KAVYA ASHWAMEGH
RG-MH-11330 · RERA P51800007183 · Last updated on MahaRERA portal: 24 Apr 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 22 months past the filed date
- 6 complaints at MahaRERA
- Completion date moved by 42 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
KAVYA ASHWAMEGH is a Others project by KAVYA CONSTRUCTION COMPANY in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800007183 on 17 Aug 2017. Possession was promised by 31 Dec 2024 and is now 22 months past that date. The completion date has moved by 42 months from the original filing. 6 complaints are on record with the regulator.
At a glance
Project
- NameKAVYA ASHWAMEGH
- TypeOthers
- Location
- MUMBAI
- Kurla
- Mumbai Suburban
- 400075
- Pincode400075
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800007183
- ReraGenie IDRG-MH-11330
Builder
- NameKAVYA CONSTRUCTION COMPANY
- Entity typePartnership
- PartnersMANSUKHLAL CHATRABHUJ VORA, JIGNESH MANSUKHLAL VORA
- Declared earlier projects4 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on17 Aug 2017
- Promised completion31 Dec 2024
- Revised completionRevised to 31 Dec 2024 (originally 30 Jun 2021)
- Buildings2 building records
- Documents filed78 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| KAVYA ASHWAMEGH CHSL A WING | NA | 19 | 0 | 0 | 0 | 0 |
| KAVYA ASHWAMEGH CHSL B WING | NA | 19 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 24 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 95%.
KAVYA ASHWAMEGH CHSL A WING45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 35% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 18% |
| Sanitary Fittings within the flats / premises | 3% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 35% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 3% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
KAVYA ASHWAMEGH CHSL B WING44%
| Activity | Progress |
|---|---|
| Excavation | 95% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 35% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 18% |
| Sanitary Fittings within the flats / premises | 3% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 35% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 3% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 24 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed2
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| KAVYA ASHWAMEGH CHSL A WING | 1 | 1 |
| KAVYA ASHWAMEGH CHSL B WING | 1 | 1 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VISION ARCHITECTURAL CONSULTANT |
| Engineer | PARAS COUNSULTANTS |
| Partner | Role in project |
|---|---|
| KAVYA CONSTRUCTION COMPANY | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 24 MONTHS
Reason as filed by the promoterDUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 12 MONTHS
Complaints filed with MahaRERA6
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000044036 | Yogesh Maru | Kavya Construction Company | 07/04/2018 |
| CC006000000500403 | Yogesh Maru | Kavya Construction Company | 10/05/2024 |
| CC006000000100564 | Shah Investments | Kavya Construction Company | 17/08/2019 |
| CC006000000196989 | Tejas Maniar | Kavya Construction Company | 13/05/2021 |
| CC006000000408559 | Rajesh Vinodchandra Shah | KAVYA CONSTRUCTION COMPANY | 20/12/2023 |
| CC12501960 | Rahul Suresh Belwalkar | Mr Nimish Manshuklal Vora | 16/06/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 18 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 18 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 27 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed78
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM - 2A KCC.pdf | 24 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: KCC-FORM-1 apr to june.pdf | 7 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: KCC-FORM-1 july tosep.pdf | 7 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: KCC-FORM-1 oct to sep.pdf | 7 Feb 2025 |
| Certificates of CA (Form 3)File: KCC FORM-3 31122024 (1).pdf | 5 Feb 2025 |
| Certificates of CA (Form 3)File: july to sep 24 form 3.pdf | 5 Feb 2025 |
| Certificates of CA (Form 3)File: oct to dec 24 form 3.pdf | 5 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: KCC-FORM-5 FY 23-24.pdf | 21 Jan 2025 |
| Certificates of CA (Form 3)File: form 3 oct to dec 23.pdf | 15 Jan 2025 |
| Certificates of CA (Form 3)File: form 3 jan to march 24.pdf | 15 Jan 2025 |
| Certificates of CA (Form 3)File: form 3 april to june 24.pdf | 15 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 12 23.pdf | 30 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 03 24.pdf | 30 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 06 24.pdf | 30 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 09 24.pdf | 30 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 12 24.pdf | 30 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2A.pdf | 21 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1-31-12-2023.pdf | 27 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 27 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 6 Jun 2024 |
| Certificates of CA (Form 3)File: Form-3 KCC 06 23.pdf | 27 Oct 2023 |
| Certificates of CA (Form 3)File: Form-3 KCC 09 23.pdf | 27 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Kavya Ashwamegh-Inventory disclosure format.pdf | 25 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2-KCC-06 23.pdf | 5 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2-KCC-09 23.pdf | 5 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: KCC-Ashwamegh- Rera Arc Certificate-06 23.pdf | 3 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: KCC-Ashwamegh- Rera Arc Certificate-09 23.pdf | 3 Oct 2023 |
| Certificates of CA (Form 3)File: Form- 3 KCC 03 21.pdf | 19 Aug 2023 |
| Certificates of CA (Form 3)File: Form -3 KCC 03 22.pdf | 19 Aug 2023 |
| Certificates of CA (Form 3)File: Form- 3 KCC 03 23.pdf | 19 Aug 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 KCC 21-22.pdf | 18 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 KCC 22-23.pdf | 18 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 KCC 03 20.pdf | 17 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 KCC 03 21.pdf | 17 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 KCC 03 22.pdf | 17 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 KCC 03 23.pdf | 17 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A KCC 03 22.pdf | 17 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A KCC 03 23.pdf | 17 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: ASHWAMEGH SOLD UNSOLD (1).pdf | 23 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 03 19.pdf | 6 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 03 20.pdf | 6 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 03 21.pdf | 6 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 03 22.pdf | 6 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 03 23.pdf | 6 May 2023 |
| Certificates of CA (Form 3)File: KCC-Rera SNCO-Form3-Dec-20.pdf | 4 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Kavya Construction Co 20-21.pdf | 5 Jan 2023 |
| Certificates of CA (Form 5)File: KCC FORM 5 17-18.pdf | 1 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: KCC FORM 5 18-19.pdf | 1 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: KCC FORM 5 19-20.pdf | 1 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: kavya Construction Company 19-20.pdf | 28 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A KCC 2020.pdf | 28 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A KCC 2021.pdf | 28 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A KCC 2021.pdf | 28 Jul 2021 |
| Disclosure of sold/ booked inventoryFile: ASHWAMEGH INVENTORY - RERA UPDATION.pdf | 28 Jul 2021 |
| Declaration about Commencement CertificateFile: CC COVERING LETTER ASHWAMEGH.pdf | 21 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 18-19.pdf | 17 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form-2A 19-20.pdf | 14 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21.pdf | 14 Jul 2021 |
| Disclosure of sold/ booked inventoryFile: INVENTORY DISCLOSURE.pdf | 14 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 19-20.pdf | 14 Jul 2021 |
| Certificates of CA (Form 3)File: CA kavya Ashwamegh compressed.pdf | 19 Oct 2018 |
| Certificates of CA (Form 5)File: KAVYA ASHWAMEGH compressed.pdf | 9 Oct 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ashwamegh ARCH.pdf | 30 Aug 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Revaldation CC.pdf | 27 Mar 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf | 29 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CERTIFICATE2.pdf | 29 Jul 2017 |
| Certificates of CA (Form 3)File: ca certificate.pdf | 29 Jul 2017 |
| Building plan approvalFile: IOD.pdf | 27 Jul 2017 |
| Details of encumbrancesFile: ENCRUMBRANCE ASHWAMEGH.pdf | 27 Jul 2017 |
| Building Plan Approval (IOD)File: IOD.pdf | 27 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect form.pdf | 26 Jul 2017 |
| Declaration in FORM BFile: FORM B.pdf | 22 Jul 2017 |
| Layout approvalFile: SANCTION PLAN.pdf | 18 Jul 2017 |
| PAN CardFile: KCC PAN CARD.pdf | 18 Jul 2017 |
| Copy of the legal title reportFile: title.pdf | 18 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: SANCTION PLAN.pdf | 18 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: cc1mb.pdf | 18 Jul 2017 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf | 18 Jul 2017 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Kavya Hill View | THANE | 107 | Completed | Jan 2012 | Late, Mar 2012 |
| Atlas, Thane | THANE | 45 | Completed | Mar 2011 | Late, May 2011 |
| Atlantis, Thane | THANE | 84 | Completed | Mar 2010 | Late, Jul 2010 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 78 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep KAVYA ASHWAMEGH on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MUMBAI6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 286 registered projects within 2 km.
THE VIEWS
AGNEL DEVELOPERS
THE VIEWS II
AGNEL DEVELOPERS
Drushti Emerald
SAMARTH DRUSHTI DEVELOPERS
East Syde
VL GAJAMUKH DEVELOPERS LLP
ROYAL ALTEZZA
SHRI GANESH DEVELOPERS
Damji Shamji Corporate Square - Wing C
Coronate Constructions
See every Mumbai Suburban project, with the district possession charts
Builder: KAVYA CONSTRUCTION COMPANY
KAVYA CONSTRUCTION COMPANY has 1 registration on MahaRERA, including KAVYA ASHWAMEGH. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 4 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that KAVYA ASHWAMEGH shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if KAVYA ASHWAMEGH is delayed beyond 31 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of KAVYA ASHWAMEGH?
The registered promoter entity is KAVYA CONSTRUCTION COMPANY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in KAVYA ASHWAMEGH?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against KAVYA ASHWAMEGH?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for KAVYA ASHWAMEGH?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at KAVYA ASHWAMEGH?
The professionals named in the filing: Architect: VISION ARCHITECTURAL CONSULTANT; Engineer: PARAS COUNSULTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in KAVYA ASHWAMEGH?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback