Home / Browse projects / Raigarh, Maharashtra / Kingston

Registration lapsed No litigation declared Residential / Group Housing project

Kingston

By Sushant Sudhakar Pol

RG-MH-99285 · RERA P52000045318 · Last updated on MahaRERA portal: 21 Nov 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 40 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
4 of 11Construction stages donefurthest along: Staircases, 78%
0Complaints at MahaRERAon this registration
Jump to the 41 documents Report an error

Kingston is a Residential / Group Housing project by Sushant Sudhakar Pol in Raigarh, Maharashtra, registered with MahaRERA as P52000045318 on 12 May 2022. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 40 months from the original filing.

At a glance

Project

  • NameKingston
  • TypeResidential / Group Housing
  • Location
    • Dongari
    • Uran
    • Raigarh
    • 400702
  • Pincode400702
  • RERA no.P52000045318
  • ReraGenie IDRG-MH-99285

Builder

  • NameSushant Sudhakar Pol
  • Entity typeIndividual

Key dates

10 months past promisethis monthRegisteredMay 2022First promiseAug 2022Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on12 May 2022
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Aug 2022)
  • Buildings1 building record
  • Documents filed41 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KingstonNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Nov 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 78%.

Kingston: 58% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor60%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises45%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks78%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.5%

Progress on shared amenities15

As on 21 Nov 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed4

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots4
Open Space4

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area200 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
Sudhakar Sonaram PolGreater Mumbai (M Corp.) (Part) (802794)Mumbai Suburban
Anita Amarlal TomarThane (M Corp.)Thane

Approvals and building plan

Permissible FSI298.86
Proposed, not sanctioned299 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNavi mumbai

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAtul Patel
EngineerSubhramnyam Rao
Chartered AccountantAA Nathani And Associates
PartnerRole in project
Sushant Sudhakar Pol-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000017975Aug 2022 → Dec 2025

Reason as filed by the promoterTo, The MahaRERA. Subject: Extension to the project bearing registration number P52000045318. Sir, I, Sushant Sudhakar Pol, hereby apply for extension u/s 7(3) of the registered project bearing vide no P P52000045318. As prescribed under circular no 07/2019 dated 08 Feb 2019, the consent of 51% of the allottees is enclosed herewith.

EXT52000012751Aug 2022 → Aug 2023

Reason as filed by the promoterRespected Sir, I, Sushant Pol, promoter of project 'Kingston' registered under MahaRERA vide registration number P52000045318. We received MahaRERA registration for the above-mentioned project on 12/05/2022, but due to a typographical error, the end date of the project was entered as 31/08/2022 (3 Months). We recently noticed the mistake. Though the project is ongoing, I hereby request you please correct the project end date to 31/08/2023. Thanks

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Apr 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Apr 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Apr 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed41

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: 123.PDF21 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (5) (1).pdf16 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: rera (1) (1).pdf16 Nov 2023
Details of encumbrances concerned to FinanceFile: Information as on date 20 16 2022 (4).pdf12 Nov 2022
Details of encumbrances concerned to LegalFile: Information as on date 20 16 2022 (4).pdf12 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 (4).pdf12 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 (4).pdf12 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 (4).pdf12 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: organized (12).pdf12 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: organized (13).pdf12 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: organized (14).pdf12 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: organized (15).pdf12 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Information as on date 20 16 2022 (5).pdf12 Nov 2022
Disclosure of sold/ booked inventoryFile: Information as on date 20 16 2022.pdf12 Nov 2022
Disclosure of sold/ booked inventoryFile: Information as on date 20 16 2022 (1).pdf12 Nov 2022
Disclosure of sold/ booked inventoryFile: Information as on date 20 16 2022 (2).pdf12 Nov 2022
Disclosure of sold/ booked inventoryFile: Information as on date 20 16 2022 (3).pdf12 Nov 2022
Proforma of Agreement for saleFile: Kingston ATS.pdf12 Nov 2022
Disclosure of sold/ booked inventoryFile: Sold Booked Inventory Disclosure Kingston.pdf5 Nov 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Kingstone.pdf5 Nov 2022
Deviation Report with respect to Allotment letterFile: Deviation Allotment Flat kingstone.pdf5 Nov 2022
Deviation Report with respect to model copy of AgreementFile: ats kingstone.pdf5 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ilovepdf_merged (21)_compressed.pdf26 Apr 2022
Layout approvalFile: Kingston layout.pdf19 Apr 2022
Copy of Layout Approval (in case of layout)File: Kingston layout.pdf19 Apr 2022
Building plan approvalFile: plan 1.pdf15 Apr 2022
Building plan approvalFile: plan 2.pdf15 Apr 2022
Building Plan Approval / NA Order for plotted developmentFile: plan 1.pdf15 Apr 2022
Building Plan Approval / NA Order for plotted developmentFile: plan 2.pdf15 Apr 2022
CERSAI detailsFile: CERSAI_Search_Report_200235194279_For_Asset_Based_Search_15_04_2022_15_30_49_959.pdf15 Apr 2022
Proforma of Allotment letterFile: Allotment Letter Format SP.pdf15 Apr 2022
PAN CardFile: shushant pol pan.pdf9 Apr 2022
Copy of the legal title reportFile: 1 Copy of the legal title report.pdf9 Apr 2022
Details of encumbrancesFile: Encumbrance.pdf9 Apr 2022
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf9 Apr 2022
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT.pdf9 Apr 2022
Declaration in FORM BFile: From B Declaration_11zon.pdf9 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf9 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf9 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A.pdf9 Apr 2022
Proforma of Allotment letterFile: Agreement_11zon.pdf9 Apr 2022

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one moved by 40 months
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Kingston on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dongari5,900+ in Raigarh

Builder: Sushant Sudhakar Pol

Sushant Sudhakar Pol has 1 registration on MahaRERA, including Kingston. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that Kingston shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Kingston is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Kingston?

The registered promoter entity is Sushant Sudhakar Pol, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Kingston?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Kingston?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Kingston?

The professionals named in the filing: Architect: Atul Patel; Engineer: Subhramnyam Rao; Chartered Accountant: AA Nathani And Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Kingston?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Kingston. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Kingston to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.