Kalakunj CD
RG-MH-17346 · RERA P52100029413 · Last updated on MahaRERA portal: 1 Oct 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 12 months past the filed date
- Completion date moved by 8 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Kalakunj CD is a Residential / Group Housing project by VG Empires LLP in Pune, Maharashtra, registered with MahaRERA as P52100029413 on 29 May 2021. Possession was promised by 31 Oct 2025 and is now 12 months past that date. The completion date has moved by 8 months from the original filing. 15 of the 41 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NameKalakunj CD
- TypeResidential / Group Housing
- Location
- PLOT NO 79
- 80 CTS NO 556
- 557
- Dahanukar Colony
- Kothrud
- Haveli
- Pune
- 411038
- Pincode411038
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100029413
- ReraGenie IDRG-MH-17346
Builder
- NameVG Empires LLP
- Entity typeOthers
- GSTIN27AASFV9419J1Z9
- PartnersPoonam Vishal Gokhale, Vishal Vasant Gokhale
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on29 May 2021
- Promised completion31 Oct 2025
- Revised completionRevised to 31 Oct 2025 (originally 28 Feb 2025)
- Buildings1 building record
- Documents filed87 files
Current status
Figures as on 1 Oct 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| KALAKUNJ C D | NA | 12 | 11 | 41 | 0 | 41 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 1 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 82%.
KALAKUNJ C D: 55% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 82% |
| Sanitary Fittings within the flats / premises | 25% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 55% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 8% |
Progress on shared amenities15
As on 1 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed50
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| KALAKUNJ C AND D CHS LTD | Kothrud | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SIDDHARTH HARISCHANDRAKAR |
| Architect | Mangesh Gotal |
| Engineer | VIJENDRA GAIKWAD |
| Engineer | Mahesh Mate |
| Chartered Accountant | NIMBOLKAR RAJPUT ASSOCIATES LLP |
| Chartered Accountant | SIDDHARTH SMART |
| Chartered Accountant | G D APTE AND COMPANY |
| Partner | Role in project |
|---|---|
| VG Empires LLP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThere is total 11 floors in the said project. And we have completed almost construction of all floors. Only the flooring and last finishing work of the project is under progress. Due to technical and unavoidable circumstances we were unable to obtain the full occupancy certificate before the due date of completion. That, we are in process and progress to complete the all-construction work of the project as well as to apply for full occupancy certificate. So, we request an extension for the completion of the project.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 19 May 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 7 Jan 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 7 Jan 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed87
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 87 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2024-2025)File: form 5 - Kalakunj.pdf | 1 Oct 2025 |
| Form 1File: FORM 1_Kalakunj.pdf | 26 Jun 2025 |
| Form 2File: Form 2 - Kalakunj.pdf | 26 Jun 2025 |
| Form 3File: FORM 3 Kalakunj CD - New.pdf | 26 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Kalakunj Sold Unsold.pdf | 26 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Kalakunj CD - 30 06 2024.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Kalakunj - 30 09 2024.pdf | 24 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Kalakunj - 31 12 2024.pdf | 24 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: 15 Kalakunj Sold Unsold 311224.pdf | 7 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: 2 Kalakunj Sold Unsold 300921.pdf | 7 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: 14 Kalakunj Sold Unsold 300924.pdf | 7 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: 13 Kalakunj Sold Unsold 300624.pdf | 7 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: 12 Kalakunj Sold Unsold 310324.pdf | 7 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: 11 Kalakunj Sold Unsold 311223.pdf | 7 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: 10 Kalakunj Sold Unsold 300923.pdf | 7 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: 9 Kalakunj Sold Unsold 300623.pdf | 7 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: 8 Kalakunj Sold Unsold 310323.pdf | 7 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: 7 Kalakunj Sold Unsold 311222.pdf | 7 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: 6 Kalakunj Sold Unsold 300922.pdf | 7 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: 5 Kalakunj Sold Unsold 300622.pdf | 7 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: 4 Kalakunj Sold Unsold 310322.pdf | 7 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: 3 Kalakunj Sold Unsold 311221.pdf | 7 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: 1 Kalakunj Sold Unsold 300621.pdf | 7 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Kalakunj 30092024.pdf | 6 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Kalakunj 31122024.pdf | 6 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Kalakunj 30092024.pdf | 6 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Kalakunj 31122024.pdf | 6 Feb 2025 |
| Layout approvalFile: 1 OF 4.pdf | 7 Jan 2025 |
| Building plan approvalFile: 2 OF 4_compressed.pdf | 7 Jan 2025 |
| Building plan approvalFile: 3 OF 4_compressed.pdf | 7 Jan 2025 |
| Building plan approvalFile: 4 OF 4_compressed.pdf | 7 Jan 2025 |
| Copy of Layout Approval (in case of layout)File: 1 OF 4.pdf | 7 Jan 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 7 Jan 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 2 OF 4_compressed.pdf | 7 Jan 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 4 OF 4_compressed.pdf | 7 Jan 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 3 OF 4_compressed.pdf | 7 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Kalakunj 31032024.pdf | 25 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Kalakunj 30062024.pdf | 25 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Kalakunj.pdf | 25 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kalakunj 30 06 2024.PDF | 19 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kalakunj - 31 12 2021.PDF | 2 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kalakunj - 31 03 2022.PDF | 2 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kalakunj - 30 06 2022.PDF | 2 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kalakunj - 30 09 2022.PDF | 2 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kalakunj - 31 12 2022.PDF | 2 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kalakunj - 31 03 2023.PDF | 2 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A Kalakunj 21-22 - Signed.pdf | 6 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A Kalakunj 22-23 - Signed.pdf | 6 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2A Kalakunj 23-24 - Signed.pdf | 6 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kalakunj CD 31 03 2024 - Signed.pdf | 3 May 2024 |
| Details of encumbrancesFile: Encumbrance - Kalakunj CD.PDF | 30 Apr 2024 |
| Details of encumbrancesFile: Aditya Birla - Mortgage Index.pdf | 30 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Kalakunj 31 03 2024.pdf | 22 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Kalakunj - Dec 23 - Signed.PDF | 7 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Kalakunj - Jun 23 - Signed.pdf | 5 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Kalakunj - Sep 23 - Signed.pdf | 5 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Kalakunj 31-12-2021.pdf | 27 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Kalakunj 31-03-2022.pdf | 27 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Kalakunj 30-06-2022.pdf | 27 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Kalakunj 30-09-2022.pdf | 27 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Kalakunj 30-09-2022.pdf | 27 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Kalakunj 31-12-2022.pdf | 27 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Kalakunj 31-03-2023.pdf | 27 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Kalakunj 30-06-2023.pdf | 27 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Kalakunj 30-09-2023.pdf | 27 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Kalakunj 31-12-2023.pdf | 27 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Kalakunj 30 06 2023.pdf | 24 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Kalakunj 30 09 2023.pdf | 24 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Kalakunj 31 12 2023.pdf | 24 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: kalakunj CD.pdf | 30 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Kalakunj 31-03-2023.PDF | 12 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: kalakunj signed.pdf | 7 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 4 Feb 2023 |
| Copy of the legal title reportFile: Kalakunj Rera Title.pdf | 19 May 2021 |
| Copy of the legal title reportFile: Title Report C.pdf | 17 May 2021 |
| Copy of the legal title reportFile: Title Report D.pdf | 17 May 2021 |
| Layout approvalFile: kalakunj plan-1.pdf | 14 May 2021 |
| Building plan approvalFile: kalakunj plan-1.pdf | 14 May 2021 |
| PAN CardFile: VG EMPIRES LLP_PAN Card.pdf | 14 May 2021 |
| Details of encumbrancesFile: encumberance.pdf | 14 May 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 87 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Kalakunj CD on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dahanukar Colony13,700+ in Pune
Filed coordinates, straight-line distance. 297 registered projects within 2 km.
Pratik Nagar Palladio Kothrud Central
Vilas Javdekar Infinitee Developers Pvt. L
NEW FRIENDS
MAJESTIQUE DUROPOLIS PRIVATE LIMITED
SARVATRA CO-OP HSG SOCIETY LTD
Suryakant Kakade
Kshitij Residency
Yash Buildcon
MAYUK
MAYUR CORPORATION
Pune Baner Project-Tower 4 and 5
Goel Ganga Ventures India Private Limited
Builder: VG Empires LLP
VG Empires LLP has 1 registration on MahaRERA, including Kalakunj CD. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Kalakunj CD shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Kalakunj CD is delayed beyond 31 Oct 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Kalakunj CD?
The registered promoter entity is VG Empires LLP, an others as per the filing. Its GSTIN 27AASFV9419J1Z9 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Kalakunj CD?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Kalakunj CD?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Kalakunj CD?
The professionals named in the filing: Architect: SIDDHARTH HARISCHANDRAKAR; Architect: Mangesh Gotal; Engineer: VIJENDRA GAIKWAD; Engineer: Mahesh Mate; Chartered Accountant: NIMBOLKAR RAJPUT ASSOCIATES LLP; Chartered Accountant: SIDDHARTH SMART. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Kalakunj CD?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback