Home / Browse projects / Thane, Maharashtra / KALYAN SQUARE

Registered No litigation declared Commercial project

KALYAN SQUARE

By KAGVIN VENTURES

RG-MH-58985 · RERA P51700048508 · Last updated on MahaRERA portal: 20 Jun 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 36 months from the original
4 of 11Construction stages donefurthest along: Installation of Lifts, 90%
7 of 44Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 92 documents Report an error

KALYAN SQUARE is a Commercial project by KAGVIN VENTURES in Thane, Maharashtra, registered with MahaRERA as P51700048508 on 3 Jan 2023. Possession is promised by 31 Dec 2027. The completion date has moved by 36 months from the original filing. 37 of the 44 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameKALYAN SQUARE
  • TypeCommercial
  • Location
    • BHIWANDI
    • kon (CT)
    • Thane
    • 421301
  • Pincode421301
  • RERA no.P51700048508
  • ReraGenie IDRG-MH-58985

Builder

  • NameKAGVIN VENTURES
  • Entity typePartnership
  • PartnersAMIT MANSHI KARIA, MIHIR PRADEEP NISHAR, SHUBH MAHESH GALA

Key dates

this monthRegisteredJan 2023First promiseDec 2024Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on3 Jan 2023
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed92 files

Current status

84%37 of 44 units booked
50.0%Work done, per cost certificate

Figures as on 20 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KALYAN SQUARENA7604444

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 90%.

KALYAN SQUARE: 69% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure54%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks56%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.61%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 20 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed32

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots32
Closed/Covered32

Land and ownership5

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,300 sq m
Land owned byThe promoter, with other names on the file
Named landowners5
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on31 Oct 2025
LandownerVillageDistrict
MR. DANABHAI KHETABHAI PATELkon (CT)Thane
MR. RAMESH VALJI PATELkon (CT)Thane
MR. CHANDULAL VALJI PATELkon (CT)Thane
MR. PARESH VALJI PATELkon (CT)Thane
MR. LADHARAM ARJUN PATELkon (CT)Thane

Approvals and building plan

Sanctioning authoritymmr
Permissible FSI2468.65
Proposed, not sanctioned2,469 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKHARKARALI
Estimated costRs 20.94 cr
Cost incurredRs 10.48 cr
Work done50.05%
BuildingWingEstimatedIncurred
KALYAN SQUARENARs 20.18 crRs 10.09 cr
-NARs 75.68 lakhRs 38.98 lakh

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectK K AND ASSOCIATES
EngineerK K AND ASSOCIATES
Chartered AccountantROHIT SAVLA AND ASSOCIATES
PartnerRole in project
KAGVIN VENTURES-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700025184Dec 2024 → Nov 2025

Reason as filed by the promoterWe Would like to request you that the Project KALYAN SQUARE which is located at SURVEY NO. 250/5/A/PT at KONGAON (CT), Bhiwandi, Thane, 421301 having its Registration No P51700048508 was mentioned to be completed on 31/12/2024 Due to below reasons project was not able to get completed on time 1) GOVERNMENT APPROVAL: The said property comes under the limit of Kongaon Grampanchayat and Sanctioning Authority is MMRDA. The Road comes under PWD and due to lack of cordination between both the Government Agencies the Project was not able to complete on time, because of lack of approvals. Even as on t

EA22052621066Dec 2024 → Dec 2027

Reason as filed by the promoterWe, KAGVIN VENTURES, are the promoters of the real estate project known as "KALYAN SQUARE" bearing Maha RERA Registration No. P51700048508. Reason We would like to respectfully inform you that the reason for applying for the RERA extension is solely due to the pending Occupation Certificate (OC) process. The construction work is substantially completed, however, the OC application process and issuance of the final OC certificate are still under process with the concerned authority. Therefore, the extension is being sought only to complete the remaining statutory compliances and obtain the fina

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12504438Narayan Raghunath SahuKAGVIN VENTURES13/12/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Nov 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Nov 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Nov 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed92

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: kalyan square form-1 date- 31-03-2026.pdf20 Jun 2026
Withdrawal Update Form 2File: kalyan square form-2 date- 31-03-2026.pdf20 Jun 2026
Withdrawal Update Form 3File: Signed Form -3 Kagvin ventures.pdf20 Jun 2026
Withdrawal Update Form 1File: Form 1 kalyan Square (1) latest.pdf12 Mar 2026
Withdrawal Update Form 2File: Form 2 kalyan Square latest.pdf12 Mar 2026
Withdrawal Update Form 3File: kalyan Square form-3_compressed.pdf12 Mar 2026
Withdrawal Update Form 1File: KALYAN SQUARE FORM 1.pdf12 Jan 2026
Withdrawal Update Form 2File: KALYAN SQUARE FORM 2.pdf12 Jan 2026
Withdrawal Update Form 3File: kalyan Square form- sep-25 (1).pdf12 Jan 2026
Withdrawal Update Form 1File: FORM 1 SQUARE QUATER 1.pdf11 Dec 2025
Withdrawal Update Form 2File: FORM 2 SQUARE QUATER 1.pdf11 Dec 2025
Withdrawal Update Form 3File: form-3 final june 25.pdf11 Dec 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: kalyan square form 1.pdf12 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KALYAN SQUARE FORM 3 (1).pdf12 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: kalyan square form 2.pdf12 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf17 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf15 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf15 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 MARCH END 2024.pdf18 Nov 2024
CERSAI detailsFile: CERSAI DECLARATION (3).pdf18 Nov 2024
Declaration about Commencement CertificateFile: CC DECLARATION.pdf18 Nov 2024
Disclosure of sold/ booked inventoryFile: INVENTORY KALYAN SQUARE.pdf18 Nov 2024
Declaration in FORM BFile: RERA FORM B KALYAN SQUARE (1).pdf18 Nov 2024
Declaration in FORM BFile: RERA FORM B KALYAN SQUARE (1).pdf18 Nov 2024
Disclosure of sold/ booked inventoryFile: INVENTORY KALYAN SQUARE.pdf18 Nov 2024
Declaration about Commencement CertificateFile: CC DECLARATION.pdf18 Nov 2024
CERSAI detailsFile: CERSAI DECLARATION (3).pdf18 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 MARCH END 2024.pdf18 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 MARCH END 2024.pdf15 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf12 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf12 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf12 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2A.pdf12 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf19 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf19 Jul 2024
Disclosure of sold/ booked inventoryFile: Inventory List (1).pdf8 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (1).pdf8 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Kalyan Square Form 2A (Jan To Mar 2024).pdf2 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kalyan Square Form 1 (Jan To Mar 2024).pdf17 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Kalyan Square Form 2 (Jan To Mar 2024).pdf17 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Ca Certificate Dec 23.pdf29 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate Dec 23.pdf17 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate Dec 23.pdf17 Jan 2024
Disclosure of sold/ booked inventoryFile: Inventory List.pdf12 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Jan - Mar 2023.pdf21 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Jan - Mar 2023.pdf21 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf8 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf8 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf8 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5 CA Certificate on Project Cost and Fund withdrawal (Form 3).pdf8 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 6 CA Certificate on Project Cost and Fund withdrawal (Form 3).pdf8 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 7 CA Certificate on Project Cost and Fund withdrawal (Form 3).pdf8 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23).pdf8 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE JAN - MAR 2023.pdf3 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE APR - JUN 2023.pdf3 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE July - Sep 2023.pdf3 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2022-2023.pdf3 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE APRIL - JUNE 2023.pdf17 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE July - Sep 2023.pdf17 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf14 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certficate Jan - Mar 2023.pdf10 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Jul - Sep 2023.pdf10 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Jan - Mar 2023.pdf10 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Jul - Sep 2023.pdf10 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf9 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf9 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf9 Oct 2023
Details of encumbrances concerned to FinanceFile: NO ENCUMBRANCE.pdf20 Dec 2022
Details of encumbrances concerned to LegalFile: NO ENCUMBRANCE.pdf20 Dec 2022
CERSAI detailsFile: CERSAI DECLARATION.pdf20 Dec 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK LETTER.pdf20 Dec 2022
Layout approvalFile: PLANS 1.pdf28 Nov 2022
Layout approvalFile: PLANS 2.pdf28 Nov 2022
Building plan approvalFile: PLANS 1.pdf28 Nov 2022
Building plan approvalFile: PLANS 2.pdf28 Nov 2022
Copy of the legal title reportFile: TITLE REPORT.pdf28 Nov 2022
Copy of Layout Approval (in case of layout)File: PLANS 1.pdf28 Nov 2022
Copy of Layout Approval (in case of layout)File: PLANS 2.pdf28 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: PLANS 1.pdf28 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: PLANS 2.pdf28 Nov 2022

How this compares with Thane

84%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 36 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KALYAN SQUARE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BHIWANDI7,600+ in Thane

Builder: KAGVIN VENTURES

KAGVIN VENTURES has 1 registration on MahaRERA, including KALYAN SQUARE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if KALYAN SQUARE is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KALYAN SQUARE?

The registered promoter entity is KAGVIN VENTURES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KALYAN SQUARE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against KALYAN SQUARE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for KALYAN SQUARE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KALYAN SQUARE?

The professionals named in the filing: Architect: K K AND ASSOCIATES; Engineer: K K AND ASSOCIATES; Chartered Accountant: ROHIT SAVLA AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KALYAN SQUARE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KALYAN SQUARE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KALYAN SQUARE to a free account