ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / Kailash Homes

Completed No litigation declared Residential / Group Housing project

Kailash Homes

By Shree Laxmi Enterprises

RG-MH-02871 · RERA P51700020561 · Last updated on MahaRERA portal: 14 Jan 2025

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
May 2025Possession promisedregistration recorded completed
22 of 22Construction stages doneacross 2 buildings; every applicable stage filed complete
1Complaints at MahaRERAon this registration
Jump to the 94 documents Report an error

Kailash Homes is a Residential / Group Housing project by Shree Laxmi Enterprises in Thane, Maharashtra, registered with MahaRERA as P51700020561 on 22 Apr 2019. The registration is recorded completed; possession was promised by 22 May 2025. The completion date has moved by 24 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameKailash Homes
  • TypeResidential / Group Housing
  • Location
    • Gauripada Road
    • Gauripada
    • Kalyan-Dombivali (M Corp.)
    • Kalyan
    • Thane
    • 421301
  • Pincode421301
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700020561
  • ReraGenie IDRG-MH-02871

Builder

  • NameShree Laxmi Enterprises
  • Entity typePartnership
  • PartnersNarendra Arjan Dhanani, Ashok Motiram Chawla, Pritam Motiram Chawla, Mahender Arjan Dhanani
  • Other registrations3 more →
  • Completed2 of 4
  • Past their filed date1
  • Declared earlier projects1 →

Key dates

this monthRegisteredApr 2019First promiseMay 2023Revised toMay 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on22 Apr 2019
  • Promised completion22 May 2025
  • Revised completionRevised to 22 May 2025 (originally 22 May 2023)
  • Buildings2 building records
  • Documents filed94 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WingNA160000
B WingNA160000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 14 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 22 construction stages are filed complete across 2 buildings.

A Wing100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B Wing100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 14 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed17

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots17
Closed/Covered17
BuildingClosed/CoveredTotal
A Wing66
B Wing1111

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,700 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityKalyan Dombivli MahanagarPalika, Kalyan
Permissible FSI5778.43
Proposed, not sanctioned5,778 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMurbad Road Opp Purnima Talkies Kalyan West - 421301

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCreations Architects & Interior Designers
EngineerEpicons Consultants Pvt Ltd
Chartered AccountantS Nagwekar & Co
Chartered AccountantBhupendra P Shah & Co
PartnerRole in project
Shree Laxmi Enterprises-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700017225May 2023 → May 2024

Reason as filed by the promoterOC for 15th Floor (Building - A) will be issued only after handing over of Hospital to Kalyan-Dombivali Municipal Corporation.

EXT51700024422May 2023 → May 2025

Reason as filed by the promoterWe have received Part OC for Wing A upto 14th Floor. OC for 15th Floor will be issued only after handing over Hospital to Kalyan-Dombivali Municipal Corporation.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000396851ankit ramashray yadavshree laxmi enterprises29/07/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Mar 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Mar 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Mar 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Mar 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 21 Oct 2024

Documents filed94

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 94 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: Form3 Kailash homes 9 oct24.pdf14 Jan 2025
Disclosure of sold/ booked inventoryFile: sold unsold 9 oct2024.pdf14 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 dt 09 oct 2024 KH.pdf13 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2 Kailash homes 9 oct 24.pdf13 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Form 4 and Final OC KH.pdf21 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC final KH.pdf18 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: MD disclosure.pdf5 Aug 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: ND disclosure.pdf5 Aug 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: AC disclosure.pdf5 Aug 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: PC disclosure.pdf5 Aug 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: declaration separate bank kailash Homes.pdf30 Jul 2024
Declaration in FORM BFile: FormB declaration.pdf9 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 Arch June24.pdf9 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2 engg Kailash Homes June24.pdf9 Jul 2024
Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD JUNE24 Kailash homes.pdf9 Jul 2024
Certificates of CA (Form 3)File: Form3 Kailash Homes June24.pdf9 Jul 2024
Other - TechnicalFile: site super homes june24.pdf9 Jul 2024
Disclosure of sold/ booked inventoryFile: sold-unsold Mar24 - Kailash Homes.pdf17 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form5 fy23-24.pdf17 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: SITE SUPERVISOR Kailash Homes fy23-24.pdf16 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2 Kailash Homes Mar24.pdf15 May 2024
Certificates of CA (Form 3)File: Form3 CA Kailash Homes Mar-24.pdf15 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Archi certi Mar 24.pdf5 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Kailash Homes Form2 sept23.pdf30 Dec 2023
Disclosure of sold/ booked inventoryFile: Kailash Homes sold-unsold.pdf30 Dec 2023
Certificates of CA (Form 3)File: Kailash homes sept23 form3.pdf26 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Homes arch sept23.pdf18 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Sept22 form2.pdf17 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Mar23 kailash homes.pdf17 Aug 2023
Certificates of CA (Form 3)File: Form3 FY2022-23.pdf17 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form5 FY22-23.pdf17 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Site super Kailash Homes.pdf2 Aug 2023
Declaration about Commencement CertificateFile: Declaration cc.pdf1 Aug 2023
Declaration in FORM BFile: FormB Kailash Homes.pdf1 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1sept19.pdf1 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2Mar20.pdf1 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3Sept20.pdf1 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 4mar21.pdf1 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 5sept21.pdf1 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 6mar22.pdf1 Aug 2023
Disclosure of sold/ booked inventoryFile: sold-unsold june23_compressed.pdf1 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Homes fy22-23 site supervisor.pdf21 Jul 2023
Disclosure of sold/ booked inventoryFile: sold unsold Mar 23 Homes.pdf7 Jun 2023
Architect’s Certificate on Completion of Project (Form 4)File: form4 Arch comple.pdf26 May 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC and Arch letter.pdf20 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Homes Mar23.pdf11 Apr 2023
Certificates of CA (Form 3)File: CA Certificate KH.pdf24 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA form1 Mar21.pdf28 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Form1 Sept 21 compressed.pdf28 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Form1 Mar 22 compressed.pdf28 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Form 1 Sept 22.pdf28 Jan 2023
Disclosure of sold/ booked inventoryFile: Kailash Homes sold unsold Sept22.pdf28 Jan 2023
Certificates of CA (Form 3)File: Form3Homes Mar22.pdf11 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form5 Homes.pdf11 Nov 2022
Details of encumbrances concerned to FinanceFile: KHomes.pdf31 Oct 2022
Details of encumbrances concerned to LegalFile: KHomes.pdf31 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2a form.pdf31 Oct 2022
Proforma of Agreement for saleFile: Agree for Sale draft.pdf31 Oct 2022
Disclosure of sold/ booked inventoryFile: Kailash Homes sold unsold.pdf20 Aug 2022
Disclosure of sold/ booked inventoryFile: sold unsold sept21.pdf16 May 2022
Certificates of CA (Form 3)File: form-3 sept21.pdf16 May 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold Kailash Homes.pdf17 Feb 2022
CERSAI detailsFile: CERSAI_Search_Report_200228475388_For_Debtor_Based_Search_20_01_2022_15_19_16_314.pdf15 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 05 Homes.pdf15 Feb 2022
Certificates of CA (Form 3)File: Form3 KH.pdf11 Feb 2022
Declaration about Commencement CertificateFile: Declaration about CC.pdf10 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: site supervisor .pdf17 Dec 2021
Certificates of CA (Form 3)File: Form 3 Kailash Homes.pdf15 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: SITE SUPERVISOR HOMES.pdf9 Apr 2021
Certificates of CA (Form 3)File: FORM3 Kailash Homes.pdf5 Apr 2021
Certificates of CA (Form 3)File: form 3 Kailash Homes.pdf5 Apr 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 KAILASH HOMES.pdf5 Apr 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Site super certi1.pdf17 Feb 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: site super certi2.pdf17 Feb 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: site super certi3.pdf17 Feb 2020
Certificates of CA (Form 3)File: Form 3.pdf29 Mar 2019
Copy of the legal title reportFile: Title Certificate.pdf27 Mar 2019
Details of encumbrancesFile: Encumbrances letter.pdf27 Mar 2019
Proforma of Allotment letterFile: Agree for Sale dtaft.pdf27 Mar 2019
Layout approvalFile: HPSCANNER0857.pdf14 Mar 2019

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 24 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Kailash Homes on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Gauripada7,600+ in Thane

2 kmKailash HomesCompleted 53Lapsed / revoked 52Other 85Dot size: filed unitsN

Filed coordinates, straight-line distance. 190 registered projects within 2 km.

Builder: Shree Laxmi Enterprises

SHREE LAXMI ENTERPRISES has 4 registrations on MahaRERA, including Kailash Gardens and Kailash Homes. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Kailash Homes is delayed beyond 22 May 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Kailash Homes?

The registered promoter entity is Shree Laxmi Enterprises, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Kailash Homes?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Kailash Homes?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Kailash Homes?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Kailash Homes?

The professionals named in the filing: Architect: Creations Architects & Interior Designers; Engineer: Epicons Consultants Pvt Ltd; Chartered Accountant: S Nagwekar & Co; Chartered Accountant: Bhupendra P Shah & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Kailash Homes?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Kailash Homes. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Kailash Homes to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.