Home / Browse projects / Raigarh, Maharashtra / Kaamdhenu Luxuria

Completed No litigation declared Residential / Group Housing project

Kaamdhenu Luxuria

By Kaamdhenu Builders

RG-MH-01828 · RERA P52000000786 · Last updated on MahaRERA portal: 22 May 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 9 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Jun 2023Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 53 documents Report an error

Kaamdhenu Luxuria is a Residential / Group Housing project by Kaamdhenu Builders in Raigarh, Maharashtra, registered with MahaRERA as P52000000786 on 23 Jul 2017. The registration is recorded completed; possession was promised by 30 Jun 2023. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameKaamdhenu Luxuria
  • TypeResidential / Group Housing
  • Location
    • Sector - 54
    • Dronagiri
    • Bokadvira
    • Uran
    • Raigarh
    • 400702
  • Pincode400702
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000000786
  • ReraGenie IDRG-MH-01828

Builder

  • NameKaamdhenu Builders
  • Entity typePartnership
  • PartnersParveen Satish Sabhlok, Monica Satish Sabhlok, Punit Sabhluk
  • Other registrations1 more →
  • Completed2 of 2
  • Declared earlier projects4 →

Key dates

this monthRegisteredJul 2017First promiseSep 2022Revised toJun 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on23 Jul 2017
  • Promised completion30 Jun 2023
  • Revised completionRevised to 30 Jun 2023 (originally 30 Sep 2022)
  • Buildings1 building record
  • Documents filed53 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Kaamdhenu LuxuriaNA230000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 May 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

Kaamdhenu Luxuria: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities21

As on 22 May 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
Sitout AreaNoNot applicable
Sai Baba MandirNoNot applicable
Landscaped Podium GardenNoNot applicable
Kids Play ZoneNoNot applicable
Indoor GamesNoNot applicable
Fitness CenterNoNot applicable

Parking filed43

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots43
Closed/Covered40
Open Space3

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,250 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1869.28
Proposed, not sanctioned1,869 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchP B No 172 No 51 Apsara Apartments Sector 17 Vashi Navi Mumbai 400703

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSoyuz Talib Architects Pvt Ltd
EngineerAssociated Consultants
PartnerRole in project
Kaamdhenu Builders-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000011612Sep 2022 → Dec 2022

Reason as filed by the promoterPROJECT IS UNDER OCCUPANCY APPLICATION

EXT52000013812Sep 2022 → Jun 2023

Reason as filed by the promoterProject under occupancy application & Process

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Aug 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 14 Apr 2023

Documents filed53

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: Form 3 Kaamdhenu Luxuria as on 15-03-2023 (Signed).pdf22 May 2024
Declaration about Commencement CertificateFile: D.pdf13 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F1.pdf13 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A - 19-20.pdf13 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A - 20-21.pdf13 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A - 21-22.pdf13 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A - 22-23.pdf13 May 2024
Architect’s Certificate on Completion of Project (Form 4)File: F4.pdf13 May 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: S F.pdf13 May 2024
Status of ConveyanceFile: Conveyance.pdf13 May 2024
Certificates of CA (Form 5)File: Form 5.pdf16 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf28 Sep 2023
Certificates of CA (Form 5)File: Form 5.pdf26 Sep 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 1 Occupancy Certificate_ Completion Certificate_ Architect's certificate of completion for14 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC_Certifecate KAAMDHENU LUXURIA.pdf14 Apr 2023
Declaration about Commencement CertificateFile: K LUXURIA CC .pdf29 Mar 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A - Quality Assurance - Kaamdhenu Luxuria.pdf29 Mar 2022
Disclosure of sold/ booked inventoryFile: sold unsold k luxuria.pdf29 Mar 2022
Certificates of CA (Form 5)File: Kaamdhenu - Luxuria - Form 5 (1).pdf30 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Kaamdhenu - Luxuria - Form 5 (1).pdf30 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 rera form 1 k luxuria architects certificate.pdf26 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2RERA FORM 2- K LUXURIA- upto june 2021.pdf4 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2RERA FORM 2- K LUXURIA- upto june 2021.pdf4 Aug 2021
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD LUXURIA.pdf15 Jul 2021
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD LUXURIA.pdf15 Jul 2021
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD LUXURIA.pdf15 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Rera audit fy 2018-19Kaamdhenu Luxuria.pdf1 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 1 Rera Audit Kaamdhenu Luxuria_Form 5.pdf1 Jul 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: luxuria soyuz talib.pdf1 Jul 2021
Certificates of CA (Form 5)File: Kaamdhenu Luxuria Form 5 2019-20.pdf29 Sep 2020
Certificates of CA (Form 5)File: Kaamdhenu Luxuria.pdf30 Sep 2019
Certificates of CA (Form 5)File: MahaRera Form 5_Luxuria.pdf28 Sep 2018
Commencement Certificates / NA Order for plotted developmentFile: C C.pdf3 Aug 2017
Proforma of Allotment letterFile: AGREEMENT FOR SALE (RERA) - KAAMDHENU LUXURIA.pdf19 Jul 2017
Details of encumbrancesFile: no encumbrances certificate.PDF18 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS CERTIFICATE.pdf18 Jul 2017
Certificates of CA (Form 3)File: KAAMDHENU_CERTIFICATE.pdf18 Jul 2017
Building plan approvalFile: PLAN 2.pdf17 Jul 2017
Building plan approvalFile: PLAN 3.pdf17 Jul 2017
Building plan approvalFile: PLAN 4.pdf17 Jul 2017
Building plan approvalFile: PLAN 5.pdf17 Jul 2017
Layout approvalFile: PLAN 1.pdf17 Jul 2017
Building plan approvalFile: PLAN 1.pdf17 Jul 2017
PAN CardFile: kaamdhenu pan card.PDF17 Jul 2017
Copy of the legal title reportFile: TITLE CERTIFICATE.pdf17 Jul 2017
Copy of Layout Approval (in case of layout)File: PLAN 1.pdf17 Jul 2017
Building Plan Approval (IOD)File: PLAN 1.pdf17 Jul 2017
Building Plan Approval (IOD)File: PLAN 2.pdf17 Jul 2017
Building Plan Approval (IOD)File: PLAN 3.pdf17 Jul 2017
Building Plan Approval (IOD)File: PLAN 4.pdf17 Jul 2017
Building Plan Approval (IOD)File: PLAN 5.pdf17 Jul 2017
Declaration in FORM BFile: FORM B.pdf17 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - Luxuria RERA.PDF17 Jul 2017

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Sai RamPlot No 125 Sector 5 Karanjade Navi Mumbai21CompletedDec 2014Late, Nov 2016
Sai AnantPlot No 12 Sector 30 Vashi Navi Mumbai29CompletedJun 2014Late, Sep 2015
Sai AshokPlot No 72 Sector 6 Karanjade Navi Mumbai17CompletedDec 2013Late, Mar 2017
Sai VeeraPlot No 26B Sector 11 Kopar Khairane Navi Mumbai20CompletedMay 2011Late, Nov 2012

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one moved by 9 months
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Kaamdhenu Luxuria on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dronagiri5,900+ in Raigarh

2 kmKaamdhenu LuxuriaCompleted 55Lapsed / revoked 18Other 30Dot size: filed unitsN

Filed coordinates, straight-line distance. 103 registered projects within 2 km.

Builder: Kaamdhenu Builders

Kaamdhenu Builders has 2 registrations on MahaRERA, including Kaamdhenu Luxuria and Kaamdhenu Celestia. Its filings disclose 4 earlier MahaRERA projects: declares 0 of 4 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Kaamdhenu Luxuria is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Kaamdhenu Luxuria?

The registered promoter entity is Kaamdhenu Builders, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Kaamdhenu Luxuria?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Kaamdhenu Luxuria?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Kaamdhenu Luxuria?

The professionals named in the filing: Architect: Soyuz Talib Architects Pvt Ltd; Engineer: Associated Consultants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Kaamdhenu Luxuria?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Kaamdhenu Luxuria. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Kaamdhenu Luxuria to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.