ReraGenieLog inGet a buyer report

Home / Browse projects / Nashik, Maharashtra / KALANIKETAN PRIDE

Registered No litigation declared Others project

KALANIKETAN PRIDE

By ELICA BUILDERS

RG-MH-31529 · RERA P51600079864 · Last updated on MahaRERA portal: 9 Jun 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Jul 2027Possession promisedno revision filed
5 of 11Construction stages donefurthest along: External plumbing and external plaster, 95%
5 of 22Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 53 documents Report an error

KALANIKETAN PRIDE is a Others project by ELICA BUILDERS in Nashik, Maharashtra, registered with MahaRERA as P51600079864 on 28 Mar 2025. Possession is promised by 5 Jul 2027. 17 of the 22 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameKALANIKETAN PRIDE
  • TypeOthers
  • Location
    • Wadala Shiwar
    • Nashik
    • 422009
  • Pincode422009
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600079864
  • ReraGenie IDRG-MH-31529

Builder

  • NameELICA BUILDERS
  • Entity typePartnership
  • GSTIN27AAJFE1096K1Z4
  • PartnersVASANT MADHUKAR GAYAKWAD, PALLAVI VINAY KULKARNI, PRANITA UTTAM MEHENDALE, AMIT KUMAR MAKHARIA, RISHIKESH SHAM GARUD, RAMCHANDRA FAKIRA KOLI, MAHENDRA HIRALAL KUMAWAT, MANGESH ANANT KULKARNI
  • ParnerKISHOR MURLIDHAR KHOND

Key dates

this monthRegisteredMar 2025PromisedJul 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Mar 2025
  • Promised completion5 Jul 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed53 files

Current status

77%17 of 22 units booked
95.0%Work done, per cost certificate

Figures as on 9 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KALANIKETAN PRIDENA4416622

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 95%.

KALANIKETAN PRIDE: 79% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 9 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes85%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area576 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on22 May 2026

Approvals and building plan

Sanctioning authorityNashik Municipal Corporation
Permissible FSI1595.98
Proposed, not sanctioned1,596 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR, SHOP NO.3 AND 4, STAR PLUS APARTMENT, NASHIK ROAD CORPORATION OFFICE, NASHIK ROAD, DEOLALI (CB), NASHIK, MAHARASHTRA-422101
Estimated costRs 4.11 cr
Cost incurredRs 3.90 cr
Work done95.0%
BuildingWingEstimatedIncurred
KALANIKETAN PRIDENARs 4.11 crRs 3.90 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPARAMETRIC DESIGN STUDIO SHOEB R SHAIKH
EngineerMAHENDRA H KUMAWAT KUMAWAT
Chartered AccountantR B SONAWANE AND ASSOCIATES
Chartered AccountantHARISH BHANDARI & ASSOCIATES
PartnerRole in project
ELICA BUILDERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jan 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jan 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jan 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 5 Jul 2027

Documents filed53

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Mar 26.pdf9 Jun 2026
Withdrawal Update Form 2File: Form 2 Mar 26.pdf9 Jun 2026
Withdrawal Update Form 3File: Form 3 Mar 26.pdf9 Jun 2026
Form 2File: Form 2 Q4 2024-25.pdf25 May 2026
Form 3File: Form 3 March 2025.pdf25 May 2026
Form 1File: FORM 1 MAR25.pdf25 May 2026
Disclosure of Sold and Booked InventoryFile: Discloser of Sold or booked Inventary - 31-03-2025.pdf25 May 2026
Withdrawal Update Form 1File: FORM 1 MAR25.pdf25 May 2026
Withdrawal Update Form 1File: Form 1 30Jun25.pdf25 May 2026
Withdrawal Update Form 1File: Form 1 30Sep25.pdf25 May 2026
Withdrawal Update Form 1File: Form 1 31Dec25.pdf25 May 2026
Withdrawal Update Form 2File: Form 2 Q4 2024-25.pdf25 May 2026
Withdrawal Update Form 2File: Form 2 Q1 FY 2025-26.pdf25 May 2026
Withdrawal Update Form 2File: Form 2 Q2 FY 2025-26.pdf25 May 2026
Withdrawal Update Form 2File: Form 2 Q3 FY 2025-26.pdf25 May 2026
Withdrawal Update Form 3File: Form 3 Mar 25.pdf25 May 2026
Withdrawal Update Form 3File: Form 3 30 Jun25_compressed.pdf25 May 2026
Withdrawal Update Form 3File: Form 3 30Sep25.pdf25 May 2026
Withdrawal Update Form 3File: Form 3 31Dec25.pdf25 May 2026
Form 5 (FY 2024-2025)File: FORM 5 MARCH2025.pdf25 May 2026
Declaration in FORM BFile: Form B Declaration Final.pdf26 Mar 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B Bank 26Mar.pdf26 Mar 2025
Proforma of Allotment letterFile: Allotment Letter.pdf20 Mar 2025
Deviation Report with respect to Allotment letterFile: Devation Report Allotment Letter.pdf20 Mar 2025
Other - TechnicalFile: Annexure A.pdf20 Mar 2025
Other - TechnicalFile: Clarification.pdf20 Mar 2025
Deviation Report with respect to model copy of AgreementFile: Devation Report Agreement to Sale.pdf20 Mar 2025
Proforma of Agreement for saleFile: Agreement to Sale.pdf20 Mar 2025
Other - TechnicalFile: NMC Email.pdf5 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: NMC Email.pdf26 Feb 2025
Other - LegalFile: Purchase Deed Plot no 15_11zon.pdf26 Feb 2025
Other - LegalFile: Purchase Deed Plot No 16 upload.pdf26 Feb 2025
Other - LegalFile: वडाळा_106_10_प्लॉट_15_Satbara.pdf26 Feb 2025
Other - LegalFile: वडाळा_106_10_प्लॉट_16_Satbara.pdf26 Feb 2025
PAN CardFile: PAN Card.pdf29 Jan 2025
Details of encumbrances concerned to FinanceFile: Encumbrances Concern to Finance.pdf29 Jan 2025
Details of encumbrances concerned to FinanceFile: Encumbrances to Legal.pdf29 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Final.pdf29 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final Elica.pdf29 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Final.pdf29 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf29 Jan 2025
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf29 Jan 2025
CERSAI detailsFile: Cersai details.pdf29 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration about all RERA Designated Bank Accounts (Format A).pdf29 Jan 2025
Details of encumbrances concerned to LegalFile: Encumbrances Concern to Finance.pdf29 Jan 2025
Details of encumbrances concerned to LegalFile: Encumbrances to Legal.pdf29 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest All Partners.pdf29 Jan 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for Secure Unsecure finance availed for the project.pdf29 Jan 2025
Layout approvalFile: Layout plan.pdf28 Jan 2025
Building plan approvalFile: Building Plan.pdf28 Jan 2025
Copy of the legal title reportFile: Title Search Report KNP RERA.pdf28 Jan 2025
Copy of Layout Approval (in case of layout)File: Layout plan.pdf28 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan.pdf28 Jan 2025

How this compares with Nashik

77%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KALANIKETAN PRIDE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Wadala Shiwar4,100+ in Nashik

Builder: ELICA BUILDERS

ELICA BUILDERS has 1 registration on MahaRERA, including KALANIKETAN PRIDE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if KALANIKETAN PRIDE is delayed beyond 5 Jul 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KALANIKETAN PRIDE?

The registered promoter entity is ELICA BUILDERS, a partnership as per the filing. Its GSTIN 27AAJFE1096K1Z4 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KALANIKETAN PRIDE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KALANIKETAN PRIDE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KALANIKETAN PRIDE?

The professionals named in the filing: Architect: PARAMETRIC DESIGN STUDIO SHOEB R SHAIKH; Engineer: MAHENDRA H KUMAWAT KUMAWAT; Chartered Accountant: R B SONAWANE AND ASSOCIATES; Chartered Accountant: HARISH BHANDARI & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KALANIKETAN PRIDE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KALANIKETAN PRIDE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KALANIKETAN PRIDE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.