Home / Browse projects / Pune, Maharashtra / Kingston Greens Phase 1
Kingston Greens Phase 1
RG-MH-41366 · RERA P52100019471 · Last updated on MahaRERA portal: 4 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 22 months
- 2 extensions taken
- Rs 20.00 crore secured on the land, in favour of IIFL
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Kingston Greens Phase 1 is a Others project by Vedant Developments in Pune, Maharashtra, registered with MahaRERA as P52100019471 on 1 Feb 2019. Possession is promised by 30 Oct 2027. The completion date has moved by 22 months from the original filing. 205 of the 339 units on this registration are recorded sold or booked, and 24 of 44 construction stages are filed complete.
At a glance
Project
- NameKingston Greens Phase 1
- TypeOthers
- Location
- Pisoli
- Haveli
- Pune
- 411028
- Pincode411028
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100019471
- ReraGenie IDRG-MH-41366
Builder
- NameVedant Developments
- Entity typePartnership
- PartnersSandeep Deepak Agarwal, Rishab Parasmal Jain
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on1 Feb 2019
- Promised completion30 Oct 2027
- Revised completionRevised to 30 Oct 2027 (originally 31 Dec 2025)
- Buildings4 building records
- Documents filed149 files
Current status
Figures as on 4 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A1 Wing | NA | 6 | 4 | 0 | 50 | 50 |
| A2 Wing | NA | 6 | 4 | 0 | 50 | 50 |
| B Wing | NA | 16 | 15 | 120 | 0 | 120 |
| C Wing | NA | 16 | 14 | 119 | 0 | 119 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 4 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
24 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Internal walls, at 85%.
A1 Wing85%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
A2 Wing85%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
B Wing60%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 40% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
C Wing30%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 35% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 4 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1001
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A1 Wing | 113 | 0 | 113 |
| A2 Wing | 115 | 0 | 115 |
| B Wing | 373 | 12 | 385 |
| C Wing | 376 | 12 | 388 |
Land and ownership1
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| Bhapkar & Bhintade Family Thru Vedant Developments | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| C Wing | NA | Rs 15.56 cr | Rs 5.50 cr |
| B Wing | NA | Rs 15.36 cr | Rs 13.54 cr |
| A1 Wing | NA | Rs 3.03 cr | Rs 2.97 cr |
| A2 Wing | NA | Rs 3.03 cr | Rs 2.97 cr |
| - | NA | Rs 2.43 cr | - |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VILAS TARWADI |
| Engineer | Devanand Patil |
| Chartered Accountant | Dilip Kundankumar Jain |
| Chartered Accountant | Jatin Oswal |
| Chartered Accountant | Sheetal Gadiya |
| Partner | Role in project |
|---|---|
| Vedant Developments | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterNA
Reason as filed by the promoter1. Revision of Previously Sanctioned Plan: o The project experienced modifications due to changes in the previously approved sanctioned plan. o Revisions were necessary to ensure compliance with statutory requirements, planning norms, and site-specific conditions. o The process of preparing, submitting, and obtaining approval for the revised plan contributed to project delays. 2. Change in Environmental Clearance (EC): o The project initially had a local body Environmental Clearance. o A revised Environmental Clearance from SEIAA and SEAC was obtained on 25.11.2025. o The process of obtaining
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 19 Jan 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Nov 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Nov 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 22 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Oct 2027
