Home / Browse projects / Pune, Maharashtra / Vatika

Registration lapsed No litigation declared Others project

Vatika

By kishor Laxmanrao Nimhan

RG-MH-16957 · RERA P52100027403 · Last updated on MahaRERA portal: 11 Jul 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 13 months past the filed date
  • Rs 11.50 crore secured on the land, in favour of bank of india
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2025Possession promised13 months past this date
20 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
44 of 163Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 105 documents Report an error

Vatika is a Others project by kishor Laxmanrao Nimhan in Pune, Maharashtra, registered with MahaRERA as P52100027403 on 8 Dec 2020. Possession was promised by 30 Sep 2025 and is now 13 months past that date. 119 of the 163 units on this registration are recorded sold or booked, and 20 of 22 construction stages are filed complete.

At a glance

Project

  • NameVatika
  • TypeOthers
  • Location
    • Warje
    • Haveli
    • Pune
    • 411058
  • Pincode411058
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100027403
  • ReraGenie IDRG-MH-16957

Builder

  • Namekishor Laxmanrao Nimhan
  • Entity typeIndividual

Key dates

13 months past promisethis monthRegisteredDec 2020PromisedSep 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on8 Dec 2020
  • Promised completion30 Sep 2025
  • Revised completionNone
  • Buildings2 building records
  • Documents filed105 files

Current status

73%119 of 163 units booked
95.1%Work done, per cost certificate

Figures as on 11 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A Wing 1NA12864367
A Wing 2NA12896096

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 11 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

A Wing 191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A Wing 291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 11 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed82

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots82
Closed/Covered82
BuildingClosed/CoveredTotal
A Wing 13434
A Wing 24848

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area4,700 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofbank of india
Secured amountRs 11.50 crore
CERSAI search filedYes
Declared on30 Jun 2025

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI11866.72
Proposed, not sanctioned8,986 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBANER ROAD BANER
Estimated costRs 33.95 cr
Cost incurredRs 32.28 cr
Work done95.07%
BuildingWingEstimatedIncurred
A Wing 2NARs 19.75 crRs 18.43 cr
A Wing 1NARs 10.25 crRs 10.25 cr
-NARs 3.95 crRs 3.59 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Architectmanohar Yerawar
ArchitectManohar - Yerawar
EngineerPRASHANT S KUMBHAR
Engineerprashant - kumbhar
Chartered AccountantM S JOSHI AND ASSOCIATES
Chartered AccountantJOSHI & RAYKAR
Chartered Accountantm
PartnerRole in project
kishor Laxmanrao Nimhan-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Mar 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Mar 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Mar 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 21 Nov 2024

Documents filed105

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 105 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FROM NO 1 ARCHITECTS.pdf11 Jul 2026
Form 2File: FROM NO 2 ENGINEER.pdf11 Jul 2026
Form 3File: FROM NO 3 CA.pdf11 Jul 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold and booked inventory.pdf11 Jul 2026
Withdrawal Update Form 1File: FROM NO 1 ARCHITECTS.pdf11 Jul 2026
Withdrawal Update Form 1File: FROM NO 1 ARCHITECTS.pdf11 Jul 2026
Withdrawal Update Form 1File: FROM NO 1 ARCHITECTS.pdf11 Jul 2026
Withdrawal Update Form 2File: FROM NO 2 ENGINEER.pdf11 Jul 2026
Withdrawal Update Form 2File: FROM NO 2 ENGINEER.pdf11 Jul 2026
Withdrawal Update Form 2File: FROM NO 2 ENGINEER.pdf11 Jul 2026
Withdrawal Update Form 3File: FROM NO 3 CA.pdf11 Jul 2026
Withdrawal Update Form 3File: FROM NO 3 CA.pdf11 Jul 2026
Withdrawal Update Form 3File: FROM NO 3 CA.pdf11 Jul 2026
Form 5 (FY 2024-2025)File: VATIKA FROM 5 (1).pdf7 Oct 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kishor Nimhan Arch Certificate 1 Mb.pdf14 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kishor Nimhan C A Certificate Form 3 1Mb.pdf14 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Kishor Nimhan Engg Certificate 1 Mb.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: Kishor Nimhan Inventory 1 Mb.pdf14 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Kishor Nimhan Quality Certificate 1 Mb.pdf14 Feb 2025
OtherFile: Arch Certificate Form 4 1Mb New.pdf25 Nov 2024
Architect’s Certificate on Completion of Project (Form 4)File: Arch Certificate Form 4 1Mb New.pdf23 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate 1 Mb.pdf21 Nov 2024
Architect’s Certificate on Completion of Project (Form 4)File: Arch Certificate Form-4 1 Mb.pdf21 Nov 2024
Architect’s Certificate on Completion of Project (Form 4)File: Arch Certificate Form-4.pdf21 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate 1 Mb.pdf21 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate 1Mb.pdf21 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Complication part.pdf21 Nov 2024
Disclosure of sold/ booked inventoryFile: Inventory.pdf21 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Assurance 1 Mb.pdf21 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Warje Vatika Arch 1 Mb.pdf7 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Warje C A Certificate 1 Mb.pdf7 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Warje Engg Certificate 1 Mb.pdf7 Nov 2024
Disclosure of sold/ booked inventoryFile: Warje Inventory A1.pdf7 Nov 2024
Disclosure of sold/ booked inventoryFile: Warje Inventory A2.pdf7 Nov 2024
CERSAI detailsFile: CERSAI_Search_Report_200319779348_For_Asset_Based_Search_05_09_2024_17_29_13_057.pdf7 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Warje Quality Assurance 1 Mb.pdf7 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: C A Form5.pdf7 Nov 2024
Declaration about Commencement CertificateFile: Declaration About C C.pdf26 Mar 2024
Layout approvalFile: Lay out.pdf22 Mar 2024
Building plan approvalFile: Lay out.pdf22 Mar 2024
Copy of the legal title reportFile: Warje Search Report.pdf22 Mar 2024
Copy of Layout Approval (in case of layout)File: Lay out.pdf22 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: Lay out.pdf22 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: C C.pdf22 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ArchCertificate New .pdf22 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Warje Arch 1 Mb.pdf26 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Warje Engg 1 Mb.pdf26 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Warje Quality Assurance 1 Mb.pdf26 Feb 2024
Disclosure of sold/ booked inventoryFile: Warje Inventory A1 1 Mb.pdf26 Feb 2024
Disclosure of sold/ booked inventoryFile: Warje Inventory A2 1 Mb.pdf26 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Warje C A 1 Mb.pdf26 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf30 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf8 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 5.pdf13 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Warje Arch Certificate Vatika 1 Mb.pdf15 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Warje Enggineers Certificate.pdf15 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Warje C A Certificate Vatika 1 Mb.pdf15 Feb 2023
Other - TechnicalFile: Non SubmissionVatika.pdf15 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: From 5_signed.pdf27 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Warje Quality Certificate 1 Mb.pdf19 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Warje Arch Certificate Vatika 1 Mb.pdf10 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Warje Engg Certificate Vatika 1 Mb.pdf10 Jan 2023
Disclosure of sold/ booked inventoryFile: Warje A-1 Inventory.pdf10 Jan 2023
Disclosure of sold/ booked inventoryFile: Warje A-2 Inventory.pdf10 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Warje C A Certificate Vatika 1 Mb.pdf10 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf14 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate Vatika.pdf26 May 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engi Certificate Warje.pdf26 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Certificate Warje.pdf26 May 2022
Disclosure of sold/ booked inventoryFile: 03 05 Vatika A-1 Flat Inventory.pdf26 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Rera Certificate.pdf26 May 2022
Building plan approvalFile: bUILDING Layout.PDF2 Nov 2021
Building Plan Approval / NA Order for plotted developmentFile: bUILDING Layout.PDF2 Nov 2021
Details of encumbrancesFile: SelfCertificationVatika_compressed-compressed.pdf27 Oct 2021
Declaration about Commencement CertificateFile: 27102021 AboutCC- 1 MB.pdf27 Oct 2021
Declaration in FORM BFile: SelfCertificationVatika_compressed-compressed.pdf27 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate 181021-compressed.pdf27 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance 161021.pdf27 Oct 2021
Disclosure of sold/ booked inventoryFile: 27102021Wing1n2Warje- 1 MB.pdf27 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 C A.pdf27 Oct 2021

How this compares with Pune

73%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Vatika on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near warje13,700+ in Pune

2 kmVatikaCompleted 39Lapsed / revoked 24Other 45Dot size: filed unitsN

Filed coordinates, straight-line distance. 108 registered projects within 2 km.

Builder: kishor Laxmanrao Nimhan

kishor Laxmanrao Nimhan has 1 registration on MahaRERA, including Vatika. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Vatika shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Vatika is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Vatika?

The registered promoter entity is kishor Laxmanrao Nimhan, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Vatika?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Vatika?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Vatika?

The professionals named in the filing: Architect: manohar Yerawar; Architect: Manohar - Yerawar; Engineer: PRASHANT S KUMBHAR; Engineer: prashant - kumbhar; Chartered Accountant: M S JOSHI AND ASSOCIATES; Chartered Accountant: JOSHI & RAYKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vatika?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vatika. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vatika to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.