Home / Browse projects / Chandrapur, Maharashtra / KHUSHI RESIDENCY
KHUSHI RESIDENCY
By RAVNEETKAUR CHARANJEETSINGH WADHWA
RG-MH-91361 · RERA P50900023672 · Last updated on MahaRERA portal: 12 Mar 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- Completion date moved by 37 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Chandrapur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
KHUSHI RESIDENCY is a Residential / Group Housing project by RAVNEETKAUR CHARANJEETSINGH WADHWA in Chandrapur, Maharashtra, registered with MahaRERA as P50900023672 on 2 Jan 2020. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 37 months from the original filing. 10 of the 10 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.
At a glance
Project
- NameKHUSHI RESIDENCY
- TypeResidential / Group Housing
- Location
- MCI
- CHANDA RAYATWARI
- Chandrapur (M Cl)
- Chandrapur
- 442401
- Pincode442401
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50900023672
- ReraGenie IDRG-MH-91361
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on2 Jan 2020
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 28 Nov 2022)
- Buildings1 building record
- Documents filed67 files
Current status
Figures as on 12 Mar 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| KHUSHI RESIDENCY | NA | 3 | 3 | 10 | 0 | 10 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 12 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 50%.
KHUSHI RESIDENCY: 18% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 50% |
| Podiums (if any) | 0% |
| Plinth | 50% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 3% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 12 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| KHUSHI RESIDENCY | NA | Rs 1.18 cr | Rs 1.18 cr |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DEVENDRA MOTWANI |
| Engineer | SWAPNIL D BOKADE |
| Chartered Accountant | RIYA ROHAN UTTARWAR |
| Partner | Role in project |
|---|---|
| RAVNEETKAUR CHARANJEETSINGH WADHWA | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterSubject: Application for Extension of Project Registration under Section 7(3) of the RERA Act for Khushi Residency (Reg. No.: P50900023672) up to 31/12/2025 Respected Sir/Madam, We, the promoters of the real estate project known as Khushi Residency, situated at Survey No. 12, 13/4, 18/1, Plot No. 78, Chandrapur (M Cl), District: Chandrapur - 442401, registered under MAHARERA Registration No.: P50900023672, respectfully submit this application for the extension of the validity of the said project registration under the provisions of Section 7(3) of the Real Estate (Regulation and Development) A
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 4 Dec 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 4 Dec 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 4 Dec 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 24 Dec 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed67
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Declaration in FORM BFile: FORM B KHUSHI RESIDENCY.pdf | 12 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 19-20 KHUSHI RESIDENCY.pdf | 12 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 20-21 KHUSHI RESIDENCY.pdf | 12 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 21-22 KHUSHI RESIDENCY.pdf | 12 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 22-23 KHUSHI RESIDENCY.pdf | 12 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 23-24 KHUSHI RESIDENCY.pdf | 12 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 FORM 2 MAR 21.pdf | 10 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 9 Khushi Recidency Form 3 31st December 2022.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 17 Khushi Recidency Form 3 31st DEC 2024.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 16 Khushi Recidency Form 3 30th September 2024.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 15 Khushi Recidency Form 3 30th June 2024.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 14 Khushi Recidency Form 3 31st MARCH 2024.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 13 Khushi Recidency Form 3 31st DECEMBER 2023.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 12 Khushi Recidency Form 3 30th September 2023.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 11 Khushi Recidency Form 3 30th June 2023.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 10 Khushi Recidency Form 3 31st March 2023.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 7 Khushi Recidency Form 3 30th June 2022.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 6 Khushi Recidency Form 3 31st March 2022.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5 Khushi Recidency Form 3 31st December 2021.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4 Khushi Recidency Form 3 30th sept 2021.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Khushi Recidency Form 3 30th June 2021.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 Khushi Recidency Form 3 31ST MARCH 2021.