Keshar
RG-MH-17509 · RERA P52100029132 · Last updated on MahaRERA portal: 27 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 41 months
- 3 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Keshar is a Residential / Group Housing project by Badhekar Properties in Pune, Maharashtra, registered with MahaRERA as P52100029132 on 29 Apr 2021. Possession is promised by 31 Aug 2027. The completion date has moved by 41 months from the original filing. 55 of the 105 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameKeshar
- TypeResidential / Group Housing
- Location
- Paud Road
- Kothrud
- Haveli
- Pune
- 411038
- Pincode411038
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100029132
- ReraGenie IDRG-MH-17509
Builder
- NameBadhekar Properties
- Entity typePartnership
- GSTIN27AATFB0231F1ZP
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnerMurlidhar Kisanrao Mohol
- Other registrations6 more →
- No longer live3 lapsed, de-registered or revoked
- Past their filed date1
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on29 Apr 2021
- Promised completion31 Aug 2027
- Revised completionRevised to 31 Aug 2027 (originally 18 Mar 2024)
- Buildings1 building record
- Documents filed238 files
Current status
Figures as on 27 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Keshar | NA | 17 | 15 | 105 | 0 | 105 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 27 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.
Keshar: 70% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 40% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
Progress on shared amenities15
As on 27 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 85% |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 30% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 70% |
| Electrical meter room, sub-station, receiving station | Yes | 40% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed143
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Pravin Badhekar | Kothrud | Pune |
| Prabhakar Ganesh Dindorkar | Kothrud | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Keshar | NA | Rs 41.19 cr | Rs 28.63 cr |
| - | NA | Rs 5.15 cr | Rs 3.01 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Prakash Kulkarni Ankur Associates |
| Engineer | Dhairyashil M Khaire |
| Engineer | Dipali Kulkarni |
| Chartered Accountant | Shirkant Mantri |
| Chartered Accountant | Dinesh Balkrishna Gandhi |
| Chartered Accountant | Shrikant Mantri and Co. |
| Partner | Role in project |
|---|---|
| Badhekar Properties | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to increase in FSI and increase in number of floors, we will need extended Date of Completion.
Reason as filed by the promoterDue to some internal changes in flats and also due to a considerable amount of time required for excavation as the strata was hard, and some subsequent activities, our project needs extension. We request you to provide us with the same as mentioned in the application.
Reason as filed by the promoterDue to overall increase in FSI and increase in number of floors, also due to some internal changes in flats and also due to a considerable amount of time required for excavation as the strata was hard, and some subsequent activities, our project needs extension. We request you to provide us with the same as mentioned in the application.
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000340855 | BHAKTI PRASHANT GATE | BADHEKAR PROPERTIES | 27/04/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 23 Apr 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 Apr 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 1 Aug 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 1 Aug 2026Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Aug 2027
Documents filed238
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 238 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2026-2027)File: Form 2A QAC Keshar 26-27.pdf | 27 Aug 2026 |
| Withdrawal Update Form 1File: Architects Certificate Keshar Mar-26.pdf | 11 Aug 2026 |
| Withdrawal Update Form 1File: Architects certificate Keshar Jun-26.pdf | 11 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 Engineers certificate Keshar Mar-26.pdf | 11 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 Engineers certificate Keshar Jun-26.pdf | 11 Aug 2026 |
| Withdrawal Update Form 3File: Keshar RERA Form 3 up to Mar-26 scan copy_compressed.pdf | 11 Aug 2026 |
| Withdrawal Update Form 3File: Keshar RERA Form 3 up to Jun-26 scan copy_compressed.pdf | 11 Aug 2026 |
| Commencement certificateFile: CC 06042021.pdf | 1 Aug 2026 |
| Commencement certificateFile: CC 2ND SANCTION- 290921.pdf | 1 Aug 2026 |
| Commencement certificateFile: Keshar 3rd CC 27422.pdf | 1 Aug 2026 |
| Commencement certificateFile: Keshar Revise Sanction CC 3129 date 050324.pdf | 1 Aug 2026 |
| Commencement certificateFile: Keshar Revise Sanction CC 0552 date 060624.pdf | 1 Aug 2026 |
| Building plan approvalFile: Keshar Revise Sanction Plan 1_11.pdf | 1 Aug 2026 |
| Building plan approvalFile: Keshar Revise Sanction Plan 2_11.pdf | 1 Aug 2026 |
| Building plan approvalFile: Keshar Revise Sanction Plan 3_11.pdf | 1 Aug 2026 |
| Building plan approvalFile: Keshar Revise Sanction Plan 4_11.pdf | 1 Aug 2026 |
| Building plan approvalFile: Keshar Revise Sanction Plan 5_11.pdf | 1 Aug 2026 |
| Building plan approvalFile: Keshar Revise Sanction Plan 6_11.pdf | 1 Aug 2026 |
| Building plan approvalFile: Keshar Revise Sanction Plan 7_11.pdf | 1 Aug 2026 |
| Building plan approvalFile: Keshar Revise Sanction Plan 8_11.pdf | 1 Aug 2026 |
| Building plan approvalFile: Keshar Revise Sanction Plan 9_11.pdf | 1 Aug 2026 |
| Building plan approvalFile: Keshar Revise Sanction Plan 10_11.pdf | 1 Aug 2026 |
| Building plan approvalFile: Keshar Revise Sanction Plan 11_11.pdf | 1 Aug 2026 |
| Commencement certificateFile: CC Keshar Revise Sanction May 2026.pdf | 1 Aug 2026 |
| Building plan approvalFile: 1 - 11 Keshar Revise Sanction May 2026_compressed.pdf | 1 Aug 2026 |
| Building plan approvalFile: 2-11 Keshar Revise Sanction May 2026.pdf | 1 Aug 2026 |
| Building plan approvalFile: 3-11 Keshar Revise Sanction May 2026_compressed.pdf | 1 Aug 2026 |
| Building plan approvalFile: 4-11 Keshar Revise Sanction May 2026_compressed.pdf | 1 Aug 2026 |
| Building plan approvalFile: 5-11 Keshar Revise Sanction May 2026_compressed.pdf | 1 Aug 2026 |
| Building plan approvalFile: 6-11 Keshar Revise Sanction May 2026_compressed.pdf | 1 Aug 2026 |
| Building plan approvalFile: 7-11 Keshar Revise Sanction May 2026_compressed.pdf | 1 Aug 2026 |
| Building plan approvalFile: 8-11 Keshar Revise Sanction May 2026_compressed.pdf | 1 Aug 2026 |
| Building plan approvalFile: 9-11 Keshar Revise Sanction May 2026_compressed.pdf | 1 Aug 2026 |
| Building plan approvalFile: 10-11 Keshar Revise Sanction May 2026_compressed.pdf | 1 Aug 2026 |
| Building plan approvalFile: 11-11 Keshar Revise Sanction May 2026_compressed.pdf | 1 Aug 2026 |
| Withdrawal Update Form 1File: Architect Certificate Keshar site Dec-25..pdf | 1 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 Engineers certificate Keshar Dec-25.pdf | 1 Aug 2026 |
| Withdrawal Update Form 3File: Keshar RERA Form 3 up to Dec-25 scan copy_compressed.pdf | 1 Aug 2026 |
| Form 5 (FY 2024-2025)File: Keshar RERA Form-5 FY 24-25 scan.pdf | 26 Mar 2026 |
| Form 2A (FY 2021-2022)File: Engineers certificate Form 2A Keshar 21-22.pdf | 21 Jan 2026 |
| Form 2A (FY 2022-2023)File: Form 2A Engineers certificate Keshar 22-23.pdf | 21 Jan 2026 |
| Form 2A (FY 2023-2024)File: Form 2A Engineers certificate Keshar 23-24.pdf | 21 Jan 2026 |
| Form 2A (FY 2024-2025)File: Form 2A Engineers certificate Keshar 24-25.pdf | 21 Jan 2026 |
| Form 2A (FY 2025-2026)File: Form 2A engineers certificate Keshar 25-26.pdf | 21 Jan 2026 |
| Form 1File: Engineer’s Certificate - Keshar Apr 2021.pdf | 26 Nov 2025 |
| Form 2File: Engineer’s Certificate - Keshar Apr 2021.pdf | 26 Nov 2025 |
| Form 3File: CA Certificate - Keshar Apr 2021.pdf | 26 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: CA Certificate - Keshar Apr 2021.pdf | 26 Nov 2025 |
| Form 1File: Engineer’s Certificate - Keshar Apr 2021.pdf | 26 Nov 2025 |
| Form 2File: Engineer’s Certificate - Keshar Apr 2021.pdf | 26 Nov 2025 |
| Form 3File: CA Certificate - Keshar Apr 2021.pdf | 26 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: CA Certificate - Keshar Apr 2021.pdf | 26 Nov 2025 |
| Form 1File: Engineer’s Certificate - Keshar Apr 2021.pdf | 26 Nov 2025 |
| Form 2File: Engineer’s Certificate - Keshar Apr 2021.pdf | 26 Nov 2025 |
| Form 3File: CA Certificate - Keshar Apr 2021.pdf | 26 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: CA Certificate - Keshar Apr 2021.pdf | 26 Nov 2025 |
| Form 1File: Form 1 Architect Certificate Keshar 30 Sept 25.pdf | 25 Nov 2025 |
| Form 2File: Form 1 Architect Certificate Keshar 30 Sept 25.pdf | 25 Nov 2025 |
| Form 3File: Form 1 Architect Certificate Keshar 30 Sept 25.pdf | 25 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Form 1 Architect Certificate Keshar 30 Sept 25.pdf | 25 Nov 2025 |
| Form 1File: Architect’s Certificate - Keshar Sep 2024.pdf | 25 Nov 2025 |
| Form 2File: Architect’s Certificate - Keshar Sep 2024.pdf | 25 Nov 2025 |
| Form 3File: Architect’s Certificate - Keshar Sep 2024.pdf | 25 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ booked inventory Sep 24.pdf | 25 Nov 2025 |
| Form 1File: Architect’s Certificate - Keshar June 2024.pdf | 25 Nov 2025 |
| Form 2File: Architect’s Certificate - Keshar June 2024.pdf | 25 Nov 2025 |
| Form 3File: Architect’s Certificate - Keshar June 2024.pdf | 25 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ booked inventory Jun 24.pdf | 25 Nov 2025 |
| Form 1File: Architect’s Certificate - Keshar Mar 2024.pdf | 25 Nov 2025 |
| Form 2File: Engineer’s Certificate - Keshar Mar 2024.pdf | 25 Nov 2025 |
| Form 3File: CA Certificate - Keshar Mar 2024.pdf | 25 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ booked inventory Mar 24.pdf | 25 Nov 2025 |
| Form 1File: Disclosure of sold_ booked inventory Dec 23.pdf | 25 Nov 2025 |
| Form 2File: Disclosure of sold_ booked inventory Dec 23.pdf | 25 Nov 2025 |
| Form 3File: Disclosure of sold_ booked inventory Dec 23.pdf | 25 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ booked inventory Dec 23.pdf | 25 Nov 2025 |
| Form 1File: Architect’s Certificate - Keshar Sep 2023.pdf | 25 Nov 2025 |
| Form 2File: Architect’s Certificate - Keshar Sep 2023.pdf | 25 Nov 2025 |
| Form 3File: Architect’s Certificate - Keshar Sep 2023.pdf | 25 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ booked inventory Sep 23.pdf | 25 Nov 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 6 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 238 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Keshar on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Paud Road13,700+ in Pune
Filed coordinates, straight-line distance. 331 registered projects within 2 km.
Pratik Nagar Palladio Kothrud Central
Vilas Javdekar Infinitee Developers Pvt. L
NEW FRIENDS
MAJESTIQUE DUROPOLIS PRIVATE LIMITED
SARVATRA CO-OP HSG SOCIETY LTD
Suryakant Kakade
Kshitij Residency
Yash Buildcon
MAYUK
MAYUR CORPORATION
Pune Baner Project-Tower 4 and 5
Goel Ganga Ventures India Private Limited
Builder: Badhekar Properties
Badhekar Properties has 7 registrations on MahaRERA, including Mayura and Keshar. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Keshar is delayed beyond 31 Aug 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Keshar?
The registered promoter entity is Badhekar Properties, a partnership as per the filing. Its GSTIN 27AATFB0231F1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Keshar?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Keshar?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Keshar?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Keshar?
The professionals named in the filing: Architect: Prakash Kulkarni Ankur Associates; Engineer: Dhairyashil M Khaire; Engineer: Dipali Kulkarni; Chartered Accountant: Shirkant Mantri; Chartered Accountant: Dinesh Balkrishna Gandhi; Chartered Accountant: Shrikant Mantri and Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Keshar?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback