Home / Browse projects / Mumbai Suburban, Maharashtra / Jekin Residency

Completed No litigation declared Residential / Group Housing project

Jekin Residency

By MUKESH BABULAL SHAH

RG-MH-21306 · RERA P51800012506 · Last updated on MahaRERA portal: 16 Mar 2022

Source: official MahaRERA filing

Red flags

  • Completion date moved by 18 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Apr 2022Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 29 documents Report an error

Jekin Residency is a Residential / Group Housing project by MUKESH BABULAL SHAH in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800012506 on 1 Sep 2017. The registration is recorded completed; possession was promised by 9 Apr 2022. The completion date has moved by 18 months from the original filing.

At a glance

Project

  • NameJekin Residency
  • TypeResidential / Group Housing
  • Location
    • Old nagardas road
    • parsi panchayat road
    • Mumbai
    • Andheri
    • Mumbai Suburban
    • 400069
  • Pincode400069
  • RERA no.P51800012506
  • ReraGenie IDRG-MH-21306

Builder

  • NameMUKESH BABULAL SHAH
  • Entity typeIndividual

Key dates

this monthRegisteredSep 2017First promiseOct 2020Revised toApr 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on1 Sep 2017
  • Promised completion9 Apr 2022
  • Revised completionRevised to 9 Apr 2022 (originally 9 Oct 2020)
  • Buildings1 building record
  • Documents filed29 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Jekin ResidencyNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Mar 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Jekin Residency: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 16 Mar 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed10

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots10
Closed/Covered9
Open Space1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area509 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2666.61
Proposed, not sanctioned1,017 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No- 2, Shroff Arcade, Sodawala Lane, Near Prabodhan, Mumbai-400092

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJeegar J. tanna (DIP Infrastructures and Projects Pvt. Ltd)
EngineerChintan V Patel
PartnerRole in project
MUKESH BABULAL SHAH-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800009820Oct 2020 → Oct 2021

Reason as filed by the promoterDear Sir, With reference to above, we are kindly pleading as under:- We kindly request you to grant us extension of our project by 3.5 months as due the Covid pandemic induced Lockdown, there was extreme shortage of labour and hence the project could not be completed on time. The project is in its final phases of completion and we beleive that extension as requested above would really help us to complete the project as well as oblige with the post completion formalities. Therefore, we request an extension of 3.5 months . We would be highly obliged by your co-operation. Thank You.

EXT51800008782Oct 2020 → Jun 2021

Reason as filed by the promoterRespected Sir, With reference to the above subject I would like to inform that the Deadline for completion of the above mentioned Project as mentioned on the RERA Site was 09/04/2020. However due to the Covid 19 Pandemic the construction was halted due to non availability of materials and labours. I have now started the work and intend to complete the ok within next 6 months hence I request you to give me and extension up to 30/06/2021 for the above project, Considering my request please do the needful

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Oct 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 13 Feb 2022

Documents filed29

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 COMPLETION CERTIFICATE 16-03-2022.pdf16 Mar 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC JEKIN RESIDENCY.pdf13 Feb 2022
Architect’s Certificate on Completion of Project (Form 4)File: Architect Certificate - Form 1 - Completion - 28092021.pdf13 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 31032020.pdf1 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM2A31032021.pdf1 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form5FY20172018.pdf1 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form5FY20182019.pdf1 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form5FY20192020.pdf1 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form5FY20202021.pdf1 Jul 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Architect Certificate June 302021.pdf1 Jul 2021
Declaration about Commencement CertificateFile: Disclosure about Commencement Certificate.pdf30 Jun 2021
Disclosure of sold/ booked inventoryFile: Discolsure of Sold Unsold Inventory.pdf30 Jun 2021
OtherFile: Consent of Allotees.pdf30 Jun 2021
Certificates of CA (Form 5)File: form 5 jimeet sir.pdf11 Jan 2019
PAN CardFile: PAN Card Mukesh Shah.pdf12 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: Full C C_c.pdf12 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: REVALIDATION LETTER, CHALLAN AND RECEIPT.pdf12 Oct 2018
Details of encumbrancesFile: Details of Encumbrances.pdf29 Jul 2017
Declaration in FORM BFile: Form B_Declaration.pdf29 Jul 2017
Proforma of Allotment letterFile: jekin Residency - RERA Sale Agreement new.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_form 1_final.pdf28 Jul 2017
Certificates of CA (Form 3)File: CA Certificate_Form 3.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_Form 2_final.pdf27 Jul 2017
Proforma of Allotment letterFile: Allotment Letter Proforma.pdf27 Jul 2017
Building plan approvalFile: IOD_.pdf26 Jul 2017
Layout approvalFile: Plan_final.pdf26 Jul 2017
Copy of the legal title reportFile: Title Certificate_.pdf26 Jul 2017
Copy of Layout Approval (in case of layout)File: Plan_final.pdf26 Jul 2017
Building Plan Approval (IOD)File: IOD_.pdf26 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 18 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Jekin Residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mumbai6,700+ in Mumbai Suburban

Builder: MUKESH BABULAL SHAH

MUKESH BABULAL SHAH has 1 registration on MahaRERA, including Jekin Residency. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Jekin Residency is delayed beyond 9 Apr 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Jekin Residency?

The registered promoter entity is MUKESH BABULAL SHAH, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Jekin Residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Jekin Residency?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Jekin Residency?

The professionals named in the filing: Architect: Jeegar J. tanna (DIP Infrastructures and Projects Pvt. Ltd); Engineer: Chintan V Patel. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Jekin Residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Jekin Residency. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Jekin Residency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.