Home / Browse projects / Chandrapur, Maharashtra / KHUSHI RESIDENCY

Registration lapsed No litigation declared Residential / Group Housing project

KHUSHI RESIDENCY

By RAVNEETKAUR CHARANJEETSINGH WADHWA

RG-MH-91361 · RERA P50900023672 · Last updated on MahaRERA portal: 12 Mar 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 37 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Chandrapur registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
1 of 11Construction stages donefurthest along: Basement (if any), 50%
0 of 10Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 67 documents Report an error

KHUSHI RESIDENCY is a Residential / Group Housing project by RAVNEETKAUR CHARANJEETSINGH WADHWA in Chandrapur, Maharashtra, registered with MahaRERA as P50900023672 on 2 Jan 2020. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 37 months from the original filing. 10 of the 10 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.

At a glance

Project

  • NameKHUSHI RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • MCI
    • CHANDA RAYATWARI
    • Chandrapur (M Cl)
    • Chandrapur
    • 442401
  • Pincode442401
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50900023672
  • ReraGenie IDRG-MH-91361

Builder

  • NameRAVNEETKAUR CHARANJEETSINGH WADHWA
  • Entity typeIndividual
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

10 months past promisethis monthRegisteredJan 2020First promiseNov 2022Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on2 Jan 2020
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 28 Nov 2022)
  • Buildings1 building record
  • Documents filed67 files

Current status

100%10 of 10 units booked
100.0%Work done, per cost certificate

Figures as on 12 Mar 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KHUSHI RESIDENCYNA3310010

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 50%.

KHUSHI RESIDENCY: 18% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)50%
Podiums (if any)0%
Plinth50%
Stilt Floor0%
Slabs of Super Structure3%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 12 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area468 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on29 Jul 2025

Approvals and building plan

Sanctioning authorityChandrapur Municipal Corporation
Permissible FSI514.8
Proposed, not sanctioned515 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJATPURA GATE MAIN ROAD CHANDRAPUR 442401
Estimated costRs 1.18 cr
Cost incurredRs 1.18 cr
Work done100.0%
BuildingWingEstimatedIncurred
KHUSHI RESIDENCYNARs 1.18 crRs 1.18 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDEVENDRA MOTWANI
EngineerSWAPNIL D BOKADE
Chartered AccountantRIYA ROHAN UTTARWAR
PartnerRole in project
RAVNEETKAUR CHARANJEETSINGH WADHWA-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50900028033Nov 2022 → Dec 2025

Reason as filed by the promoterSubject: Application for Extension of Project Registration under Section 7(3) of the RERA Act for Khushi Residency (Reg. No.: P50900023672) up to 31/12/2025 Respected Sir/Madam, We, the promoters of the real estate project known as Khushi Residency, situated at Survey No. 12, 13/4, 18/1, Plot No. 78, Chandrapur (M Cl), District: Chandrapur - 442401, registered under MAHARERA Registration No.: P50900023672, respectfully submit this application for the extension of the validity of the said project registration under the provisions of Section 7(3) of the Real Estate (Regulation and Development) A

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Dec 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Dec 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Dec 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Dec 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed67

