Home / Browse projects / Thane, Maharashtra / JAYRAM MALI COMPLEX
JAYRAM MALI COMPLEX
RG-MH-15760 · RERA P51700023739 · Last updated on MahaRERA portal: 14 Nov 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 19 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
JAYRAM MALI COMPLEX is a Others project by M/S EKVEERA CONSTRUCTIONS in Thane, Maharashtra, registered with MahaRERA as P51700023739 on 3 Jan 2020. Possession is promised by 31 Dec 2026. The completion date has moved by 19 months from the original filing. 0 of the 11 units on this registration are recorded sold or booked, and 18 of 22 construction stages are filed complete.
At a glance
Project
- NameJAYRAM MALI COMPLEX
- TypeOthers
- Location
- TISGOAN ROAD
- GANESH TEMPLE
- Tisgaon
- Kalyan
- Thane
- 421306
- Pincode421306
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700023739
- ReraGenie IDRG-MH-15760
Builder
- NameM/S EKVEERA CONSTRUCTIONS
- Entity typePartnership
- PartnersJAYRAM BABU MALI, SUSHILA KUNDLIK MALI
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on3 Jan 2020
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 May 2025)
- Buildings2 building records
- Documents filed17 files
Current status
Figures as on 14 Nov 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING B | NA | 8 | 8 | 0 | 7 | 7 |
| WING C | NA | 4 | 4 | 2 | 2 | 4 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 14 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.
WING B82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING C82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 14 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed40
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| WING B | 6 | 14 | 20 |
| WING C | 6 | 14 | 20 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| KUNDALIK JAYRAM MALI | KATEMANEVALI | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| WING B | NA | Rs 3.40 cr | Rs 3.23 cr |
| WING C | NA | Rs 3.40 cr | Rs 3.23 cr |
| - | NA | Rs 1.20 cr | Rs 78.00 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RACHANA |
| Engineer | rajesh thakare |
| Chartered Accountant | ram kundnani |
| Chartered Accountant | Suresh Radhkrishnani |
| Partner | Role in project |
|---|---|
| M/S EKVEERA CONSTRUCTIONS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promotercertain unforeseen circumstances beyond the ours control Post-Pandemic or Market Disruptions a. Post Pandemic Consequenses e.g., lesser Buying power due to instability in daily earnings caused unavoidable delays b. Financial crises due to Post Covid Slow Down in money market leads to poor booking in project c. Heavy competition in Market to sell at low margine d. Increase in rates of Raw Materials every now and then which leads to increase in construction cost
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 1 Nov 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 1 Nov 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 1 Nov 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 10 Jul 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed17
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: architect certificate sep 25.pdf | 14 Nov 2025 |
| Withdrawal Update Form 2File: ENGINEER CERIFICATE.pdf | 14 Nov 2025 |
| Withdrawal Update Form 3File: CA CERTIFICATE.pdf | 14 Nov 2025 |
| Commencement certificateFile: Commencement Certificate.pdf | 10 Jul 2025 |
| OtherFile: open parking.pdf | 9 Dec 2019 |
| Building plan approvalFile: PERMISSION FROM KDMC.pdf | 1 Nov 2019 |
| Layout approvalFile: plan approval.pdf | 1 Nov 2019 |
| PAN CardFile: PANCARD.pdf | 1 Nov 2019 |
| Copy of the legal title reportFile: title report.pdf | 1 Nov 2019 |
| Details of encumbrancesFile: TITLE CLEAR CERTIFICATE.pdf | 1 Nov 2019 |
| Copy of Layout Approval (in case of layout)File: plan approval.pdf | 1 Nov 2019 |
| Building Plan Approval / NA Order for plotted developmentFile: PERMISSION FROM KDMC.pdf | 1 Nov 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: kdmc approval.pdf | 1 Nov 2019 |
| Declaration in FORM BFile: declaration in form B.pdf | 1 Nov 2019 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERIFICATE.pdf | 1 Nov 2019 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf | 1 Nov 2019 |
| Proforma of Allotment letterFile: AGREEMENT FOR SALE FINAL.pdf | 1 Nov 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 17 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep JAYRAM MALI COMPLEX on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near GANESH TEMPLE7,600+ in Thane
Filed coordinates, straight-line distance. 282 registered projects within 2 km.
Kohinoor Eden
KGI REALTY PRIVATE LIMITED
Olympia City Phase 1
Balaji Rattan Lifespaces
Krishna Trident
Sonawane Infrastructure Private Limited
Rai s Heaven
RAI RESIDENCY Private Limited
Metro Grande Tower C and D
West Pioneer Properties India Pvt Ltd
SEASON SAHARA BUILDING NO 4 AND 5
SAMARTH SAI BUILDERS & DEVELOPERS
See every Thane project, with the district possession charts
Builder: M/S EKVEERA CONSTRUCTIONS
M/S EKVEERA CONSTRUCTIONS has 1 registration on MahaRERA, including JAYRAM MALI COMPLEX. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if JAYRAM MALI COMPLEX is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of JAYRAM MALI COMPLEX?
The registered promoter entity is M/S EKVEERA CONSTRUCTIONS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in JAYRAM MALI COMPLEX?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for JAYRAM MALI COMPLEX?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at JAYRAM MALI COMPLEX?
The professionals named in the filing: Architect: RACHANA; Engineer: rajesh thakare; Chartered Accountant: ram kundnani; Chartered Accountant: Suresh Radhkrishnani. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in JAYRAM MALI COMPLEX?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.