ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / JUBILEE PARK

Registration lapsed No litigation declared Others project

JUBILEE PARK

By AURANGABAD HOLIDAY RESORTS

RG-MH-24093 · RERA P52100007295 · Last updated on MahaRERA portal: 10 Nov 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 58 months past the filed date
  • 11 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2021Possession promised58 months past this date
9 of 11Construction stages donefurthest along: Installation of Lifts, 86%
16 of 43Units unsoldnot recorded sold or booked
11Complaints at MahaRERAon this registration
Jump to the 29 documents Report an error

JUBILEE PARK is a Others project by AURANGABAD HOLIDAY RESORTS in Pune, Maharashtra, registered with MahaRERA as P52100007295 on 17 Aug 2017. Possession was promised by 30 Dec 2021 and is now 58 months past that date. 27 of the 43 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete. 11 complaints are on record with the regulator.

At a glance

Project

  • NameJUBILEE PARK
  • TypeOthers
  • Location
    • WARJE
    • Haveli
    • Pune
    • 411058
  • Pincode411058
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100007295
  • ReraGenie IDRG-MH-24093

Builder

  • NameAURANGABAD HOLIDAY RESORTS
  • Entity typePartnership
  • GSTIN27AAPFA1100L1ZN
  • PartnerPOONAM RAJESH PAWAR

Key dates

58 months past promisethis monthRegisteredAug 2017PromisedDec 2021

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on17 Aug 2017
  • Promised completion30 Dec 2021
  • Revised completionNone
  • Buildings1 building record
  • Documents filed29 files

Current status

63%27 of 43 units booked

Figures as on 10 Nov 2023, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING BNA171143043

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Nov 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 86%.

WING B: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.86%

Progress on shared amenities16

As on 10 Nov 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
WATCHMAN CABIN AND ENTRANCE GATEYes0%

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area734 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityPUNE MUNICIPAL CORPORATION
Permissible FSI3662.45
Proposed, not sanctioned3,662 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch1732, SADASHIV PETH, TILAK ROAD, PUNE 411030

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDILIP G KALE
ArchitectPRAJKTA V GORE
EngineerJAYANT V INAMDAR
EngineerTEJAS S MANDLECHA
Chartered AccountantCA SIDDHANT ABHAY BORA
Chartered AccountantSPCM & ASSOCIATES
PartnerRole in project
AURANGABAD HOLIDAY RESORTS-

Litigation declared1

CaseCourtStatus
4255/2015CHIEF JUDICIAL MAGISTRATE EVIDENCE BEFORE CHARGE

Complaints filed with MahaRERA11

Case no.ComplainantRespondentFiled
CC005000000022870Rahul Ganpatrao NarawdeAurangabad Holiday Resorts06/04/2019
CC005000000023416Pushkar DeshpandeAurangabad Holiday Resorts10/09/2019
CC005000000023427Rasik MahajanAurangabad Holiday Resorts14/09/2019
CC005000000023426Manoj BardeAurangabad Holiday Resorts14/09/2019
CC005000000033471Mangilal ChoudharyAurangabad Holiday Resorts25/09/2019
CC005000000043660Shridhar ParundekarAurangabad Holiday Resorts19/11/2019
CC005000000023446Chetan KathalayAurangabad Holiday Resorts18/09/2019
CC005000000033467Shashikant KulkarniAurangabad Holiday Resorts24/09/2019
CC005000000033468Hrishikesh KulkarniAurangabad Holiday Resorts24/09/2019
CC005000000033466Raju DixitAurangabad Holiday Resorts24/09/2019
CC005000000095819Mrs. Vidula Girish RaoAurangabad Holiday Resorts17/11/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed29

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Other - TechnicalFile: Letter to MahaRERA.pdf10 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf12 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 aurangabad holiday.pdf11 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 03312022.pdf7 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 03312023.pdf7 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 03312023.pdf7 Oct 2023
Certificates of CA (Form 3)File: RERA FORM 3 (2021-22).pdf7 Oct 2023
Certificates of CA (Form 3)File: RERA FORM 3 (2022-23).pdf7 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA FORM 5 (2021-22).pdf7 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RERA FORM 5 (2022-23).pdf7 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera certificate Aurangabad holiday resort.pdf14 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 05-SIGNED.pdf13 Jan 2022
Layout approvalFile: Layout Plan .pdf31 Jul 2017
Building plan approvalFile: EVEN EIGHT FLOOR PLAN.pdf31 Jul 2017
Building plan approvalFile: ODD FLOOR PLAN.pdf31 Jul 2017
PAN CardFile: Company pan Card.pdf31 Jul 2017
Copy of the legal title reportFile: Supplementrary title opinion.pdf31 Jul 2017
Copy of the legal title reportFile: TITLE OPINION.pdf31 Jul 2017
Copy of the legal title reportFile: Supplementary legal report.pdf31 Jul 2017
Details of encumbrancesFile: Encumbrance Certificate.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Plan .pdf31 Jul 2017
Building Plan Approval (IOD)File: ODD FLOOR PLAN.pdf31 Jul 2017
Building Plan Approval (IOD)File: EVEN EIGHT FLOOR PLAN.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commncment Certificate.pdf31 Jul 2017
Declaration in FORM BFile: FORM B1.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf31 Jul 2017
Certificates of CA (Form 3)File: FORM 3 CA CERTIFICATE.pdf31 Jul 2017
Proforma of Allotment letterFile: Flat Sale Draft.pdf31 Jul 2017

How this compares with Pune

63%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep JUBILEE PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near WARJE13,700+ in Pune

2 kmJUBILEE PARKCompleted 25Lapsed / revoked 8Other 21Dot size: filed unitsN

Filed coordinates, straight-line distance. 54 registered projects within 2 km.

Builder: AURANGABAD HOLIDAY RESORTS

AURANGABAD HOLIDAY RESORTS has 1 registration on MahaRERA, including JUBILEE PARK. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that JUBILEE PARK shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if JUBILEE PARK is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of JUBILEE PARK?

The registered promoter entity is AURANGABAD HOLIDAY RESORTS, a partnership as per the filing. Its GSTIN 27AAPFA1100L1ZN can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in JUBILEE PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against JUBILEE PARK?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for JUBILEE PARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at JUBILEE PARK?

The professionals named in the filing: Architect: DILIP G KALE; Architect: PRAJKTA V GORE; Engineer: JAYANT V INAMDAR; Engineer: TEJAS S MANDLECHA; Chartered Accountant: CA SIDDHANT ABHAY BORA; Chartered Accountant: SPCM & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in JUBILEE PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About JUBILEE PARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save JUBILEE PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.