Home / Browse projects / Jewel of Queen

Registration lapsed Litigation declared Residential / Group Housing project

Jewel of Queen

By Bhairaav Kothari Realtors LLP

RG-MH-49560 · RERA P51900013962 · Last updated on MahaRERA portal: 25 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date
  • Litigation declared, 1 case

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Dec 2023Possession promised34 months past this date
4 of 11Construction stages donefurthest along: Podiums (if any), 40%
6 of 6Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 23 documents Report an error

Jewel of Queen is a Residential / Group Housing project by Bhairaav Kothari Realtors LLP in Girgaum, 400002, registered with MahaRERA as P51900013962 on 2 Nov 2017. Possession was promised by 30 Dec 2023 and is now 34 months past that date. 0 of the 6 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameJewel of Queen
  • TypeResidential / Group Housing
  • Location
    • Babasaheb Jaykar Marg
    • Girgaum
    • 400002
  • Pincode400002
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900013962
  • ReraGenie IDRG-MH-49560

Builder

  • NameBhairaav Kothari Realtors LLP
  • Entity typePartnership
  • GSTIN27AAOFB5172E1ZE
  • PartnersNarendra Kothari, Sunny Kothari, Madanlal Jain, Savita Jain

Key dates

34 months past promisethis monthRegisteredNov 2017PromisedDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on2 Nov 2017
  • Promised completion30 Dec 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed23 files

Current status

0%0 of 6 units booked

Figures as on 25 Feb 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
JOQ 1NA216606

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 40%.

JOQ 1: 40% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)40%
Plinth100%
Stilt Floor100%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 25 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed24

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots24
Closed/Covered24

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,230 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Kushalraj Land Developers Pvt Ltd-Mumbai City

Approvals and building plan

Sanctioning authorityBrihanmumbai Municipal Corporation
Permissible FSI11613.87
Proposed, not sanctioned2,614 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVeer Mahal CHS Ltd, Gr Flr, Shop No 9,10,11,12, Dr Babasaheb Ambedkar Rd, Lalbaug, Parel, Mumbai 400

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGirish Nerurkar
ArchitectSaurabh Chatterjee
Chartered AccountantK.Kaveria & Co.
PartnerRole in project
Bhairaav Kothari Realtors LLP-

Litigation declared1

CaseCourtStatus
2627/2014High CourtMatter listed for final hearing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Oct 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Oct 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Oct 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Dec 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed23

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Other - LegalFile: Arbitration Interim order 27 05 202-1-32.pdf25 Feb 2025
Other - LegalFile: Arbitration Interim order 27 05 202-33-64.pdf25 Feb 2025
Other - LegalFile: MAHARERA notice JOQ Reply C.pdf17 Dec 2024
Other - LegalFile: JOQ Declaration 29 12 2023.pdf29 Dec 2023
Details of encumbrancesFile: Annexure I Detail of Encumbrance.pdf19 Sep 2022
Declaration in FORM BFile: Form B.pdf19 Sep 2022
Details of encumbrancesFile: Encumbrance detail.pdf19 May 2022
Declaration in FORM BFile: RERA Form B Declaration.pdf19 May 2022
Commencement Certificates / NA Order for plotted developmentFile: Further CC.pdf18 Dec 2018
Certificates of CA (Form 5)File: BKRLLP -Form 5 Auditor Report 2017-2018.pdf31 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf27 Oct 2017
Building plan approvalFile: New IOD.pdf26 Oct 2017
Copy of the legal title reportFile: title certificat 311 .pdf26 Oct 2017
Copy of the legal title reportFile: title certificat 312.pdf26 Oct 2017
Copy of the legal title reportFile: titie certificat 313-314.pdf26 Oct 2017
Copy of the legal title reportFile: title certificat317.pdf26 Oct 2017
Details of encumbrancesFile: HC Order B.pdf26 Oct 2017
Building Plan Approval (IOD)File: New IOD.pdf26 Oct 2017
Declaration in FORM BFile: JOQ RERA form.pdf26 Oct 2017
Layout approvalFile: PHASE LAYOUT.pdf25 Oct 2017
Copy of Layout Approval (in case of layout)File: PHASE LAYOUT.pdf25 Oct 2017
Certificates of CA (Form 3)File: CA Certificate.pdf25 Oct 2017
Proforma of Allotment letterFile: BKRLLP Promoter Certificate.pdf25 Oct 2017

Keep Jewel of Queen on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Girgaum

2 kmJewel of QueenCompleted 6Lapsed / revoked 8Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 20 registered projects within 2 km.

Builder: Bhairaav Kothari Realtors LLP

Bhairaav Kothari Realtors LLP has 1 registration on MahaRERA, including Jewel of Queen. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record.

Frequently asked questions

What does it mean that Jewel of Queen shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Jewel of Queen is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Jewel of Queen?

The registered promoter entity is Bhairaav Kothari Realtors LLP, a partnership as per the filing. Its GSTIN 27AAOFB5172E1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Jewel of Queen?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Jewel of Queen?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Jewel of Queen?

The professionals named in the filing: Architect: Girish Nerurkar; Architect: Saurabh Chatterjee; Chartered Accountant: K.Kaveria & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Jewel of Queen?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Jewel of Queen. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Jewel of Queen to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.