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: FORM B KHUSHI RESIDENCY.pdf12 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 19-20 KHUSHI RESIDENCY.pdf12 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 20-21 KHUSHI RESIDENCY.pdf12 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 21-22 KHUSHI RESIDENCY.pdf12 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 22-23 KHUSHI RESIDENCY.pdf12 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 23-24 KHUSHI RESIDENCY.pdf12 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 FORM 2 MAR 21.pdf10 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 9 Khushi Recidency Form 3 31st December 2022.pdf3 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 17 Khushi Recidency Form 3 31st DEC 2024.pdf3 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 16 Khushi Recidency Form 3 30th September 2024.pdf3 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 15 Khushi Recidency Form 3 30th June 2024.pdf3 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 14 Khushi Recidency Form 3 31st MARCH 2024.pdf3 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 13 Khushi Recidency Form 3 31st DECEMBER 2023.pdf3 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 12 Khushi Recidency Form 3 30th September 2023.pdf3 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 11 Khushi Recidency Form 3 30th June 2023.pdf3 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 10 Khushi Recidency Form 3 31st March 2023.pdf3 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 7 Khushi Recidency Form 3 30th June 2022.pdf3 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 6 Khushi Recidency Form 3 31st March 2022.pdf3 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5 Khushi Recidency Form 3 31st December 2021.pdf3 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4 Khushi Recidency Form 3 30th sept 2021.pdf3 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Khushi Recidency Form 3 30th June 2021.pdf3 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 Khushi Recidency Form 3 31ST MARCH 2021.pdf3 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 Khushi Recidency Form 3 31st march 2020.pdf3 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 8 Khushi Recidency Form 3 30th September 2022.pdf3 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5 FORM 2 SEP 22.pdf3 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 14 FORM 2 DEC 24.pdf3 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 13 FORM 2 SEP 24.pdf3 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 12 FORM 2 JUNE 24.pdf3 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 11 FORM 2 MARCH 24.pdf3 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 10 FORM 2 DEC 23.pdf3 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 9 FORM 2 SEP 23.pdf3 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8 FORM 2 JUNE 23.pdf3 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7 FORM 2 MAR 23.pdf3 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6 FORM 2 DEC 22.pdf3 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 FORM 2 JUNE 22.pdf3 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 FORM 2 MAR 22.pdf3 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 FORM 2 MAR 20.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: disclosure of sold inventory KHUSHI RESIDENCY.pdf3 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 13 30th june 2024.pdf1 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 31st march 2020.pdf1 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 15 31st DEC 2024.pdf1 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 14 30th Sept 2024.pdf1 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 12 31st march 2024.pdf1 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 11 31st DEC 2023.pdf1 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10 30th sept 2023.pdf1 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9 30TH JUNE 2023.pdf1 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8 31st march 2023.pdf1 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7 31st DEC 2022.pdf1 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 30th sept 2022.pdf1 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5 30th june 2022.pdf1 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 31st march 2022.pdf1 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 31st Dec 2021.pdf1 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 31st march 2021.pdf1 Mar 2025
Details of encumbrancesFile: Encumbrance certificate from Advocate.pdf24 Dec 2019
Commencement Certificates / NA Order for plotted developmentFile: Letter for change in name in commencement certificate.pdf24 Dec 2019
OtherFile: Letter for change in name in commencement certificate.pdf24 Dec 2019
Layout approvalFile: LAYOUT APPROVAL.pdf4 Dec 2019
Building plan approvalFile: BUILDING PLAN.pdf4 Dec 2019
PAN CardFile: PAN CARD.pdf4 Dec 2019
Copy of the legal title reportFile: LEGAL TITLE REPORT.pdf4 Dec 2019
Details of encumbrancesFile: Encymbrance Certificate.pdf4 Dec 2019
Copy of Layout Approval (in case of layout)File: LAYOUT APPROVAL.pdf4 Dec 2019
Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN.pdf4 Dec 2019
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf4 Dec 2019
Declaration in FORM BFile: FORM B.pdf4 Dec 2019
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf4 Dec 2019
Proforma of Allotment letterFile: Allotment Letter.pdf4 Dec 2019

How this compares with Chandrapur

100%of this project is bookeddistrict median 18%
10%of Chandrapur projects moved their completion datethis one moved by 37 months
39%of Chandrapur registrations have lapsed or been cancelledthis one is among them

Computed across the 220+ Chandrapur projects on ReraGenie, from their own filings.

Keep KHUSHI RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHANDA RAYATWARI220+ in Chandrapur

2 kmKHUSHI RESIDENCYCompleted 9Lapsed / revoked 6Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 17 registered projects within 2 km.

Builder: RAVNEETKAUR CHARANJEETSINGH WADHWA

RAVNEETKAUR CHARANJEETSINGH WADHWA has 2 registrations on MahaRERA, including KHUSHI RESIDENCY and GURUNANAK NAGARI. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Chandrapur district page.

Frequently asked questions

What does it mean that KHUSHI RESIDENCY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if KHUSHI RESIDENCY is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KHUSHI RESIDENCY?

The registered promoter entity is RAVNEETKAUR CHARANJEETSINGH WADHWA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KHUSHI RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KHUSHI RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KHUSHI RESIDENCY?

The professionals named in the filing: Architect: DEVENDRA MOTWANI; Engineer: SWAPNIL D BOKADE; Chartered Accountant: RIYA ROHAN UTTARWAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KHUSHI RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KHUSHI RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KHUSHI RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.