ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / KASTURI APPARTMENTS

Completed No litigation declared Residential / Group Housing project

KASTURI APPARTMENTS

By SKY DEVELOPERS AND PROMOTERS INDIA PVT. LTD.

RG-MH-00534 · RERA P50500000856 · Last updated on MahaRERA portal: 24 Feb 2022

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
3 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 17 documents Report an error

KASTURI APPARTMENTS is a Residential / Group Housing project by SKY DEVELOPERS AND PROMOTERS INDIA PVT. LTD. in Nagpur, Maharashtra, registered with MahaRERA as P50500000856 on 23 Jul 2017. The registration is recorded completed; possession was promised by 30 Dec 2021. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NameKASTURI APPARTMENTS
  • TypeResidential / Group Housing
  • Location
    • MIDC KALMESHWAR ROAD
    • JSW MAIN GATE
    • Kalmeshwar (MCL)
    • Kalameshwar
    • Nagpur
    • 441501
  • Pincode441501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500000856
  • ReraGenie IDRG-MH-00534

Builder

  • NameSKY DEVELOPERS AND PROMOTERS INDIA PVT. LTD.
  • Entity typeCompany
  • Managing DirectorsSAIFUDDIN FIDAALI DAMA, YUSUF HASANALI BEHRAINWALA, KHUZEMA QUTBUDDIN MAIMOON
  • Other registrations5 more →
  • Completed3 of 6
  • Declared earlier projects3 →

Key dates

this monthRegisteredJul 2017First promiseDec 2019Revised toDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on23 Jul 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed17 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KASTURI APPARTMENTSNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Feb 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

KASTURI APPARTMENTS: 27% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Feb 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed96

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots96
Closed/Covered96

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,997 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2383.33
Proposed, not sanctioned2,383 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPATNI BHAWAN, 1ST FLOOR,GANDHIBAGH, NAGPUR, 440002

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVINIT JUGALKISHOR SHRIVASTAVA
PartnerRole in project
SKY DEVELOPERS AND PROMOTERS INDIA PVT. LTD.-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50500002174Dec 2019 → Dec 2020

Reason as filed by the promoterSlow Booking and non development of layout

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 2 Feb 2022

Documents filed17

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: 6ee3ff24d66c4bce9121821b137202ad-0001-converted.pdf24 Feb 2022
Architect’s Certificate on Completion of Project (Form 4)File: 6ee3ff24d66c4bce9121821b137202ad-0001-converted.pdf24 Feb 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Kalmeshwar O C-converted.pdf2 Feb 2022
Certificates of CA (Form 5)File: KA.pdf6 Oct 2018
Certificates of CA (Form 3)File: FORM 3 CA FINAL.pdf15 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT-ilovepdf-compressed.pdf14 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM ENGINEER CERTIFICATE FINAL-ilovepdf-compressed.pdf14 Jul 2017
Building plan approvalFile: BLDG PERMIT-ilovepdf-compressed.pdf12 Jul 2017
Layout approvalFile: LAYOUT MAP KALMESHWAR-ilovepdf-compressed.pdf12 Jul 2017
PAN CardFile: SKY PAN.pdf12 Jul 2017
Copy of the legal title reportFile: kalmeshwar title report-ilovepdf-compressed.pdf12 Jul 2017
Details of encumbrancesFile: kalmeshwar title report-ilovepdf-compressed.pdf12 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT MAP KALMESHWAR-ilovepdf-compressed.pdf12 Jul 2017
Building Plan Approval (IOD)File: BLDG PERMIT-ilovepdf-compressed.pdf12 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: BLDG PERMIT-ilovepdf-compressed.pdf12 Jul 2017
Declaration in FORM BFile: form B kalmeshwar-ilovepdf-compressed.pdf12 Jul 2017
Proforma of Allotment letterFile: AGREEMENT AND ALLOTMENT AS PER RERA.pdf12 Jul 2017

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date2 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Kasturi GardenP50500021136WELA HARI ROAD, Nagpur220Jun 2019OngoingDec 2030Not due yet
kASTURI HEIGHTP50500004982Nagpur144Aug 2017OngoingDec 2026Registered original: Dec 2023Not due yet
J. K. HEIGHTSP50600023850SARAFA BAZAAR, Bhandara79Jan 2020OngoingDec 2025Not delivered

How this compares with Nagpur

13%of Nagpur projects moved their completion datethis one moved by 24 months
22%of Nagpur registrations have lapsed or been cancelledthis one is completed

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KASTURI APPARTMENTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near JSW MAIN GATE2,800+ in Nagpur

2 kmKASTURI APPARTMENTSCompleted 1Other 4Dot size: filed unitsN

Filed coordinates, straight-line distance. 5 registered projects within 2 km.

Builder: SKY DEVELOPERS AND PROMOTERS INDIA PVT. LTD.

SKY DEVELOPERS AND PROMOTERS INDIA PVT. LTD. has 6 registrations on MahaRERA, including kASTURI HEIGHT and KASTURI APPARTMENTS. Its filings disclose 3 earlier MahaRERA projects, none completed yet. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if KASTURI APPARTMENTS is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KASTURI APPARTMENTS?

The registered promoter entity is SKY DEVELOPERS AND PROMOTERS INDIA PVT. LTD., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KASTURI APPARTMENTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KASTURI APPARTMENTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KASTURI APPARTMENTS?

The professionals named in the filing: Architect: VINIT JUGALKISHOR SHRIVASTAVA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KASTURI APPARTMENTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KASTURI APPARTMENTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KASTURI APPARTMENTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.