Home / Browse projects / Pune, Maharashtra / KAMALRAJ DATTAVIHAR E AND H
KAMALRAJ DATTAVIHAR E AND H
RG-MH-22598 · RERA P52100031669 · Last updated on MahaRERA portal: 22 Jan 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 5 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
KAMALRAJ DATTAVIHAR E AND H is a Residential / Group Housing project by KAMALRAJ ESTATE in Pune, Maharashtra, registered with MahaRERA as P52100031669 on 3 Nov 2021. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 5 months from the original filing. 199 of the 224 units on this registration are recorded sold or booked, and 16 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameKAMALRAJ DATTAVIHAR E AND H
- TypeResidential / Group Housing
- Location
- DEHU ROAD
- BORHADEWADI
- Moshi
- Haveli
- Pune
- 412105
- Pincode412105
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100031669
- ReraGenie IDRG-MH-22598
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on3 Nov 2021
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 31 Jul 2025)
- Buildings2 building records
- Documents filed46 files
Current status
Figures as on 22 Jan 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| KAMALRAJ DATTAVIHAR E | NA | 16 | 14 | 112 | 0 | 112 |
| KAMALRAJ DATTAVIHAR H | NA | 16 | 14 | 112 | 0 | 112 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 22 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
16 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 90%.
KAMALRAJ DATTAVIHAR E81%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
KAMALRAJ DATTAVIHAR H81%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Progress on shared amenities15
As on 22 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 90% |
| Water Supply | Yes | 90% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 90% |
| Landscaping & Tree Planting | Yes | 85% |
| Street Lighting | Yes | 90% |
| Community Buildings | Yes | 90% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 90% |
| Solid Waste Management And Disposal | Yes | 90% |
| Water conservation /Rain water harvesting | Yes | 90% |
| Energy managemcnt | Yes | 90% |
| Fire protection and fire safety requirements | Yes | 90% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed110
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| KAMALRAJ DATTAVIHAR E | 55 | 55 |
| KAMALRAJ DATTAVIHAR H | 55 | 55 |
Land and ownership5
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| YOGESH DATTATRAY BORATE | Moshi | Pune |
| SANDEEP DATTATRAY BORATE | Moshi | Pune |
| DEEPAK DATTATRAY BORATE | Moshi | Pune |
| VIKAS DATTATRAY BORATE | Moshi | Pune |
| RADHIKA DATTATRAY BORATE | Moshi | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| KAMALRAJ DATTAVIHAR E | NA | Rs 19.80 cr | Rs 19.58 cr |
| KAMALRAJ DATTAVIHAR H | NA | Rs 19.80 cr | Rs 19.58 cr |
| - | NA | Rs 4.80 cr | Rs 4.78 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VIKAS ACHALKAR |
| Engineer | AMOL MANKAR |
| Chartered Accountant | AGH AND ASSOCIATES |
| Chartered Accountant | Chandrashekhar Ramanlal Luniya |
| Partner | Role in project |
|---|---|
| KAMALRAJ ESTATE | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDelay due to lack of labour availability, rainy season, some paper work related to project such as revised plan, 95% of work completed. Only 5% Work is balance, which will completed before 31st December 2025.
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12504461 | Vishram Sacchidanand Khatavakar | KAMALRAJ ESTATE | 14/12/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Oct 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 18 Nov 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Nov 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed46
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Dattavihar E and H - Form 1.pdf | 22 Jan 2026 |
| Withdrawal Update Form 2File: Form-2-25-26-3rd Qtr Dattavihar E and H.pdf | 22 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 - Dec 25 - Dattavihar E and H.pdf | 22 Jan 2026 |
| Form 5 (FY 2024-2025)File: Form 5 DV E and H.pdf | 29 Nov 2025 |
| Withdrawal Update Form 1File: Dattavihar E and H - Form 1.pdf | 31 Oct 2025 |
| Withdrawal Update Form 2File: Form 2 - Dattavihar Eu0026H 25-26 - 2nd Qtr.pdf | 31 Oct 2025 |
| Withdrawal Update Form 3File: Form - 3 DV- E u0026 H- 25-26 - Q2.pdf | 31 Oct 2025 |
| Withdrawal Update Form 1File: Kamalraj Form 1 DV E and H.pdf | 21 Jul 2025 |
| Withdrawal Update Form 2File: Dattavihar E and H Form 2.pdf | 21 Jul 2025 |
| Withdrawal Update Form 3File: DV E and H.pdf | 21 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DV E H.pdf | 18 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Dattavihar E H.pdf | 14 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Dattavihar E H.pdf | 31 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DV- E H - Dec-24.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kamalraj Form 1 - Dattavihar E H.pdf | 18 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Dv E H - Sept 24.pdf | 18 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 DV E H.pdf | 17 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DV E H.pdf | 20 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DV E and H.pdf | 20 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DV E and H March 24.pdf | 20 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 DV E and H Dec 23.pdf | 20 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 DV E and H Dec23.pdf | 12 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 DV - E and H.pdf | 8 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 DV - E and H.pdf | 8 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect DV E H.pdf | 11 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 22.pdf | 1 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22 Dattavihar E and H.pdf | 8 Dec 2022 |
| Layout approvalFile: Plan.pdf | 18 Nov 2022 |
| Building plan approvalFile: Plan.pdf | 18 Nov 2022 |
| Copy of Layout Approval (in case of layout)File: Plan.pdf | 18 Nov 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan.pdf | 18 Nov 2022 |
| Layout approvalFile: E H Sanction plan layout.pdf | 25 Oct 2021 |
| Building plan approvalFile: E H Sanction plan layout.pdf | 25 Oct 2021 |
| PAN CardFile: KE Pancard.pdf | 25 Oct 2021 |
| Copy of the legal title reportFile: E H SEARCH REPORT.pdf | 25 Oct 2021 |
| Details of encumbrancesFile: E H Encumbrances.pdf | 25 Oct 2021 |
| Copy of Layout Approval (in case of layout)File: E H Sanction plan layout.pdf | 25 Oct 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: E H Sanction plan layout.pdf | 25 Oct 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: E H commencement certificate.pdf | 25 Oct 2021 |
| Declaration about Commencement CertificateFile: E H Declration for Commencement certificate.pdf | 25 Oct 2021 |
| Declaration in FORM BFile: E H Developer Form B.pdf | 25 Oct 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: E H Architect Form 1.pdf | 25 Oct 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: E H Engineer Form 2.pdf | 25 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: E H Engineer Quality Certificate 2A.pdf | 25 Oct 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: E H Building Form No 3.pdf | 25 Oct 2021 |
| Proforma of Allotment letterFile: E H Rera ATS.pdf | 25 Oct 2021 |
Promoter's earlier projects8
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| KAMALRAJ AKSHARDHAM B and C BUILDINGP52100056285 | CHOVISAWADI, Pune | 220 | May 2024 | Ongoing | Dec 2028 | Not due yet |
| KAMALRAJ AKSHARDHAM A BUILDINGP52100079718 | CHOVISAWADI, Pune | 108 | Mar 2025 | Ongoing | Dec 2028 | Not due yet |
| Kamalaraj Athens B and CP52100028848 | Kaveri Nagar, Pune | 182 | Apr 2021 | Ongoing | Jun 2027 | Not due yet |
| KAMALRAJ ATHENS AP52100054711 | KAVERI NAGAR, Pune | 112 | Feb 2024 | Ongoing | Jun 2027 | Not due yet |
| KAMALRAJ DATTAVIHAR CENTRALP52100025876 | Borade Wadi, Pune | 124 | Jul 2020 | Completed | Sep 2025Registered original: Mar 2022 | Feb 2024 |
| KAMALRAJ DATTAVIHAR G - F BUILDINGP52100025201 | BORADE WADI, Pune | - | Mar 2020 | Completed | Dec 2023 | Dec 2023 |
| Kamalraj Datta Vihar D BuildingP52100015707 | Borhadewadi ( Moshi ), Pune | - | Mar 2018 | Completed | Jun 2022 | Late, Oct 2022 |
| Kamalraj Datta Vihar A BldngP52100002971 | MOSHI, Pune | - | Aug 2017 | Completed | Dec 2021Registered original: Dec 2019 | Late, Oct 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 8 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 46 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep KAMALRAJ DATTAVIHAR E AND H on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BORHADEWADI13,700+ in Pune
Filed coordinates, straight-line distance. 434 registered projects within 2 km.
TANISH PARK
TANISH DEVELOPERS
Ajinkya Towers
APAK Bussiness Innovation Pvt Ltd
SILVER GARDENIA
SILVER PROMOTERS AND DEVELOPERS
Mangalam Life Park
Mangalam Buildcorp
SingaPune Ph 3
Xrbia Mirth Properties LLP
SingaPune Ph 2
Xrbia Mirth Properties LLP
Builder: KAMALRAJ ESTATE
KAMALRAJ ESTATE has 9 registrations on MahaRERA, including Kamalraj Datta Vihar A Bldng and Kamalraj Datta Vihar D Building. Its filings disclose 9 earlier MahaRERA projects: declares 2 of 4 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that KAMALRAJ DATTAVIHAR E AND H shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if KAMALRAJ DATTAVIHAR E AND H is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of KAMALRAJ DATTAVIHAR E AND H?
The registered promoter entity is KAMALRAJ ESTATE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in KAMALRAJ DATTAVIHAR E AND H?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against KAMALRAJ DATTAVIHAR E AND H?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for KAMALRAJ DATTAVIHAR E AND H?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at KAMALRAJ DATTAVIHAR E AND H?
The professionals named in the filing: Architect: VIKAS ACHALKAR; Engineer: AMOL MANKAR; Chartered Accountant: AGH AND ASSOCIATES; Chartered Accountant: Chandrashekhar Ramanlal Luniya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in KAMALRAJ DATTAVIHAR E AND H?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback