Home / Browse projects / Nagpur, Maharashtra / Kasturi Garden

Registered No litigation declared Residential / Group Housing project

Kasturi Garden

By SKY DEVELOPERS AND PROMOTERS INDIA PVT. LTD.

RG-MH-87497 · RERA P50500021136 · Last updated on MahaRERA portal: 18 Jan 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2030Possession promisedno revision filed
14 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 90%
75 of 220Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 56 documents Report an error

Kasturi Garden is a Residential / Group Housing project by SKY DEVELOPERS AND PROMOTERS INDIA PVT. LTD. in Nagpur, Maharashtra, registered with MahaRERA as P50500021136 on 10 Jun 2019. Possession is promised by 30 Dec 2030. 145 of the 220 units on this registration are recorded sold or booked, and 14 of 33 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameKasturi Garden
  • TypeResidential / Group Housing
  • Location
    • WELA HARI ROAD
    • Gotal Panjari
    • Nagpur (Rural)
    • Nagpur
    • 441108
  • Pincode441108
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500021136
  • ReraGenie IDRG-MH-87497

Builder

  • NameSKY DEVELOPERS AND PROMOTERS INDIA PVT. LTD.
  • Entity typeCompany
  • Managing DirectorsSAIFUDDIN FIDAALI DAMA, YUSUF HASANALI BEHRAINWALA, KHUZEMA QUTBUDDIN MAIMOON
  • Other registrations5 more →
  • Completed3 of 6
  • Declared earlier projects3 →

Key dates

this monthRegisteredJun 2019PromisedDec 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 Jun 2019
  • Promised completion30 Dec 2030
  • Revised completionNone
  • Buildings3 building records
  • Documents filed56 files

Current status

66%145 of 220 units booked
79.6%Work done, per cost certificate

Figures as on 18 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA5580080
WING BNA5550050
WING CNA5590090

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 18 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 90%.

WING A55%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks55%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING B19%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor5%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING C82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 18 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes45%
Water SupplyYes40%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes45%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingYes40%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes40%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes45%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed77

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots77
Open Space77
BuildingOpen SpaceTotal
WING A2727
WING B1717
WING C3333

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area7,640 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on22 Aug 2025

Approvals and building plan

Sanctioning authorityNagpur Metropolitan Region Development Authority
Permissible FSI22376.0
Proposed, not sanctioned12,376 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR PATNI BHAWAN GANDHIBAGH NAGPUR 440002
Estimated costRs 81.75 cr
Cost incurredRs 65.10 cr
Work done79.64%
BuildingWingEstimatedIncurred
WING ANARs 27.25 crRs 21.70 cr
WING BNARs 27.25 crRs 21.70 cr
WING CNARs 27.25 crRs 21.70 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARC ASHFAQUE HUSAIN
ArchitectRAJENDRA R SULKE
ArchitectALOK LUNIA
EngineerR & G ASSOCIATES
EngineerAshfaque Husain
Chartered AccountantCA PARVEZ ALI
Chartered AccountantJayendra Chilate
PartnerRole in project
SKY DEVELOPERS AND PROMOTERS INDIA PVT. LTD.-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12500437Kasturi Garden Flat Owners AOPSKY DEVELOPERS AND PROMOTERS INDIA PVT. LTD.10/02/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 May 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 May 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 May 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 May 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2030

Documents filed56

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: form 1- kasturi garden.pdf18 Jan 2026
Withdrawal Update Form 2File: form 2 - kasturi garden.pdf18 Jan 2026
Withdrawal Update Form 3File: form 3-kasturi garden.pdf18 Jan 2026
Withdrawal Update Form 1File: Form1 Kasturi Garden.pdf29 Oct 2025
Withdrawal Update Form 2File: Form2 Kasturi Garden.pdf29 Oct 2025
Withdrawal Update Form 3File: Form3 Kasturi Garden_compressed.pdf29 Oct 2025
Form 1File: FORM1 Jan-March2025.pdf24 Aug 2025
Form 2File: FORM 2 Jan-March 2025.pdf24 Aug 2025
Form 3File: Form3 Jan-March25 KG_compressed.pdf24 Aug 2025
Disclosure of Sold and Booked InventoryFile: sold inventory jan-march25.pdf24 Aug 2025
Form 5 (FY 2021-2022)File: CA (Form 5) (FY 2021-22).pdf24 Aug 2025
Form 5 (FY 2022-2023)File: CA (Form 5) (FY 2022-23).pdf24 Aug 2025
Form 5 (FY 2023-2024)File: CA (Form 5) (FY 2023-24).pdf24 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 April to June24 kasturi garden.pdf7 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 July to Sep24 Kasturi garden.pdf7 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 oct to dec24 kasturi garden.pdf7 Feb 2025
Certificates of CA (Form 3)File: Form3 July sep24 kasturi garden_compressed.pdf7 Feb 2025
Certificates of CA (Form 3)File: Form3 oct dec24 kasturi garden_compressed.pdf7 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 July to Sep24 kasturi garden.pdf7 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 oct to dec24 kasturi garden.pdf7 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form5 23-24 kasturi garden.pdf7 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 Karturi Garden.pdf8 Aug 2024
Disclosure of sold/ booked inventoryFile: sold inventory Kasturi Garden_compressed.pdf8 Aug 2024
Certificates of CA (Form 3)File: Form3 Kasturi Garden_compressed.pdf8 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1 KASTURI GARDEN.pdf23 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 Kasturi garden.pdf23 Apr 2024
Disclosure of sold/ booked inventoryFile: ilovepdf_merged (2)_compressed.pdf23 Apr 2024
Certificates of CA (Form 3)File: form3 Kasturi garden_compressed.pdf23 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form1 sep.pdf22 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form1 kasturi garden.pdf22 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf22 Feb 2024
Disclosure of sold/ booked inventoryFile: K.pdf17 Feb 2024
Disclosure of sold/ booked inventoryFile: kasturi garden sold inventory_compressed.pdf17 Feb 2024
Certificates of CA (Form 3)File: kasturi garden form 3_compressed.pdf17 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2 kasturi garden.pdf31 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A kasturi Garden.pdf31 Oct 2023
Certificates of CA (Form 3)File: FORM - 3 CA Certificate.pdf31 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 kasturi garden.pdf31 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1 Kasturi Garden_compressed.pdf21 Apr 2023
Certificates of CA (Form 3)File: FORM -3 kasturi garden_compressed_compressed.pdf19 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM -2kasturi garden_compressed.pdf18 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM -5 kasturi garden_compressed.pdf18 Apr 2023
OtherFile: Plinth Level Certificate Kasturi Garden-converted.pdf6 Aug 2020
Certificates of CA (Form 3)File: CA form3_compressed.pdf3 Jun 2019
Building plan approvalFile: sanction plan.pdf30 May 2019
Layout approvalFile: layout plan.pdf30 May 2019
PAN CardFile: SKY PAN.pdf30 May 2019
Copy of the legal title reportFile: garden legal title report_compressed.pdf30 May 2019
Details of encumbrancesFile: garden legal title report_compressed.pdf30 May 2019
Copy of Layout Approval (in case of layout)File: layout plan.pdf30 May 2019
Building Plan Approval (IOD)File: sanction plan.pdf30 May 2019
Commencement Certificates / NA Order for plotted developmentFile: commencement certificate_compressed.pdf30 May 2019
Declaration in FORM BFile: form B.pdf30 May 2019
Proforma of Allotment letterFile: alotment letter.pdf30 May 2019
Proforma of Allotment letterFile: undertaking for ATS.pdf30 May 2019
OtherFile: amalgamation letter.pdf30 May 2019

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
kASTURI HEIGHTP50500004982Nagpur144Aug 2017OngoingDec 2026Registered original: Dec 2023Not due yet
J. K. HEIGHTSP50600023850SARAFA BAZAAR, Bhandara79Jan 2020OngoingDec 2025Not delivered

How this compares with Nagpur

66%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Kasturi Garden on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near WELA HARI ROAD2,800+ in Nagpur

2 kmKasturi GardenCompleted 17Lapsed / revoked 9Other 41Dot size: filed unitsN

Filed coordinates, straight-line distance. 67 registered projects within 2 km.

Builder: SKY DEVELOPERS AND PROMOTERS INDIA PVT. LTD.

SKY DEVELOPERS AND PROMOTERS INDIA PVT. LTD. has 6 registrations on MahaRERA, including kASTURI HEIGHT and KASTURI APPARTMENTS. Its filings disclose 3 earlier MahaRERA projects, none completed yet. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if Kasturi Garden is delayed beyond 30 Dec 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Kasturi Garden?

The registered promoter entity is SKY DEVELOPERS AND PROMOTERS INDIA PVT. LTD., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Kasturi Garden?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Kasturi Garden?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Kasturi Garden?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Kasturi Garden?

The professionals named in the filing: Architect: ARC ASHFAQUE HUSAIN; Architect: RAJENDRA R SULKE; Architect: ALOK LUNIA; Engineer: R & G ASSOCIATES; Engineer: Ashfaque Husain; Chartered Accountant: CA PARVEZ ALI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Kasturi Garden?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Kasturi Garden. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Kasturi Garden to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.