Red flags
- Completion date moved by 60 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
JEEVAN PRADEEP CO OPERATIVE HOUSING SOCIETY LTD is a Residential / Group Housing project by BELVALKAR HOUSING LLP in Pune, Maharashtra, registered with MahaRERA as P52100052944 on 5 Oct 2023. Possession is promised by 31 Jul 2031. The completion date has moved by 60 months from the original filing. 0 of the 35 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.
At a glance
Project
- NameJEEVAN PRADEEP CO OPERATIVE HOUSING SOCIETY LTD
- TypeResidential / Group Housing
- Location
- HARI KRISHNA MANDIR ROAD
- MODEL COLONY
- Pune (M Corp.)
- Pune City
- Pune
- 411016
- Pincode411016
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100052944
- ReraGenie IDRG-MH-41824
Builder
- NameBELVALKAR HOUSING LLP
- Entity typePartnership
- LLPINAAD-1077
- GSTIN27AAOFB7578A1Z8
- LLPIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- Designated PartnersNeel BELVALKAR, Sameer Sharatchandra Belvalkar
- Other registrations12 more →
- Completed1 of 13
- No longer live1 lapsed, de-registered or revoked
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on5 Oct 2023
- Promised completion31 Jul 2031
- Revised completionRevised to 31 Jul 2031 (originally 31 Jul 2026)
- Buildings1 building record
- Documents filed102 files
Current status
Figures as on 4 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| JEEVAN PRADEEP CO-OPERATIVE HOUSING SOCIETY LTD | NA | 13 | 12 | 35 | 0 | 35 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 4 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.
JEEVAN PRADEEP CO-OPERATIVE HOUSING SOCIETY LTD: 0% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 4 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed52
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership19
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| KIRAN RAM MOGHE | Pune (M Corp.) | Pune |
| YOGITA SACHIN SOLANKE | Pune (M Corp.) | Pune |
| VIJAY KALYANSUNDARAM SHASTRI | Pune (M Corp.) | Pune |
| ABHIJIT PRAKASH JOSHI | Pune (M Corp.) | Pune |
| PRAKASH RAMCHANDRA LONDHE | Pune (M Corp.) | Pune |
| JAYASHREE BHANUDAS MEHTA | Pune (M Corp.) | Pune |
| LATA NARAYAN PANDIT | Pune (M Corp.) | Pune |
| ASHOK RAMESH DONGRE | Pune (M Corp.) | Pune |
| SANCHARIKA RANJAN BANERJEE | Pune (M Corp.) | Pune |
| SHWETAMBARI SHARADKUMAR SHETYE | Pune (M Corp.) | Pune |
| JAY RAM MOGHE | Pune (M Corp.) | Pune |
| CHAITRALI DYANESHWAR SHINDE | Pune (M Corp.) | Pune |
| DYANESHWAR DAGDU SHINDE | Pune (M Corp.) | Pune |
| LEENA ABHIJIT JOSHI | Pune (M Corp.) | Pune |
| SANGITA PRAKASH LONDHE | Pune (M Corp.) | Pune |
| PUSHAPA NICHOLAS SALDHANA | Pune (M Corp.) | Pune |
| ANITA ARUN SABNIS | Pune (M Corp.) | Pune |
| DR NIREN RAMESH DONGRE | Pune (M Corp.) | Pune |
| JEEVAN PRADEEP CO OPERATIVE HOUSING SOCIETY LTD | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| JEEVAN PRADEEP CO-OPERATIVE HOUSING SOCIETY LTD | NA | Rs 17.47 cr | Rs 17.65 lakh |
| - | NA | Rs 99.77 lakh | Rs 22.63 lakh |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MANOJ TATOOSKAR |
| Engineer | VIVEK CHAVAN |
| Chartered Accountant | Billimoria and Associates |
| Chartered Accountant | CA Pushpak Bogati |
| Chartered Accountant | Pushpa Bogati |
| Partner | Role in project |
|---|---|
| BELVALKAR HOUSING LLP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1. The land and existing building is owned by Jeevan Pradeep Co. op Housing society Ltd and this is a redevelopment project. There are 12 units and 12 members. 2. After selection and due appointment of Belvalkar Housing LLP as re-developer unanimously the Society and all the 12 members have executed and registered the Development agreement and Power Of Attorney ( registered vide no.12573/2)023 on 25/06/2023 and 12574/2023 on 25/06/2023 and at haveli No.21 respectively 3. RERA registration was obtained on 12/03/2025 Bearing No P52100052944 4. Belvalkar Housing LLP after obtaining plan approvals
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Jul 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 7 Jul 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Apr 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 18 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Jul 2031
Documents filed102
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 102 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Form 2A Jeevan Pradeep 25 26.pdf | 4 Aug 2026 |
| Withdrawal Update Form 1File: FORM_01_JEEVAN PRADEEP_JUN 26.pdf | 25 Jul 2026 |
| Withdrawal Update Form 2File: FORM_02_JEEVAN PRADEEP_JUN 26.pdf | 25 Jul 2026 |
| Withdrawal Update Form 3File: FORM 3 JEEVAN PRADEEP JUNE 26.pdf | 25 Jul 2026 |
| Withdrawal Update Form 1File: FORM_01_JEEVAN PRADEEP_MAR 26.pdf | 29 Apr 2026 |
| Withdrawal Update Form 2File: FORM_02_JEEVAN PRADEEP_MAR 26.pdf | 29 Apr 2026 |
| Withdrawal Update Form 3File: FORM 3 MARCH 26- JEEVAN PRADEEP.pdf | 29 Apr 2026 |
| Withdrawal Update Form 1File: FORM_01_JEEVAN PARADEEP_DEC 25.pdf | 31 Jan 2026 |
| Withdrawal Update Form 2File: FORM_02_JEEVAN PRADEEP_DEC25.pdf | 31 Jan 2026 |
| Withdrawal Update Form 3File: FORM 3 DEC 2025 JEEVAN PRADEEP.pdf | 31 Jan 2026 |
| Withdrawal Update Form 1File: FORM_01_JEEVAN PRADEEP_JUNEu002725 (1).pdf | 6 Nov 2025 |
| Withdrawal Update Form 1File: FORM_01_JEEVAN PRADEEP_JUNEu002725 (1).pdf | 6 Nov 2025 |
| Withdrawal Update Form 1File: FORM_01_JEEVAN PRADEEP_SEPTu002725.pdf | 6 Nov 2025 |
| Withdrawal Update Form 1File: FORM_01_JEEVAN PRADEEP_SEPTu002725.pdf | 6 Nov 2025 |
| Withdrawal Update Form 1File: FORM_01_JEEVAN PRADEEP_SEPTu002725.pdf | 6 Nov 2025 |
| Withdrawal Update Form 2File: FORM 02_JEEVAN_JUNu002725.pdf | 6 Nov 2025 |
| Withdrawal Update Form 2File: FORM 02_JEEVAN_JUNu002725.pdf | 6 Nov 2025 |
| Withdrawal Update Form 2File: FORM_02_JEEVAN PRADEEP_SEPTu002725.pdf | 6 Nov 2025 |
| Withdrawal Update Form 2File: FORM_02_JEEVAN PRADEEP_SEPTu002725.pdf | 6 Nov 2025 |
| Withdrawal Update Form 2File: FORM_02_JEEVAN PRADEEP_SEPTu002725.pdf | 6 Nov 2025 |
| Withdrawal Update Form 3File: FORM 3 JEEVAN PRADEEP.pdf | 6 Nov 2025 |
| Withdrawal Update Form 3File: FORM 3 JEEVAN PRADEEP.pdf | 6 Nov 2025 |
| Withdrawal Update Form 3File: Form 3_Jeevan Pradeep_Sep 2025.pdf | 6 Nov 2025 |
| Withdrawal Update Form 3File: Form 3_Jeevan Pradeep_Sep 2025.pdf | 6 Nov 2025 |
| Withdrawal Update Form 3File: Form 3_Jeevan Pradeep_Sep 2025.pdf | 6 Nov 2025 |
| Form 5 (FY 2024-2025)File: Jeevanpradeep.pdf | 5 Sep 2025 |
| Withdrawal Update Form 1File: March 25 form 1 Jeevan pradip.pdf | 24 Jun 2025 |
| Withdrawal Update Form 2File: Form 2 March 25 Jeevan pradip.pdf | 24 Jun 2025 |
| Withdrawal Update Form 3File: Form 3_Jiveen Prdip_March 2025.pdf | 24 Jun 2025 |
| Form 1File: Form 1_Jeevan Pradeep_Dec 2024.pdf | 31 May 2025 |
| Form 2File: Form 2_Jeevan Pradeep_Dec 2024.pdf | 31 May 2025 |
| Form 3File: Form 3_Jeevan Pradeep_Dec 2024.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold _Jeevan Pradeep _Dec 2024.pdf | 31 May 2025 |
| Form 1File: Form 1_Jeevan Pradeep_Dec 2024.pdf | 31 May 2025 |
| Form 2File: Form 2_Jeevan Pradeep_Dec 2024.pdf | 31 May 2025 |
| Form 3File: Form 3_Jeevan Pradeep_Dec 2024.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold _Jeevan Pradeep _Dec 2024.pdf | 31 May 2025 |
| Form 5 (FY 2023-2024)File: Jeevan F5 23-24.pdf | 31 May 2025 |
| Form 1File: FORM 1 JEEVAN PRADIP MARCH 25.pdf | 20 May 2025 |
| Form 2File: FORM_02_JEEVANPRADEEP_MAR'25.pdf | 20 May 2025 |
| Form 3File: Form 3_Jiveen Prdip_March 2025.pdf | 20 May 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCOLSURE OF SOLD -JEEVAN PRADEEP-MARCH 2025.pdf | 20 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Jeevan F5 23-24.pdf | 22 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM_1_JEEVAN_PRADEEP_DEC'24.pdf | 6 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 JEEVAN PRADEEP- MARCH 2024.pdf | 6 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 JEEVAN PRADEEP- JUNE 2024.pdf | 6 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 JEEVAN PRADEEP- SEPT 2024.pdf | 6 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 JEEVAN PRADEEP- DEC 2024.pdf | 6 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 02_ENGG_JEEVANPRADEEP_JUNE'24.pdf | 6 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 02_ENGG_JEEVANPRADEEP_SEPT'24.pdf | 6 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 02_ENGG_JEEVANPRADEEP_DEC'24.pdf | 6 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Mar 24.pdf | 6 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Jun 24.pdf | 6 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Sep 24.pdf | 6 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Dec 24.pdf | 6 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1_Jeevan_Pradeep_Mar’24.pdf | 20 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2_Jeevan_Pardeep_Mar’24.pdf | 20 Apr 2024 |
| Building plan approvalFile: 01 - LAYOUT.pdf | 18 Apr 2024 |
| Building plan approvalFile: 02 - PLAN.pdf | 18 Apr 2024 |
| Building plan approvalFile: 03 - PLAN.pdf | 18 Apr 2024 |
| Building plan approvalFile: 04 - PLAN.pdf | 18 Apr 2024 |
| Building plan approvalFile: 05 - SECTION, ELEVATION.pdf | 18 Apr 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 01 - LAYOUT.pdf | 18 Apr 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 02 - PLAN.pdf | 18 Apr 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 03 - PLAN.pdf | 18 Apr 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 04 - PLAN.pdf | 18 Apr 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 05 - SECTION, ELEVATION.pdf | 18 Apr 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC_REV.pdf | 18 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: JEEVAN P_ARCH20240203_18500073.pdf | 8 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: JEEVAN P_ENGG20240203_18244260.pdf | 8 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 Jeevan Pradeep.pdf | 5 Feb 2024 |
| Details of encumbrances concerned to FinanceFile: No Encumbrances Letter.pdf | 8 Sep 2023 |
| Details of encumbrances concerned to LegalFile: No Encumbrances Letter.pdf | 8 Sep 2023 |
| Details of encumbrances concerned to FinanceFile: Nil Encumbrance legal.pdf | 2 Sep 2023 |
| Details of encumbrances concerned to LegalFile: Nil Encumbrance legal.pdf | 2 Sep 2023 |
| CERSAI detailsFile: CERSAI UNDERTAKING.pdf | 30 Aug 2023 |
| Declaration in FORM BFile: FORM B -JEEVAN PRADEEP SOC.pdf | 25 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CERTIFICATE.pdf | 22 Aug 2023 |
| Proforma of Agreement for saleFile: RERA_agreement_to_Sell_Jeevan_Pradip_Society.pdf | 9 Aug 2023 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf | 9 Aug 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Kalpak Co Op Hsg SocietyP52100045697 | Kothrud, Pune | 23 | Jun 2022 | Completed | May 2024 | May 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 12 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 102 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep JEEVAN PRADEEP CO OPERATIVE HOUSING SOCIETY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MODEL COLONY13,700+ in Pune
Filed coordinates, straight-line distance. 138 registered projects within 2 km.
KUSUM CO. OPERATIVE HOUSING SOCIETY LIMITED
M/S FORTUNE DEVELOPERS
VB FOREST CASTLE BY ASCENT LANDMARKS
ASCENT LANDMARKS LLP
TEJ MAYURBAN
TEJRAJ PROFILE INFRA LLP
The Luxe Towers - Building I and J
Neelsidhi Mohar Raisoni Developers LLP
TEJ MIDTOWN
TEJRAJ GANPATRAO PATIL
Bellagio Courtyards
MICHELNGELO LLP
Builder: BELVALKAR HOUSING LLP
BELVALKAR HOUSING LLP has 13 registrations on MahaRERA, including Snehshilp and Kalpak Co Op Hsg Society. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if JEEVAN PRADEEP CO OPERATIVE HOUSING SOCIETY LTD is delayed beyond 31 Jul 2031?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of JEEVAN PRADEEP CO OPERATIVE HOUSING SOCIETY LTD?
The registered promoter entity is BELVALKAR HOUSING LLP, a partnership as per the filing. Its LLPIN AAD-1077 and GSTIN 27AAOFB7578A1Z8 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in JEEVAN PRADEEP CO OPERATIVE HOUSING SOCIETY LTD?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for JEEVAN PRADEEP CO OPERATIVE HOUSING SOCIETY LTD?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at JEEVAN PRADEEP CO OPERATIVE HOUSING SOCIETY LTD?
The professionals named in the filing: Architect: MANOJ TATOOSKAR; Engineer: VIVEK CHAVAN; Chartered Accountant: Billimoria and Associates; Chartered Accountant: CA Pushpak Bogati; Chartered Accountant: Pushpa Bogati. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in JEEVAN PRADEEP CO OPERATIVE HOUSING SOCIETY LTD?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback