladio Kothrud Central
Vilas Javdekar Infinitee Developers Pvt. L
NEW FRIENDS
MAJESTIQUE DUROPOLIS PRIVATE LIMITED
SARVATRA CO-OP HSG SOCIETY LTD
Suryakant Kakade
Kshitij Residency
Yash Buildcon
MAYUK
MAYUR CORPORATION
Pune Baner Project-Tower 4 and 5
Goel Ganga Ventures India Private Limited
Builder: GPL REALTY
GPL REALTY has 1 registration on MahaRERA, including Kishor Kunj. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Kishor Kunj is delayed beyond 31 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Kishor Kunj?
The registered promoter entity is GPL REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Kishor Kunj?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Kishor Kunj?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Kishor Kunj?
The professionals named in the filing: Architect: Swapnil Nahar; Engineer: nilesh anpat; Chartered Accountant: R J Lahoti and co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Kishor Kunj?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback