Home / Browse projects / Pune, Maharashtra / Kalpataru Jade Skyline

Registered No litigation declared Residential / Group Housing project

Kalpataru Jade Skyline

By Astrum Developments Private Limited

RG-MH-27361 · RERA P52100033791 · Last updated on MahaRERA portal: 22 Jun 2026

Source: official MahaRERA filing

Red flags

  • 3 complaints at MahaRERA
  • Rs 48.00 crore secured on the land, in favour of Aditya Birla Capital Limited

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
150 of 465Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 94 documents Report an error

Kalpataru Jade Skyline is a Residential / Group Housing project by Astrum Developments Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100033791 on 8 Mar 2022. Possession is promised by 31 Dec 2026. 315 of the 465 units on this registration are recorded sold or booked. 3 complaints are on record with the regulator.

At a glance

Project

  • NameKalpataru Jade Skyline
  • TypeResidential / Group Housing
  • Location
    • Off Pan Card Road
    • Baner
    • Haveli
    • Pune
    • 411045
  • Pincode411045
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100033791
  • ReraGenie IDRG-MH-27361

Builder

  • NameAstrum Developments Private Limited
  • Entity typeCompany
  • CINU45309MH2021PTC355055
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Other registrations8 more →
  • Completed8 of 9

Key dates

this monthRegisteredMar 2022PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on8 Mar 2022
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed94 files

Current status

68%315 of 465 units booked
87.2%Work done, per cost certificate

Figures as on 22 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Jade Skyline- Wing A1, A2, A3, A4 and A5NA29214650465

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Jade Skyline- Wing A1, A2, A3, A4 and A5:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 22 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed2727

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2,727
Closed/Covered2,136
Open Space591

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,772 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofAditya Birla Capital Limited
Secured amountRs 48.00 crore
CERSAI search filedYes
Declared on27 Apr 2026
LandownerVillageDistrict
Dr. Babul Rustumkhan PathanBanerPune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI40000.0
Proposed, not sanctioned39,338 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJeevan Prakash Building , Sir P M Road , Fort , Mumbai- 400001
Estimated costRs 236.01 cr
Cost incurredRs 205.71 cr
Work done87.16%
BuildingWingEstimatedIncurred
Jade Skyline- Wing A1, A2, A3, A4 and A5NARs 211.52 crRs 188.99 cr
-NARs 24.49 crRs 16.72 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSwapnil Potdar (Architect Certificate-Form 1 and Form 4)
ArchitectMINAJ MAGDUM
ArchitectSwapnil Potdar (Architect Certificate-Form 1)
EngineerSwapnil Wagh
EngineerVishwas Kadam ( Engineer Certificate-Form 2)
Chartered AccountantSinghi & Co.
Chartered AccountantC R Mohnot & Co ( CA Certificate-Form 3)
PartnerRole in project
Astrum Developments Private Limited-

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC12603912Astrum Developments Private LimitedMr Vishal Shankar Bachhav24/06/2026
CC12603913Astrum Developments Private LimitedMr Laxman Bharat Jagdale24/06/2026
CC12604254Astrum Developments Private LimitedMr Sitaram Rambhau Shinde07/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 May 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Jan 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 May 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed94

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 94 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A Jade Skyline.pdf22 Jun 2026
Withdrawal Update Form 1File: Jade Skyline AC.pdf22 Apr 2026
Withdrawal Update Form 1File: Jade Skyline AC.pdf22 Apr 2026
Withdrawal Update Form 2File: Jade Skyline EC.pdf22 Apr 2026
Withdrawal Update Form 2File: Jade Skyline EC.pdf22 Apr 2026
Withdrawal Update Form 3File: CA Certificate Skyline Dec-25.pdf22 Apr 2026
Withdrawal Update Form 3File: Skyline.pdf22 Apr 2026
Withdrawal Update Form 1File: Jade Skyline AC.pdf21 Apr 2026
Withdrawal Update Form 1File: Jade Skyline AC.pdf21 Apr 2026
Withdrawal Update Form 2File: Jade Skyline EC.pdf21 Apr 2026
Withdrawal Update Form 2File: Jade Skyline EC.pdf21 Apr 2026
Withdrawal Update Form 3File: Skyline.pdf21 Apr 2026
Withdrawal Update Form 3File: Skyline.pdf21 Apr 2026
Withdrawal Update Form 1File: Jade Skyline AC.pdf20 Nov 2025
Withdrawal Update Form 2File: Jade Skyline EC.pdf20 Nov 2025
Withdrawal Update Form 3File: CA certificate- Kalpataru Jade Skyline- Astrum Development Pvt Ltd - QE-30-09-2025.pdf20 Nov 2025
Form 5 (FY 2024-2025)File: Jade Skyline.pdf26 Sep 2025
Disclosure of Sold and Booked InventoryFile: KL Jadeskyline.pdf23 Jul 2025
Form 1File: Jade skyline.pdf23 Jul 2025
Form 2File: Jade Skyline.pdf23 Jul 2025
Form 3File: CA Certificate_Kalpataru Skyline Jun-25.pdf23 Jul 2025
Form 2A (FY 2024-2025)File: Jade Skyline.pdf7 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KL Jade Skyline.pdf21 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Jade Skyline_Engineers Certificate.pdf21 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Form 3_Jade Skyline_March 25.pdf20 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Jade Skyline.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Jade H (2).pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Jade Skyline.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Jade Skyline.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Jade Skyline .pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Jade Skyline.pdf30 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Jade Skyline.pdf20 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kalpataru Jade Skyline_UPLOAD.pdf20 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Jade Skyline.pdf20 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Jade Skyline.pdf11 Oct 2024
Disclosure of sold/ booked inventoryFile: Jade Skyline.pdf6 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Jade skyline.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Jade skyline.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Skyline June24.pdf20 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Jade Skyline.pdf14 Jun 2024
Disclosure of sold/ booked inventoryFile: K Jade Skyline.pdf14 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kalpataru Jade Skyline.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Kalpataru Jade Skyline.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Kalpataru Jade Skyline.pdf19 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Kalpataru Jade Skyline.pdf19 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Kalpataru Jade Skyline.pdf19 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Astrum Skyline Mar-2024.pdf19 Apr 2024
Disclosure of sold/ booked inventoryFile: K Jade skyline.pdf30 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Jade Skyline.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Jade Skyline.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - K Jade Skyline Dec-2023.pdf20 Jan 2024
Disclosure of sold/ booked inventoryFile: Jade Skyline.pdf12 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Jade Skyline.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Jade Skyline.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: K Jade Skyline.pdf20 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Kalpataru Skyline.pdf30 Sep 2023
Disclosure of sold/ booked inventoryFile: K jade Skyline.pdf13 Sep 2023
Disclosure of sold/ booked inventoryFile: Jade Skyline.pdf12 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Jade Skyline.pdf25 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Jade Skyline.pdf25 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA Certificate Skyline.pdf25 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Aurum.pdf22 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: K Jade Skyline.pdf22 Jun 2023
Layout approvalFile: Jade upload.pdf26 May 2023
Copy of Layout Approval (in case of layout)File: Jade upload.pdf26 May 2023
Commencement Certificates / NA Order for plotted developmentFile: Jade CC.pdf26 May 2023
Declaration about Commencement CertificateFile: Jade Skyline.pdf26 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arcitect Cer Aurum.pdf23 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Cer Aurum.pdf23 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Aurum.pdf23 Feb 2023
Layout approvalFile: Jade Skyline Approved layout.pdf3 Jan 2023
Building plan approvalFile: Jade Skyline CC.pdf3 Jan 2023
Copy of Layout Approval (in case of layout)File: Jade Skyline Approved layout.pdf3 Jan 2023
Building Plan Approval / NA Order for plotted developmentFile: Jade Skyline CC.pdf3 Jan 2023
Declaration about Commencement CertificateFile: Jade Sky line CCD.pdf3 Jan 2023
Layout approvalFile: Jade Skyline Proposed 1.pdf25 Nov 2022
Copy of Layout Approval (in case of layout)File: Jade Skyline Proposed 1.pdf25 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Kalpataru Aurum.pdf30 Sep 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Aurum.pdf21 Apr 2022
Copy of the legal title reportFile: 3408_001 Final.pdf1 Mar 2022

How this compares with Pune

68%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Kalpataru Jade Skyline on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Baner13,700+ in Pune

2 kmKalpataru Jade SkylineCompleted 146Lapsed / revoked 54Other 159Dot size: filed unitsN

Filed coordinates, straight-line distance. 359 registered projects within 2 km.

Builder: Astrum Developments Private Limited

Astrum Developments Private Limited has 9 registrations on MahaRERA, including Kalpataru Jade Residences B and Kalpataru Jade Residences C. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Kalpataru Jade Skyline is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Kalpataru Jade Skyline?

The registered promoter entity is Astrum Developments Private Limited, a company as per the filing. Its CIN U45309MH2021PTC355055 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Kalpataru Jade Skyline?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Kalpataru Jade Skyline?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Kalpataru Jade Skyline?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Kalpataru Jade Skyline?

The professionals named in the filing: Architect: Swapnil Potdar (Architect Certificate-Form 1 and Form 4); Architect: MINAJ MAGDUM; Architect: Swapnil Potdar (Architect Certificate-Form 1); Engineer: Swapnil Wagh; Engineer: Vishwas Kadam ( Engineer Certificate-Form 2); Chartered Accountant: Singhi & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Kalpataru Jade Skyline?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Kalpataru Jade Skyline. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Kalpataru Jade Skyline to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.