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 Khushi Recidency Form 3 31st march 2020.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 8 Khushi Recidency Form 3 30th September 2022.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5 FORM 2 SEP 22.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 14 FORM 2 DEC 24.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 13 FORM 2 SEP 24.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 12 FORM 2 JUNE 24.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 11 FORM 2 MARCH 24.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 10 FORM 2 DEC 23.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 9 FORM 2 SEP 23.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8 FORM 2 JUNE 23.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7 FORM 2 MAR 23.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6 FORM 2 DEC 22.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 FORM 2 JUNE 22.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 FORM 2 MAR 22.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 FORM 2 MAR 20.pdf | 3 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: disclosure of sold inventory KHUSHI RESIDENCY.pdf | 3 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 13 30th june 2024.pdf | 1 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 31st march 2020.pdf | 1 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 15 31st DEC 2024.pdf | 1 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 14 30th Sept 2024.pdf | 1 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 12 31st march 2024.pdf | 1 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 11 31st DEC 2023.pdf | 1 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10 30th sept 2023.pdf | 1 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9 30TH JUNE 2023.pdf | 1 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8 31st march 2023.pdf | 1 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7 31st DEC 2022.pdf | 1 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 30th sept 2022.pdf | 1 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5 30th june 2022.pdf | 1 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 31st march 2022.pdf | 1 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 31st Dec 2021.pdf | 1 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 31st march 2021.pdf | 1 Mar 2025 |
| Details of encumbrancesFile: Encumbrance certificate from Advocate.pdf | 24 Dec 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: Letter for change in name in commencement certificate.pdf | 24 Dec 2019 |
| OtherFile: Letter for change in name in commencement certificate.pdf | 24 Dec 2019 |
| Layout approvalFile: LAYOUT APPROVAL.pdf | 4 Dec 2019 |
| Building plan approvalFile: BUILDING PLAN.pdf | 4 Dec 2019 |
| PAN CardFile: PAN CARD.pdf | 4 Dec 2019 |
| Copy of the legal title reportFile: LEGAL TITLE REPORT.pdf | 4 Dec 2019 |
| Details of encumbrancesFile: Encymbrance Certificate.pdf | 4 Dec 2019 |
| Copy of Layout Approval (in case of layout)File: LAYOUT APPROVAL.pdf | 4 Dec 2019 |
| Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN.pdf | 4 Dec 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf | 4 Dec 2019 |
| Declaration in FORM BFile: FORM B.pdf | 4 Dec 2019 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 4 Dec 2019 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 4 Dec 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Chandrapur
Computed across the 220+ Chandrapur projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 67 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep KHUSHI RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near CHANDA RAYATWARI220+ in Chandrapur
Filed coordinates, straight-line distance. 17 registered projects within 2 km.
CHAWHAN ROYALS
MANGESH RATILAL CHAWHAN
SINGH TOWER
SINGH BUILDCON & SOLUTIONS
CHAWHAN ROYALS TOWER-1
MANGESH RATILAL CHAWHAN
ATHARVA PLAZA
ATHARVA INFRA
GAJANAN PLAZA 4
S V BUILDERS
SKAND RESIDENCY
VAISHNAVI CONSTRUCTION
See every Chandrapur project, with the district possession charts
Builder: RAVNEETKAUR CHARANJEETSINGH WADHWA
RAVNEETKAUR CHARANJEETSINGH WADHWA has 2 registrations on MahaRERA, including KHUSHI RESIDENCY and GURUNANAK NAGARI. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Chandrapur district page.
Frequently asked questions
What does it mean that KHUSHI RESIDENCY shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if KHUSHI RESIDENCY is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of KHUSHI RESIDENCY?
The registered promoter entity is RAVNEETKAUR CHARANJEETSINGH WADHWA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in KHUSHI RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for KHUSHI RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at KHUSHI RESIDENCY?
The professionals named in the filing: Architect: DEVENDRA MOTWANI; Engineer: SWAPNIL D BOKADE; Chartered Accountant: RIYA ROHAN UTTARWAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in KHUSHI RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.