Registered No litigation declared Residential / Group Housing project

KAVISH RESIDENCY

By DAMLE GANDHE LLP

RG-MH-85597 · RERA P52100054664 · Last updated on MahaRERA portal: 22 Jul 2026

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date
  • Completion date moved by 5 months
  • 1 extension taken
  • Rs 2.00 crore secured on the land, in favour of PUNE MERCHANTS CO OPERATIVE BANK LIMITED

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
6 of 11Construction stages donefurthest along: Internal walls, 80%
3 of 6Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 70 documents Report an error

KAVISH RESIDENCY is a Residential / Group Housing project by DAMLE GANDHE LLP in Pune, Maharashtra, registered with MahaRERA as P52100054664 on 2 Feb 2024. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 5 months from the original filing. 3 of the 6 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameKAVISH RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • BANER ROAD
    • MOHAN NAGAR CO-OPERATIVE HOUSING SOCIETY
    • Baner
    • Haveli
    • Pune
    • 411045
  • Pincode411045
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100054664
  • ReraGenie IDRG-MH-85597

Builder

  • NameDAMLE GANDHE LLP
  • Entity typePartnership
  • PartnersRAJESH ARVIND GANDHE, PRASHANT RAMKRISHNA DAMLE
  • Other registrations1 more →
  • Completed1 of 2
  • Past their filed date1
  • Declared earlier projects1 →

Key dates

1 months past promisethis monthRegisteredFeb 2024First promiseApr 2026Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on2 Feb 2024
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 1 Apr 2026)
  • Buildings1 building record
  • Documents filed70 files

Current status

50%3 of 6 units booked
71.6%Work done, per cost certificate

Figures as on 22 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KAVISH RESIDENCYNA33606

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 80%.

KAVISH RESIDENCY: 69% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises16%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.62%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 22 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed10

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots10
Closed/Covered10

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area321 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofPUNE MERCHANTS CO OPERATIVE BANK LIMITED
Secured amountRs 2.00 crore
CERSAI search filedYes
Declared on11 Feb 2026
LandownerVillageDistrict
MOHAN NAGAR CO-OP HOUSING SOCIETY LTDPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPUNE MUNICIPAL CORPORATION
Permissible FSI870.0
Proposed, not sanctioned519 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDECCAN, PUNE
Estimated costRs 3.56 cr
Cost incurredRs 2.55 cr
Work done71.64%
BuildingWingEstimatedIncurred
KAVISH RESIDENCYNARs 3.30 crRs 2.33 cr
-NARs 26.00 lakhRs 22.10 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVAISHALI GANDHE
ArchitectPROLIFEC DESIGNS STUDIO
EngineerKanitkar and Kulkarni
EngineerTALATHI CONSTRUCTIONS
EngineerPrashant Ramkrishna Damle
Chartered AccountantDB GANDHI AND ASSOCIATES
PartnerRole in project
DAMLE GANDHE LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA11022619799Apr 2026 → Sep 2026

Reason as filed by the promoterWe received Basic sanction at first, however excavation royal took time than anticipated. After that Revised sanction took delay and construction period was delayed parallelly. Now that we have revised sanction with us to complete the building we need extension. One the extension is granted we will do a correction application for updating all the revised units

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Sep 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Sep 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Sep 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed70

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A Quality Assurance Certificate.pdf22 Jul 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate.pdf21 Jul 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate.pdf21 Jul 2026
Withdrawal Update Form 3File: Form 3 CA Certificate.pdf21 Jul 2026
Withdrawal Update Form 1File: Form 1.pdf20 Jun 2026
Withdrawal Update Form 2File: Form 2.pdf20 Jun 2026
Withdrawal Update Form 3File: Form 3.pdf20 Jun 2026
Form 2A (FY 2024-2025)File: Form 2A FY 2024-25.pdf5 May 2026
Form 5 (FY 2024-2025)File: Form 5 FY 2024-25.pdf5 May 2026
Form 1File: Architect Certificate.pdf10 Feb 2026
Form 2File: Engineer Certificate.pdf10 Feb 2026
Form 3File: CA Certificate_compressed.pdf10 Feb 2026
Disclosure of Sold and Booked InventoryFile: Sold_Unsold Inventory.pdf10 Feb 2026
Form 1File: Architect Certificate - 30062025.pdf1 Jan 2026
Form 2File: Engineers Certificate - 30062025.pdf1 Jan 2026
Form 3File: CA Certificate - Form 3 - 30062025.pdf1 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventories - 30062025.pdf1 Jan 2026
Form 1File: Architect Certificate - 30092025.pdf1 Jan 2026
Form 2File: Engineers Certificate - 30092025.pdf1 Jan 2026
Form 3File: CA Certificate - Form 3 - 30092025_compressed.pdf1 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventories - 30092025.pdf1 Jan 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate.pdf16 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate_compressed.pdf16 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer Certificate.pdf16 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate Q3.pdf25 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate Q3_compressed.pdf25 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate Q3.pdf25 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventories Q3.pdf25 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate - 30062024.pdf6 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate - 30092024.pdf6 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - Form - 3 - 30062024_compressed.pdf6 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - Form - 3 - 30092024.pdf6 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - 30062024.pdf6 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - 30092024.pdf6 Nov 2024
Disclosure of sold/ booked inventoryFile: Sold-Unsold invetory - 30062024.pdf6 Nov 2024
Disclosure of sold/ booked inventoryFile: Sold-Unsold invetory - 30092024.pdf6 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 01012024 to 31032024.pdf13 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 01012024 to 31032024.pdf13 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventories 01012024 to 31032024.pdf13 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate 01012024 to 31032024_compressed.pdf13 May 2024
Commencement Certificates / NA Order for plotted developmentFile: Plinth checking certificate.pdf31 Jan 2024
Other - LegalFile: IMG-20240117-WA0001 (1).pdf17 Jan 2024
Other - LegalFile: 5.pdf15 Jan 2024
Other - LegalFile: mohan nagar NOC DGLLP.pdf3 Jan 2024
Other - TechnicalFile: Signed_173583_AppendixF.pdf4 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf18 Oct 2023
Proforma of Agreement for saleFile: 16 Proforma of the agreement for sale_Final.pdf18 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate_compressed.pdf5 Oct 2023
CERSAI detailsFile: No Cersai report.pdf2 Oct 2023
Layout approvalFile: 6 SANCTIONED PLAN 01-01.pdf23 Sep 2023
Building plan approvalFile: 6 SANCTIONED PLAN 01-01.pdf23 Sep 2023
PAN CardFile: 2 DGLLP PAN Card.pdf23 Sep 2023
Copy of the legal title reportFile: 3 Title Search 30 Years_compressed.pdf23 Sep 2023
Details of encumbrances concerned to FinanceFile: 4 Details of encumbrances concerned to Finance.pdf23 Sep 2023
Details of encumbrances concerned to FinanceFile: 5 Details of encumbrances concerned to Legal.pdf23 Sep 2023
Details of encumbrances concerned to LegalFile: 4 Details of encumbrances concerned to Finance.pdf23 Sep 2023
Details of encumbrances concerned to LegalFile: 5 Details of encumbrances concerned to Legal.pdf23 Sep 2023
Copy of Layout Approval (in case of layout)File: 6 SANCTIONED PLAN 01-01.pdf23 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: 6 SANCTIONED PLAN 01-01.pdf23 Sep 2023
Commencement Certificates / NA Order for plotted developmentFile: 8 Commencement Certificate.pdf23 Sep 2023
Commencement Certificates / NA Order for plotted developmentFile: 8 Architect Certificate plinth checking.pdf23 Sep 2023
Declaration about Commencement CertificateFile: 9 Declaration about Commencement Certificate.pdf23 Sep 2023
Declaration in FORM BFile: 10 Form B Affidavit cum Declaration.pdf23 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 11 Architect Certificate_Rera.pdf23 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: 23 Annexure A - Disclosure - PRD.pdf23 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: 23 Annexure A - Disclosure - RAG.pdf23 Sep 2023
Proforma of Allotment letterFile: 16 Proforma of the allotment letter.pdf23 Sep 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 19 Separate Bank Account details including no encumbrances on the Bank.pdf23 Sep 2023
Deviation Report with respect to Allotment letterFile: 17 Deviation Report with respect to Allotment letter.pdf23 Sep 2023
Deviation Report with respect to model copy of AgreementFile: 18 Deviation Report with respect to model copy of Agreement.pdf23 Sep 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
RIDDHISH RESIDENCYPlot no B - 43 Survey No 94-1 part 95 96-1-1 96-1-2 96-2 96-4 97 at Mohannagar Co- op Hsg Society Baner Haveli Pune - 41104510CompletedMar 2018Late, Mar 2018

How this compares with Pune

50%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 5 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KAVISH RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MOHAN NAGAR CO-OPERATIVE HOUSING SOCIETY13,700+ in Pune

2 kmKAVISH RESIDENCYCompleted 133Lapsed / revoked 39Other 90Dot size: filed unitsN

Filed coordinates, straight-line distance. 262 registered projects within 2 km.

Builder: DAMLE GANDHE LLP

Damle Gandhe LLP has 2 registrations on MahaRERA, including Riddhish Residency and KAVISH RESIDENCY. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if KAVISH RESIDENCY is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KAVISH RESIDENCY?

The registered promoter entity is DAMLE GANDHE LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KAVISH RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KAVISH RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KAVISH RESIDENCY?

The professionals named in the filing: Architect: VAISHALI GANDHE; Architect: PROLIFEC DESIGNS STUDIO; Engineer: Kanitkar and Kulkarni; Engineer: TALATHI CONSTRUCTIONS; Engineer: Prashant Ramkrishna Damle; Chartered Accountant: DB GANDHI AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KAVISH RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KAVISH RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KAVISH RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.