Home / Browse projects / Nashik, Maharashtra / KANKARIYAS AVENUE

Registration lapsed No litigation declared Others project

KANKARIYAS AVENUE

By OM SANDEEPKUMAR KANKARIYA

RG-MH-13978 · RERA P51600030398 · Last updated on MahaRERA portal: 19 Jun 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date
  • Completion date moved by 8 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
1 of 11Construction stages donefurthest along: Basement (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 20 documents Report an error

KANKARIYAS AVENUE is a Others project by OM SANDEEPKUMAR KANKARIYA in Nashik, Maharashtra, registered with MahaRERA as P51600030398 on 20 Aug 2021. Possession was promised by 31 Dec 2023 and is now 34 months past that date. The completion date has moved by 8 months from the original filing.

At a glance

Project

  • NameKANKARIYAS AVENUE
  • TypeOthers
  • Location
    • PATHARDI SHIWAR
    • PATHARDI-1
    • Nashik
    • 422009
  • Pincode422009
  • RERA no.P51600030398
  • ReraGenie IDRG-MH-13978

Builder

  • NameOM SANDEEPKUMAR KANKARIYA
  • Entity typeIndividual

Key dates

34 months past promisethis monthRegisteredAug 2021First promiseApr 2023Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on20 Aug 2021
  • Promised completion31 Dec 2023
  • Revised completionRevised to 31 Dec 2023 (originally 30 Apr 2023)
  • Buildings1 building record
  • Documents filed20 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KANKARIYAS AVENUENA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Jun 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

KANKARIYAS AVENUE: 9% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 Jun 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed46

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots46
Closed/Covered34
Open Space12

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area528 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1330.08
Proposed, not sanctioned1,330 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNASARDI BRIDGE UNTWADI NASHIK

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDHIRAJ WALUNJ
EngineerAmolkumar M Bhoi
Chartered AccountantANAND RATHI & ASSOCIATES
PartnerRole in project
OM SANDEEPKUMAR KANKARIYA-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51600017438Apr 2023 → Dec 2023

Reason as filed by the promoterTHE PROJECT HAS BEEN COMPLETED AND THE PROJECT ARCHITECT HAS ALSO ISSUED THE PROJECT COMPLETIN CERTIFICATE IN FORM 4. THE SAME HAS BEEN UPLOADED ON MAHARERA. WE ARE IN THE PROCESS OF OBTAINING THE COMPLETION/OCCUPANCY CERTIFICATE FROM NASHIK MUNICIPAL CORPORATION, WE THEREFORE REQUEST YOU PLEASE EXTEND THE DATE OF COMPLETION TO 31.12.2023 ON MAHARERA.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Jul 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Aug 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Jul 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 19 Jun 2024

Documents filed20

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: completion certificate.pdf19 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5.pdf31 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form2a 22.pdf30 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: forn 2a.pdf30 Aug 2023
Disclosure of sold/ booked inventoryFile: sold unsold.pdf30 Aug 2023
Declaration in FORM BFile: 1.pdf29 Aug 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: form 4.pdf3 Jun 2023
Layout approvalFile: LAYOUYFINAL_compressed.pdf10 Aug 2021
Copy of Layout Approval (in case of layout)File: LAYOUYFINAL_compressed.pdf10 Aug 2021
Proforma of Allotment letterFile: PROFORMA ALLOTMENT LETTER.pdf19 Jul 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf13 Jul 2021
Building plan approvalFile: PLAN_compressed.pdf8 Jul 2021
PAN CardFile: PAN.pdf8 Jul 2021
Copy of the legal title reportFile: TITLE REPORT.pdf8 Jul 2021
Details of encumbrancesFile: 20210707082835.pdf8 Jul 2021
Building Plan Approval / NA Order for plotted developmentFile: PLAN_compressed.pdf8 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT_compressed.pdf8 Jul 2021
Declaration about Commencement CertificateFile: declarationcommencementcertificate_compressed.pdf8 Jul 2021
Declaration in FORM BFile: form b_compressed.pdf8 Jul 2021
Proforma of Allotment letterFile: DRAFT AGMT.pdf8 Jul 2021

How this compares with Nashik

10%of Nashik projects moved their completion datethis one moved by 8 months
19%of Nashik registrations have lapsed or been cancelledthis one is among them

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KANKARIYAS AVENUE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PATHARDI-14,100+ in Nashik

Builder: OM SANDEEPKUMAR KANKARIYA

OM SANDEEPKUMAR KANKARIYA has 1 registration on MahaRERA, including KANKARIYAS AVENUE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What does it mean that KANKARIYAS AVENUE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if KANKARIYAS AVENUE is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KANKARIYAS AVENUE?

The registered promoter entity is OM SANDEEPKUMAR KANKARIYA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KANKARIYAS AVENUE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KANKARIYAS AVENUE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KANKARIYAS AVENUE?

The professionals named in the filing: Architect: DHIRAJ WALUNJ; Engineer: Amolkumar M Bhoi; Chartered Accountant: ANAND RATHI & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KANKARIYAS AVENUE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KANKARIYAS AVENUE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KANKARIYAS AVENUE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.