Home / Browse projects / Pune, Maharashtra / Kakkad Oneworld

Registered No litigation declared Commercial project

Kakkad Oneworld

By Kakkad Erectors LLP

RG-MH-38338 · RERA P52100055312 · Last updated on MahaRERA portal: 19 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 25 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jan 2031Possession promisedmoved 25 months from the original
0 of 11Construction stages donefurthest along: Excavation, 85%
42 of 43Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 118 documents Report an error

Kakkad Oneworld is a Commercial project by Kakkad Erectors LLP in Pune, Maharashtra, registered with MahaRERA as P52100055312 on 14 Mar 2024. Possession is promised by 30 Jan 2031. The completion date has moved by 25 months from the original filing. 1 of the 43 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.

At a glance

Project

  • NameKakkad Oneworld
  • TypeCommercial
  • Location
    • Balewadi
    • Haveli
    • Pune
    • 411045
  • Pincode411045
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100055312
  • ReraGenie IDRG-MH-38338

Builder

  • NameKakkad Erectors LLP
  • Entity typePartnership
  • PartnersJayesh Ramesh Jain, Rishi Anand Kakkad, Rupesh Bhailal Bhimjiani, Kavita Rupesh Bhijiani, Amrish Jayantilal Kakkad

Key dates

this monthRegisteredMar 2024First promiseDec 2028Revised toJan 2031

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on14 Mar 2024
  • Promised completion30 Jan 2031
  • Revised completionRevised to 30 Jan 2031 (originally 31 Dec 2028)
  • Buildings1 building record
  • Documents filed118 files

Current status

2%1 of 43 units booked
4.7%Work done, per cost certificate

Figures as on 19 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Kakkad OneworldNA18804343

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 85%.

Kakkad Oneworld: 8% average across the applicable activities

ActivityProgress
Excavation85%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed3048

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots3,048
Closed/Covered3,048

Land and ownership12

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area9,850 sq m
Land owned byNot the promoter
Named landowners12
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on7 Jan 2026
LandownerVillageDistrict
Alka Sharad BalwadkarBalewadiPune
Bharat Mahadu BalwadkarBalewadiPune
Akshay Sharad BalwadkarBalewadiPune
Jaywant Mahipati BalwadkarBalewadiPune
Kisan Dhondiba BalwadkarBalewadiPune
Gangubai Mahadu BalwadkarBalewadiPune
Akshada Shatrughna BalwadkarBalewadiPune
Sambhaji Shreepati BalwadkarBalewadiPune
Sopan Jaywant BalwadkarBalewadiPune
Shantaram Jaywant BalwadkarBalewadiPune
Tanaji Jaywant BalwadkarBalewadiPune
Shivaji Shreepati BalwadkarBalewadiPune

Approvals and building plan

Sanctioning authorityPune Mahanagarpalika
Permissible FSI18575.57
Proposed, not sanctioned18,576 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLaukik Apartments Bhandarkar Road Pune
Estimated costRs 207.00 cr
Cost incurredRs 9.62 cr
Work done4.65%
BuildingWingEstimatedIncurred
Kakkad OneworldNARs 180.22 crRs 9.62 cr
-NARs 26.78 cr-

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDSP Design Associates Pvt Ltd
ArchitectKetan Chavan
ArchitectManoj Tatooskar
EngineerDelcon Structure Consultant Pvt Ltd
EngineerSavan Padmawar
Chartered AccountantLathi and Tapdiya
Chartered AccountantKiran Kanani
Chartered AccountantC V Deshpande
PartnerRole in project
Kakkad Erectors LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P52100055312/WarDec 2028 → Jan 2031

Reason as filed by the promoterNA

EA04062621235Dec 2028 → Sep 2030

Reason as filed by the promoterThe registered project comprises commercial building structures. The delay in the project has occurred due to changes in planning, pursuant to which the Commencement Certificate (CC) was obtained from the respective authority in 20-11-2025. The said changes and approvals have been duly updated on the MahaRERA portal In view of the above circumstances, we hereby request an extension of the project completion timeline up to 30-09-2030.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Feb 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jan 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jan 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jan 2031

Documents filed118

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 118 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2025-2026)File: Form 5 Kakkad oneworld.PDF19 Aug 2026
Withdrawal Update Form 1File: Form 1 kakkad oneworld june 26.PDF14 Aug 2026
Withdrawal Update Form 2File: Form 2 K Oneworld june 26.PDF14 Aug 2026
Withdrawal Update Form 3File: Form 3 kakkad oneworld june 26.PDF14 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A 2025 26 One World_29062026162350.PDF29 Jun 2026
Withdrawal Update Form 1File: Form 1 march 26 Kakkad Oneworld.PDF15 May 2026
Withdrawal Update Form 2File: Form 2 March 26 Kakkad Oneworld.PDF15 May 2026
Withdrawal Update Form 3File: Form 3 March 26 Kakkad Oneworld.PDF15 May 2026
Layout approvalFile: 1-06.pdf29 Jan 2026
Building plan approvalFile: 1-06.pdf29 Jan 2026
Building plan approvalFile: 2-6.pdf29 Jan 2026
Building plan approvalFile: 3-6.pdf29 Jan 2026
Building plan approvalFile: 4-6.pdf29 Jan 2026
Building plan approvalFile: 5-06.pdf29 Jan 2026
Building plan approvalFile: 6-6.pdf29 Jan 2026
Form 1File: Form 1 dec 26_08012026142231.PDF29 Jan 2026
Form 2File: Form 2 dec 26.PDF29 Jan 2026
Form 3File: Form 3_23012026123516.PDF29 Jan 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold_27012026173504.PDF29 Jan 2026
OthersFile: Form 2A dec 25_27012026173412.PDF29 Jan 2026
Form 1File: 2 Architect’s Certificate of Percentage of Completion of Work (Form 1) (2).pdf11 Dec 2025
Form 3File: 2 CA Certificate on Project Cost & Fund withdrawal (Form 3) (2).pdf11 Dec 2025
Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_ booked inventory (3).pdf11 Dec 2025
OthersFile: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24) (2).pdf11 Dec 2025
Form 2File: 2 Engineer’s Certificate on Cost Incurred on Project (Form 2) (3).pdf11 Dec 2025
Form 1File: 3 Architect’s Certificate of Percentage of Completion of Work (Form 1) (1).pdf11 Dec 2025
Form 2File: 3 Engineer’s Certificate on Cost Incurred on Project (Form 2) (2).pdf11 Dec 2025
Form 3File: Form 3 June 2024 Kakkad Oneworld.PDF11 Dec 2025
Disclosure of Sold and Booked InventoryFile: 2 Disclosure of sold_ booked inventory (3).pdf11 Dec 2025
OthersFile: 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24) (2).pdf11 Dec 2025
Form 1File: 4 Architect’s Certificate of Percentage of Completion of Work (Form 1) (1).pdf11 Dec 2025
Form 2File: 4 Engineer’s Certificate on Cost Incurred on Project (Form 2) (2).pdf11 Dec 2025
Form 3File: Form 3 Sept 2024 Kakkad Oneworld.PDF11 Dec 2025
Disclosure of Sold and Booked InventoryFile: 3 Disclosure of sold_ booked inventory (2).pdf11 Dec 2025
OthersFile: 3 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24) (2).pdf11 Dec 2025
Form 1File: Form 1 dec 24 Kakkad oneworld.PDF11 Dec 2025
Form 2File: 5 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1).pdf11 Dec 2025
Form 3File: Form 3 Dec 2024.PDF11 Dec 2025
Disclosure of Sold and Booked InventoryFile: 4 Disclosure of sold_ booked inventory (2).pdf11 Dec 2025
OthersFile: 4 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24) (2).pdf11 Dec 2025
Form 1File: Form 1 March25 Kakkad Oneworld.PDF11 Dec 2025
Form 2File: Form 2 march 25 Kakkad Oneworld.PDF11 Dec 2025
Form 3File: From3 march 31 2025.PDF11 Dec 2025
Disclosure of Sold and Booked InventoryFile: Disclosure inventory 31 03 2025_11122025141033.PDF11 Dec 2025
OthersFile: Form 2A march 25 Kakkad Oneworld.PDF11 Dec 2025
Form 1File: Form 1 june 25 Kakkad Oneworld.PDF11 Dec 2025
Form 2File: Form 2 june 25 Kakkad Oneworld.PDF11 Dec 2025
Form 3File: From3 june 30 2025.PDF11 Dec 2025
Disclosure of Sold and Booked InventoryFile: Disclosure inventory 30 06 2025_11122025140927.PDF11 Dec 2025
OthersFile: Form 2A June 25 Kakkad Oneworld.pdf11 Dec 2025
Form 1File: Form 1 Kakkad Oneworld Oct 25.pdf11 Dec 2025
Form 2File: Form 2 Kakkad Oneworld 01 10 2025_29112025122402.PDF11 Dec 2025
Form 3File: From3 september30 2025.PDF11 Dec 2025
Disclosure of Sold and Booked InventoryFile: Disclosure inventory 30 09 2025_11122025141002.PDF11 Dec 2025
OthersFile: Form 2A sept 25_08122025175528.PDF11 Dec 2025
Form 5 (FY 2023-2024)File: Form 5 march 2024_11022025181852.PDF11 Dec 2025
Form 5 (FY 2024-2025)File: Form 5 kakkad erectors llp 24-25.PDF27 Sep 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 kakkad Erectors llp march 31 2024_13032025120438.PDF17 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 march 2024_11022025181852.PDF11 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 march 24_30012025110923.PDF1 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 june 24_30012025111032.PDF1 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 sept 24_30012025111151.PDF1 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 dec 24_30012025111326.PDF1 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 march 24_28012025174115.PDF29 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 june 24_28012025173928.PDF29 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 sept 24_28012025172517.PDF29 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 dec 24_28012025172151.PDF29 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure june 24_28012025181918.PDF29 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure sept 24_28012025181942.PDF29 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure dec 24_28012025181836.PDF29 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A june 24_28012025173849.PDF29 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A sept 24_28012025173746.PDF29 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A dec 24_28012025172328.PDF29 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kakkad onewold form 1 march24.PDF22 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 march 24.PDF22 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A March 24.PDF22 Jun 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory march 24.PDF22 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Kakkad Erectors LLP.pdf28 Feb 2024
Other - FinanceFile: CA Certificate Kakkad One World.pdf21 Feb 2024
Other - TechnicalFile: Annexure A_21022024163544.PDF21 Feb 2024

How this compares with Pune

2%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 25 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Kakkad Oneworld on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Balewadi13,700+ in Pune

2 kmKakkad OneworldCompleted 128Lapsed / revoked 43Other 122Dot size: filed unitsN

Filed coordinates, straight-line distance. 293 registered projects within 2 km.

Builder: Kakkad Erectors LLP

Kakkad Erectors LLP has 1 registration on MahaRERA, including Kakkad Oneworld. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Kakkad Oneworld is delayed beyond 30 Jan 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Kakkad Oneworld?

The registered promoter entity is Kakkad Erectors LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Kakkad Oneworld?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Kakkad Oneworld?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Kakkad Oneworld?

The professionals named in the filing: Architect: DSP Design Associates Pvt Ltd; Architect: Ketan Chavan; Architect: Manoj Tatooskar; Engineer: Delcon Structure Consultant Pvt Ltd; Engineer: Savan Padmawar; Chartered Accountant: Lathi and Tapdiya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Kakkad Oneworld?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Kakkad Oneworld. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Kakkad Oneworld to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.