Home / Browse projects / Pune, Maharashtra / KAMALRAJ DATTAVIHAR CENTRAL

Completed No litigation declared Commercial project

KAMALRAJ DATTAVIHAR CENTRAL

By KAMALRAJ ESTATE

RG-MH-16188 · RERA P52100025876 · Last updated on MahaRERA portal: 22 Jul 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 42 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2025Possession promisedregistration recorded completed
7 of 11Construction stages donefurthest along: Internal walls, 90%
95 of 124Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 42 documents Report an error

KAMALRAJ DATTAVIHAR CENTRAL is a Commercial project by KAMALRAJ ESTATE in Pune, Maharashtra, registered with MahaRERA as P52100025876 on 24 Jul 2020. The registration is recorded completed; possession was promised by 30 Sep 2025. The completion date has moved by 42 months from the original filing. 29 of the 124 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameKAMALRAJ DATTAVIHAR CENTRAL
  • TypeCommercial
  • Location
    • DEHU ROAD
    • Borade Wadi
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 412105
  • Pincode412105
  • RERA no.P52100025876
  • ReraGenie IDRG-MH-16188

Builder

  • NameKAMALRAJ ESTATE
  • Entity typePartnership
  • PartnerKAMLESH KANYALAL GANDHI
  • Other registrations8 more →
  • Completed3 of 9
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects9 →

Key dates

this monthRegisteredJul 2020First promiseMar 2022Revised toSep 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on24 Jul 2020
  • Promised completion30 Sep 2025
  • Revised completionRevised to 30 Sep 2025 (originally 31 Mar 2022)
  • Buildings1 building record
  • Documents filed42 files

Current status

23%29 of 124 units booked

Figures as on 22 Jul 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KAMALRAJ CENTRALNA1160124124

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

KAMALRAJ CENTRAL: 95% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%

Progress on shared amenities15

As on 22 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes70%
Water SupplyYes75%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes70%
Storm Water DrainsYes70%
Landscaping & Tree PlantingYes30%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes70%
Solid Waste Management And DisposalYes90%
Water conservation /Rain water harvestingYes70%
Energy managemcntYes70%
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership5

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,732 sq m
Land owned byThe promoter, with other names on the file
Named landowners5
LandownerVillageDistrict
YOGESH DATTATRAY BORATEYAWALEWADIPune
SANDIP DATTATRAY BORATEPimpri Chinchawad (M Corp.)Pune
DEEPAK DATTATRAY BORATEPimpri Chinchawad (M Corp.)Pune
VIKAS DATTATRAY BORATEPimpri Chinchawad (M Corp.)Pune
RADHIKA DATTATRAY BORATEPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Munciple Corporation
Permissible FSI5732.47
Proposed, not sanctioned5,732 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKASARWADI PUNE

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVIKAS ACHALKAR
EngineerAMOL MANKAR
Chartered AccountantAGH & ASSOCIATES
PartnerRole in project
KAMALRAJ ESTATE-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100018868Mar 2022 → Sep 2025

Reason as filed by the promoterDue to Pendamic Situation of Covid19 and scarcity of labour, no work started.

EXT52100009335Mar 2022 → Mar 2023

Reason as filed by the promoterDue to Pendamic Situation of Covid19 and scarcity of labour, no work started.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Mar 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Mar 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Mar 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Mar 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 23 Feb 2024

Documents filed42

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: DV Central Completion Ground and first.pdf22 Jul 2025
Occupational CertificateFile: DV G and F and Central Second and Third Completion certificate.pdf22 Jul 2025
Occupational CertificateFile: Completion Certificate Verification For RERA Application No -P52100025876.pdf22 Jul 2025
Occupational CertificateFile: Completion Central Forth and Fifth.pdf17 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Datta_Vihar_Commercial_Quality_Assurance_Form_2A.pdf16 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kamalraj Form 1 - Dattavihar Central.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Dv Central - Sept 24.pdf18 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 DV Central.pdf17 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DV - Central.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DV Central.pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DV Central.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DV Central March 24.pdf20 Apr 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Central Ground and first Completion certificate.pdf23 Feb 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Central Second and Third Completion certificate.pdf23 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Central Dec 23.pdf20 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 DV Central Dec 23.pdf12 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 DV - Central.pdf8 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 DV- Central.pdf8 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Central.pdf11 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Central Dec 22.pdf1 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22 Dattavihar Central.pdf8 Dec 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A DV Central.pdf28 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: KE DV Central Form 5.pdf22 Jul 2022
CERSAI detailsFile: CERSAI_Search_Report_200242452232_For_Asset_Based_Search_18_07_2022_16_57_33_049.pdf19 Jul 2022
Declaration about Commencement CertificateFile: Kamalraj Commercial Bldg Declaration about commencement.pdf3 Jul 2021
Disclosure of sold/ booked inventoryFile: Kamalraj Commercial Bldg - Inventory Details.pdf3 Jul 2021
Details of Restarting of Construction work post lockdownFile: Kamalraj Datta Vihar Commercial Bldg Declaration for resuming work.pdf22 Dec 2020
Proforma of Allotment letterFile: KAMALRAJ CENTRAL ( Commercial ).pdf24 Jun 2020
Declaration in FORM BFile: DV COMMERCIAL FORM B DEVELOPER.pdf6 Apr 2020
Declaration in FORM BFile: DV Commercial Landowner FORM B.pdf6 Apr 2020
Layout approvalFile: Commercial IOD Layout.pdf19 Mar 2020
Building plan approvalFile: Commercial Sanction Layout.pdf19 Mar 2020
PAN CardFile: KE Pancard.pdf19 Mar 2020
Copy of the legal title reportFile: Title Serch Report.pdf19 Mar 2020
Details of encumbrancesFile: Commercial Bldg Encumbrances.pdf19 Mar 2020
Copy of Layout Approval (in case of layout)File: Commercial IOD Layout.pdf19 Mar 2020
Building Plan Approval / NA Order for plotted developmentFile: Commercial Sanction Layout.pdf19 Mar 2020
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate IOD.pdf19 Mar 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Commercial Building Architect Certificate.pdf19 Mar 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Commercial Building Form 2 Engineer Certificate.pdf19 Mar 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Commercial Building Engineer Quality Certificate.pdf19 Mar 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Commercial Form 3 C A.pdf19 Mar 2020

Promoter's earlier projects8

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise2 delivered late1 not delivered by the promised date4 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
KAMALRAJ AKSHARDHAM B and C BUILDINGP52100056285CHOVISAWADI, Pune220May 2024OngoingDec 2028Not due yet
KAMALRAJ AKSHARDHAM A BUILDINGP52100079718CHOVISAWADI, Pune108Mar 2025OngoingDec 2028Not due yet
Kamalaraj Athens B and CP52100028848Kaveri Nagar, Pune182Apr 2021OngoingJun 2027Not due yet
KAMALRAJ ATHENS AP52100054711KAVERI NAGAR, Pune112Feb 2024OngoingJun 2027Not due yet
KAMALRAJ DATTAVIHAR E AND HP52100031669BORHADEWADI, Pune152Nov 2021OngoingJul 2025Not delivered
KAMALRAJ DATTAVIHAR G - F BUILDINGP52100025201BORADE WADI, Pune-Mar 2020CompletedDec 2023Dec 2023
Kamalraj Datta Vihar D BuildingP52100015707Borhadewadi ( Moshi ), Pune-Mar 2018CompletedJun 2022Late, Oct 2022
Kamalraj Datta Vihar A BldngP52100002971MOSHI, Pune-Aug 2017CompletedDec 2021Registered original: Dec 2019Late, Oct 2022

How this compares with Pune

23%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 42 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KAMALRAJ DATTAVIHAR CENTRAL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Borade Wadi13,700+ in Pune

Builder: KAMALRAJ ESTATE

KAMALRAJ ESTATE has 9 registrations on MahaRERA, including Kamalraj Datta Vihar A Bldng and Kamalraj Datta Vihar D Building. Its filings disclose 9 earlier MahaRERA projects: declares 2 of 4 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if KAMALRAJ DATTAVIHAR CENTRAL is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KAMALRAJ DATTAVIHAR CENTRAL?

The registered promoter entity is KAMALRAJ ESTATE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KAMALRAJ DATTAVIHAR CENTRAL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KAMALRAJ DATTAVIHAR CENTRAL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KAMALRAJ DATTAVIHAR CENTRAL?

The professionals named in the filing: Architect: VIKAS ACHALKAR; Engineer: AMOL MANKAR; Chartered Accountant: AGH & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KAMALRAJ DATTAVIHAR CENTRAL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KAMALRAJ DATTAVIHAR CENTRAL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KAMALRAJ DATTAVIHAR CENTRAL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.