Red flags

  • 1 complaint at MahaRERA
  • Rs 400.00 crore secured on the land, in favour of ICICI Bank Limited

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedno revision filed
6 of 11Construction stages donefurthest along: Internal walls, 73%
19 of 82Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 75 documents Report an error

Kalpataru Vivant - South Wing C is a Residential / Group Housing project by Alder Residency Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800053558 on 10 Nov 2023. Possession is promised by 31 Dec 2028. 63 of the 82 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameKalpataru Vivant - South Wing C
  • TypeResidential / Group Housing
  • Location
    • Station Road
    • JVLR
    • Andheri
    • Mumbai Suburban
    • 400060
  • Pincode400060
  • RERA no.P51800053558
  • ReraGenie IDRG-MH-06440

Builder

  • NameAlder Residency Private Limited
  • Entity typeCompany
  • CINU45201MH2008PTC182570
  • GSTIN27AAHCA1405F1Z6
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • DirectorsLokesh Jain, Devesh Bhatt
  • Other registrations9 more →
  • Completed6 of 10

Key dates

this monthRegisteredNov 2023PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 Nov 2023
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed75 files

Current status

77%63 of 82 units booked
55.5%Work done, per cost certificate

Figures as on 22 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building No-2 Wing - CNA272182082

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 73%.

Building No-2 Wing - C: 65% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises73%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.13%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.4%

Progress on shared amenities15

As on 22 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsYes60%
Landscaping & Tree PlantingYes26%
Street LightingYes30%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes60%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes70%
Electrical meter room, sub-station, receiving stationYes77%
Aggregate area of recreational Open SpaceYes15%
Open ParkingNoNot applicable

Parking filed23

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots23
Closed/Covered23

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area305 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofICICI Bank Limited
Secured amountRs 400.00 crore
CERSAI search filedYes
Declared on3 Dec 2025

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI4260.15
Proposed, not sanctioned3,760 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICICI Bank Ltd., 215, Free Press House, Free Press Marg, Nariman Point, Mumbai.400021
Estimated costRs 31.31 cr
Cost incurredRs 17.38 cr
Work done55.51%
BuildingWingEstimatedIncurred
Building No-2 Wing - CNARs 22.81 crRs 11.34 cr
-NARs 8.50 crRs 6.04 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJethe & Associates
EngineerSunil Jadhav
Chartered AccountantC.R Mohnot & Co.
Chartered Accountantkkc & associates llp
PartnerRole in project
Alder Residency Private Limited-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12600688MERU RAIAlder Residency Private Limited06/02/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Oct 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Oct 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Oct 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed75

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A Vivant South Wing C.pdf22 Jun 2026
Withdrawal Update Form 1File: Vivant South Wing C AC.pdf20 Apr 2026
Withdrawal Update Form 2File: Vivant South Wing C EC.pdf20 Apr 2026
Withdrawal Update Form 3File: CA certificate-Kalpataru Vivant South -Wing C -RERA QE- 31-03-2026.pdf20 Apr 2026
Withdrawal Update Form 1File: Vivant South C AC.pdf20 Jan 2026
Withdrawal Update Form 2File: Vivant South C EC.pdf20 Jan 2026
Withdrawal Update Form 3File: SC.pdf20 Jan 2026
Withdrawal Update Form 1File: Vivant South Wing C AC.pdf23 Oct 2025
Withdrawal Update Form 2File: Vivant South Wing C EC.pdf23 Oct 2025
Withdrawal Update Form 3File: SC.pdf23 Oct 2025
Form 5 (FY 2024-2025)File: Vivant South C.pdf24 Sep 2025
Form 2A (FY 2024-2025)File: Vivant SC.pdf12 Aug 2025
Disclosure of Sold and Booked InventoryFile: VivantSWC.pdf20 Jul 2025
Form 1File: Vivant South C.pdf20 Jul 2025
Form 2File: Vivant SC.pdf20 Jul 2025
Form 3File: Vivant South Wing C.pdf20 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vivant SC AC 31032025.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: South C-Mar 25.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Vivant South Wing C EC.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vivant SC AC.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: South C.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Vivant SC EC.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Vivant South C.pdf20 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: Full CC of Wing C S.pdf11 Nov 2024
Declaration about Commencement CertificateFile: Vivant SC 11112024.pdf11 Nov 2024
Disclosure of sold/ booked inventoryFile: Vivant South C.pdf30 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vivant SC.pdf21 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Vivnat south C.pdf21 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Vivant SC.pdf21 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Vivant South C.pdf11 Oct 2024
Disclosure of sold/ booked inventoryFile: Vivant SC.pdf6 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vivant SC.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Vivant SC.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: South WIng C.pdf20 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Vivant South Wing C.pdf14 Jun 2024
Disclosure of sold/ booked inventoryFile: K Vivant south wing C.pdf9 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kalpataru Vivant South C.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Kalpataru Vivant South C.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: S C.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: K Vivant South Wing C.pdf30 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: K Vivant South W-C.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: K Vivant South W-C.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SOUTH WING C.pdf20 Jan 2024
Proforma of Agreement for saleFile: KL Vivant South Wing C.pdf28 Nov 2023
Details of encumbrances concerned to FinanceFile: K Vivant SWC.pdf24 Nov 2023
Details of encumbrances concerned to LegalFile: K Vivant SWC.pdf24 Nov 2023
CERSAI detailsFile: CERSAI_Acknowledgemnt_Report_200287123635_For_Registration_Of_Security_Interest_17_11_202324 Nov 2023
Details of encumbrances concerned to FinanceFile: EC Finance SC.pdf2 Nov 2023
Details of encumbrances concerned to LegalFile: EC Finance SC.pdf2 Nov 2023
Proforma of Agreement for saleFile: AFS Wing C.pdf2 Nov 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format Bank Declaration SC.pdf2 Nov 2023
CERSAI detailsFile: CERSAI Dec SC.pdf30 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Vivant South C.pdf30 Oct 2023
Proforma of Allotment letterFile: Letter of Intent final.pdf28 Oct 2023
Deviation Report with respect to Allotment letterFile: Vivant South wing C DAL.pdf27 Oct 2023
Deviation Report with respect to model copy of AgreementFile: Vivant South wing C DAFS.pdf27 Oct 2023
Layout approvalFile: Segment 001 of Drawing.pdf26 Oct 2023
Building plan approvalFile: Segment 003 of Drawing.pdf26 Oct 2023
Building plan approvalFile: Segment 004 of Drawing.pdf26 Oct 2023
Building plan approvalFile: Segment 006 of Drawing.pdf26 Oct 2023
Building plan approvalFile: Segment 002 of Drawing.pdf26 Oct 2023
PAN CardFile: 1 PAN Card (1).pdf26 Oct 2023
Copy of the legal title reportFile: 2 Copy of the legal title report (2).pdf26 Oct 2023
Copy of Layout Approval (in case of layout)File: Segment 001 of Drawing.pdf26 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Segment 002 of Drawing.pdf26 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Segment 003 of Drawing.pdf26 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Segment 004 of Drawing.pdf26 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Segment 006 of Drawing.pdf26 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: Further CC.pdf26 Oct 2023
Declaration about Commencement CertificateFile: K Vivant SC.pdf26 Oct 2023
Declaration in FORM BFile: Kalpataru Vivant - Wing C.pdf26 Oct 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Devesh Wing C.pdf26 Oct 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A VGB Wing C.pdf26 Oct 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A LJ Wing C.pdf26 Oct 2023
Copy of the legal title reportFile: Alder MahaRERA TC RERA.pdf25 Oct 2023

How this compares with Mumbai Suburban

77%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Kalpataru Vivant - South Wing C on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near JVLR6,700+ in Mumbai Suburban

Builder: Alder Residency Private Limited

Alder Residency Private Limited has 10 registrations on MahaRERA, including Kalpataru Vivant - South Wing A and Kalpataru Vivant - North Wing B. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Kalpataru Vivant - South Wing C is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Kalpataru Vivant - South Wing C?

The registered promoter entity is Alder Residency Private Limited, a company as per the filing. Its CIN U45201MH2008PTC182570 and GSTIN 27AAHCA1405F1Z6 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Kalpataru Vivant - South Wing C?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Kalpataru Vivant - South Wing C?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Kalpataru Vivant - South Wing C?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Kalpataru Vivant - South Wing C?

The professionals named in the filing: Architect: Jethe & Associates; Engineer: Sunil Jadhav; Chartered Accountant: C.R Mohnot & Co.; Chartered Accountant: kkc & associates llp. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Kalpataru Vivant - South Wing C?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Kalpataru Vivant - South Wing C. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Kalpataru Vivant - South Wing C to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.