Documents filed149
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 149 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Architect Certificate-June 26 Green.pdf | 4 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer certifictes June 2026-Q1-Greens.pdf | 4 Aug 2026 |
| Withdrawal Update Form 3File: Form 3 -Q1-FY 26-27 Signed.pdf | 4 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate-March 26 Green.pdf | 27 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 engieere Certificate -Green-March 26.pdf | 27 Jul 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 27 Jul 2026 |
| Withdrawal Update Form 1File: Kingston Green Phase 1 Q3 Form 1.pdf | 31 Jan 2026 |
| Withdrawal Update Form 2File: Kingston Green Phase 1 Q3 Form 2.pdf | 31 Jan 2026 |
| Withdrawal Update Form 3File: Kingston Greens Phase I Q3 Form 3.pdf | 31 Jan 2026 |
| Withdrawal Update Form 1File: Form 1 - Architect Certificate -Sept 2025.pdf | 31 Dec 2025 |
| Withdrawal Update Form 2File: Form 2 -Engineer Certificate for Sept 2025.pdf | 31 Dec 2025 |
| Withdrawal Update Form 3File: Form 3-CA Certificate for Sept 2025.pdf | 31 Dec 2025 |
| Withdrawal Update Form 1File: Form 1 - Architect Certificate -June 25 Kingston Green Phase I.pdf | 30 Dec 2025 |
| Withdrawal Update Form 2File: Form 2 - Engineer Certificate for June 25 Kingston Greens Phase I.pdf | 30 Dec 2025 |
| Withdrawal Update Form 3File: Form 3 CA Certificate for June 2025.pdf | 30 Dec 2025 |
| Form 1File: Form 1 - Architect Certificate -March 25.pdf | 24 Dec 2025 |
| Form 2File: Engineere Certificate for March 25 -Green.pdf | 24 Dec 2025 |
| Form 3File: FORM 3 Q4 FY 24-25_Signed.pdf | 24 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold and unsold inventory_Signed.pdf | 24 Dec 2025 |
| Form 1File: Form 1 - Architect Certificate -Dec 24.pdf | 23 Dec 2025 |
| Form 2File: Form 2 Engineere Certificate-December 2024.pdf | 23 Dec 2025 |
| Form 3File: Final form 3 Q3 FY 2024-25.pdf | 23 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold and unsold inventory_signed.pdf | 23 Dec 2025 |
| Certificates of CA (Form 3)File: FORM 3 For Correction Updated.pdf | 24 Jan 2025 |
| Layout approvalFile: 1.pdf | 25 Nov 2024 |
| Building plan approvalFile: 1.pdf | 25 Nov 2024 |
| Building plan approvalFile: 2.pdf | 25 Nov 2024 |
| Building plan approvalFile: 3.pdf | 25 Nov 2024 |
| Building plan approvalFile: 3.pdf | 25 Nov 2024 |
| Building plan approvalFile: 4.pdf | 25 Nov 2024 |
| Building plan approvalFile: 5.pdf | 25 Nov 2024 |
| Building plan approvalFile: 6.pdf | 25 Nov 2024 |
| Building plan approvalFile: 7.pdf | 25 Nov 2024 |
| Building plan approvalFile: 8.pdf | 25 Nov 2024 |
| Building plan approvalFile: 9.pdf | 25 Nov 2024 |
| Building plan approvalFile: 12.pdf | 25 Nov 2024 |
| Building plan approvalFile: 10.pdf | 25 Nov 2024 |
| Building plan approvalFile: 12.pdf | 25 Nov 2024 |
| Building plan approvalFile: 11.pdf | 25 Nov 2024 |
| Copy of Layout Approval (in case of layout)File: 1.pdf | 25 Nov 2024 |
| Certificates of CA (Form 3)File: FORM 3 For Correction Updated signed.pdf | 25 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2- Enginere Certificate -13-11-2024.pdf | 25 Nov 2024 |
| Building Plan Approval (IOD)File: 7.pdf | 25 Nov 2024 |
| Building Plan Approval (IOD)File: 11.pdf | 25 Nov 2024 |
| Building Plan Approval (IOD)File: 12.pdf | 25 Nov 2024 |
| Building Plan Approval (IOD)File: 10.pdf | 25 Nov 2024 |
| Building Plan Approval (IOD)File: 12.pdf | 25 Nov 2024 |
| Building Plan Approval (IOD)File: 9.pdf | 25 Nov 2024 |
| Building Plan Approval (IOD)File: 8.pdf | 25 Nov 2024 |
| Building Plan Approval (IOD)File: 6.pdf | 25 Nov 2024 |
| Building Plan Approval (IOD)File: 5.pdf | 25 Nov 2024 |
| Building Plan Approval (IOD)File: 4.pdf | 25 Nov 2024 |
| Building Plan Approval (IOD)File: 3.pdf | 25 Nov 2024 |
| Building Plan Approval (IOD)File: 3.pdf | 25 Nov 2024 |
| Building Plan Approval (IOD)File: 2.pdf | 25 Nov 2024 |
| Building Plan Approval (IOD)File: 1.pdf | 25 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD-BOOKED INVENTORY signed.pdf | 25 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Vedant Developments FY 22-23 signed.pdf | 25 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Vedant Developments FY 23-24.pdf | 25 Nov 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: KINGSTON GREENS CC.pdf | 22 Nov 2024 |
| Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf | 22 Nov 2024 |
| Proforma of Agreement for saleFile: Kingston Greens- Draft Agreement (With Addittional Clauses).pdf | 22 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architect Certificate Q4 - March 23.pdf | 19 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 Architect Certificate Q1 - June 23.pdf | 19 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 FORM 1 MARCH 23.pdf | 19 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 FORM 1 JUNE 23.pdf | 19 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 FORM 1 Q2 23-24.pdf | 19 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 FORM1 Q3 DEC23.pdf | 19 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5 FORM Q4 MARCH 24.pdf | 19 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 FORM1 JUNE 24.pdf | 19 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7 FORM 1 Q2 24-25.pdf | 19 Nov 2024 |
| Certificates of CA (Form 3)File: 1 FORM 3-March 2023.pdf | 19 Nov 2024 |
| Certificates of CA (Form 3)File: 7 Form 3 Q2 FY 24-25-final.pdf | 19 Nov 2024 |
| Certificates of CA (Form 3)File: 6 Form 3 Q1 FY 24-25-final.pdf | 19 Nov 2024 |
| Certificates of CA (Form 3)File: 5 Form 3 Q4 FY 23-24 - final.pdf | 19 Nov 2024 |
| Certificates of CA (Form 3)File: 4 Form 3 Q3 FY 23-24 -final.pdf | 19 Nov 2024 |
| Certificates of CA (Form 3)File: 3 Form 3 Q2 FY 23-24 - final.pdf | 19 Nov 2024 |
| Certificates of CA (Form 3)File: 2 Form 3 Q1 FY 23-24 - final_compressed.pdf | 19 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6 FORM 2 - Engineer Certificate June 24.pdf | 19 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINERE - SEP 24.pdf | 19 Nov 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 149 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Kingston Greens Phase 1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Pisoli13,700+ in Pune
Filed coordinates, straight-line distance. 141 registered projects within 2 km.
Amanora Arbano Towers 73,74,75 and 76
City Corporation Limited
Astrana
Dilip Baburao Tupe
Leisure Town Phase 1
Sai Proviso Homes
ARV Newtown Phase III
Vedant Infracon
Kumar Parc Residences - A2
Kumar Properties Infratech Developers Pvt
Kumar Parc residences - A1
Kumar Properties Infratech Developers Pvt
Builder: Vedant Developments
Vedant Developments has 1 registration on MahaRERA, including Kingston Greens Phase 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Kingston Greens Phase 1 is delayed beyond 30 Oct 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Kingston Greens Phase 1?
The registered promoter entity is Vedant Developments, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Kingston Greens Phase 1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Kingston Greens Phase 1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Kingston Greens Phase 1?
The professionals named in the filing: Architect: VILAS TARWADI; Engineer: Devanand Patil; Chartered Accountant: Dilip Kundankumar Jain; Chartered Accountant: Jatin Oswal; Chartered Accountant: Sheetal Gadiya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Kingston Greens Phase 1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback