By Vedant Estates & Properties

RG-MH-00196 · RERA PR1260002501474 · Last updated on MahaRERA portal: 18 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 4 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Apr 2030Possession promisedmoved 4 months from the original
3 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 10%
170 of 190Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 17 documents Report an error

Kingston Aura Wing F and G is a Residential / Group Housing project by Vedant Estates & Properties in Pune, Maharashtra, registered with MahaRERA as PR1260002501474 on 14 Nov 2025. Possession is promised by 30 Apr 2030. The completion date has moved by 4 months from the original filing. 20 of the 190 units on this registration are recorded sold or booked, and 3 of 22 construction stages are filed complete.

At a glance

Project

  • NameKingston Aura Wing F and G
  • TypeResidential / Group Housing
  • Location
    • Hadpasar Road
    • Autade Handewadi
    • OUATADE HANDEWADI
    • Haveli
    • Pune
    • 411028
  • Pincode411028
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR1260002501474
  • ReraGenie IDRG-MH-00196

Builder

  • NameVedant Estates & Properties
  • Entity typePartnership
  • PartnersShashikala Deepak Agarwal, Sandeep Deepak Agarwal
  • Declared earlier projects1 →

Key dates

this monthRegisteredNov 2025First promiseDec 2029Revised toApr 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on14 Nov 2025
  • Promised completion30 Apr 2030
  • Revised completionRevised to 30 Apr 2030 (originally 31 Dec 2029)
  • Buildings2 building records
  • Documents filed17 files

Current status

11%20 of 190 units booked
5.4%Work done, per cost certificate

Figures as on 18 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Kingston Aura Wing FNA151272072
Kingston Aura Wing GNA15121180118

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 18 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 10%.

Kingston Aura Wing F28%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Kingston Aura Wing G0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNo0%
Water SupplyNo0%
Sewerage (Chamber, Lines, Septic Tank , STP)No0%
Storm Water DrainsNo0%
Landscaping & Tree PlantingNo0%
Street LightingNo0%
Community BuildingsNo0%
Treatment And Disposal Of Sewage And Sullage WaterNo0%
Solid Waste Management And DisposalNo0%
Water conservation /Rain water harvestingNo0%
Energy managemcntNo0%
Fire protection and fire safety requirementsNo0%
Electrical meter room, sub-station, receiving stationNo0%
Aggregate area of recreational Open SpaceNo0%
Open ParkingNo0%

Parking filed674

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots674
Open Space144
Stilt / Ground296
Podiums / Upper Parking Floor234
BuildingOpen SpaceStilt / GroundPodiums / Upper Parking FloorTotal
Kingston Aura Wing F38128111277
Kingston Aura Wing G106168123397

Land and ownership8

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area28,825 sq m
Land owned byThe promoter, with other names on the file
Named landowners8
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on4 Nov 2025
LandownerVillageDistrict
Anuj AgarwalPune (M Corp.)Pune
Mohammad Khursheed Riaz SiddiquiePune (M Corp.)Pune
Vikas Bhanudas HandeOUATADE HANDEWADIPune
Pushpa Bhagawan lalaPune (CB)Pune
Kaluram Sitaram HandeOUATADE HANDEWADIPune
Deepak dagadu KanseHadapsarPune
Sureshkumar Magharamji ChoudhariHadapsarPune
Vikas devidas HandeOUATADE HANDEWADIPune

Approvals and building plan

Sanctioning authorityPune Metropolitan Regional Development Authority
Permissible FSI28760.12
Proposed, not sanctioned20,253 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAMAR AVINASH CORPORATE CITY,3RD FLOOR,BUND GARDEN ROAD,PUNE 411001
Estimated costRs 48.00 cr
Cost incurredRs 2.60 cr
Work done5.42%
BuildingWingEstimatedIncurred
Kingston Aura Wing FNARs 20.00 crRs 2.60 cr
Kingston Aura Wing GNARs 20.00 cr-
-NARs 8.00 cr-

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVILAS TARWADI
EngineerSunil Nalge
Chartered AccountantJatin Oswal
PartnerRole in project
Vedant Estate & Properties-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR1260002501474/WarDec 2029 → Apr 2030

Reason as filed by the promoterNA

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportNot on the file

    A lawyer's report on who owns the land and what is registered against it.

  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Oct 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Oct 2025
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2030

Documents filed17

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect Certificate-Aura F G -June 26.pdf18 Sep 2026
Withdrawal Update Form 2File: Form - 2_updated-Aura F G - June 26.pdf18 Sep 2026
Withdrawal Update Form 3File: Form 3 revised Q1 fy 26 27 Aura F n G_compressed.pdf18 Sep 2026
Form 2A (FY 2025-2026)File: FORM 2A - VEP.pdf9 Sep 2026
Withdrawal Update Form 1File: Architect Certificate-Aura F G -June 26.pdf7 Sep 2026
Withdrawal Update Form 2File: Form - 2_updated-Aura F G - June 26.pdf7 Sep 2026
Withdrawal Update Form 3File: Form 3 - VEP-Q1 FY 26-17 AURA F N G.pdf7 Sep 2026
Withdrawal Update Form 1File: Form -1 ARchitect certificate Green March 26.pdf29 Jun 2026
Withdrawal Update Form 2File: Form 2- Green -March 26 Engineere Certificate.pdf29 Jun 2026
Withdrawal Update Form 3File: Form 3 Signed.pdf29 Jun 2026
Withdrawal Update Form 1File: form 1 Architect certificate Dec25.pdf18 Jun 2026
Withdrawal Update Form 2File: Form 2Engineere report.pdf18 Jun 2026
Withdrawal Update Form 3File: Form 3 Q3 FY 2025-26 - Wing F and G_11zon.pdf18 Jun 2026
Declaration and undertaking (Annexure A)File: declaration cum undertaking.pdf1 Nov 2025
Layout approvalFile: 1 layout.pdf12 Oct 2025
Building plan approvalFile: 28 Wing F.pdf12 Oct 2025
Building plan approvalFile: 31 Wing G.pdf12 Oct 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationRegisteredStatusPromisedDelivered
Kingston Aura A, B, C, D, E and ApexP52100005126AUTADE HANDEWADI, PuneAug 2017CompletedMar 2023Registered original: Mar 2022Dec 2022

How this compares with Pune

11%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 4 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Kingston Aura Wing F and G on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Autade Handewadi13,700+ in Pune

2 kmKingston Aura Wing F andCompleted 40Lapsed / revoked 16Other 51Dot size: filed unitsN

Filed coordinates, straight-line distance. 107 registered projects within 2 km.

Builder: Vedant Estates & Properties

Vedant Estates & Properties has 1 registration on MahaRERA, including Kingston Aura Wing F and G. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Kingston Aura Wing F and G is delayed beyond 30 Apr 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Kingston Aura Wing F and G?

The registered promoter entity is Vedant Estates & Properties, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Kingston Aura Wing F and G?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Kingston Aura Wing F and G?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Kingston Aura Wing F and G?

The professionals named in the filing: Architect: VILAS TARWADI; Engineer: Sunil Nalge; Chartered Accountant: Jatin Oswal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Kingston Aura Wing F and G?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Kingston Aura Wing F and G. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Kingston Aura Wing F and G to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.