Home / Browse projects / Thane, Maharashtra / JASMINE RESIDENCY

Registration lapsed Litigation declared Mixed project

JASMINE RESIDENCY

By A.A.CORP.

RG-MH-28308 · RERA P51700025771 · Last updated on MahaRERA portal: 14 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 11 months past the filed date
  • Litigation declared, 2 cases

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Nov 2025Possession promised11 months past this date
4 of 11Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 90%
0 of 1Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 79 documents Report an error

JASMINE RESIDENCY is a Mixed project by A.A.CORP. in Thane, Maharashtra, registered with MahaRERA as P51700025771 on 14 Jul 2020. Possession was promised by 24 Nov 2025 and is now 11 months past that date. 1 of the 1 unit on this registration is recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameJASMINE RESIDENCY
  • TypeMixed
  • Location
    • ISMAIL ESTATE
    • KASHIGAON
    • NEEL KAMAL NAKA
    • MIRA ROAD
    • MIRA BHAYANDER THANE - 401107
    • NEAR WESTERN EXPRESS HIGHWAY
    • KASHI GAON
    • Mira-Bhayandar (M Corp.)
    • ...
  • Pincode401107
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700025771
  • ReraGenie IDRG-MH-28308

Builder

  • NameA.A.CORP.
  • Entity typePartnership
  • PartnersANAND RAMPRASAD AGRAWAL, JORDAN STEPHEN PEREIRA
  • Declared earlier projects2 →

Key dates

11 months past promisethis monthRegisteredJul 2020PromisedNov 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on14 Jul 2020
  • Promised completion24 Nov 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed79 files

Current status

100%1 of 1 units booked

Figures as on 14 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
JASMINE RESIDENCYNA2113000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 14 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 90%.

JASMINE RESIDENCY63%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.25%
NA Plot Without StructureNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 14 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed40

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots40
Closed/Covered40

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,554 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityMira Bhayandar Municipal Corporation
Permissible FSI6655.83
Proposed, not sanctioned3,640 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGR FL,SHEETAL SAROVAR,SHEETAL NAGAR,NR MIRA ROAD TELEPHONE EXG,MTNL ROAD,WING B,MIRA ROAD,MIRA BHAYA

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAVINASH MHATRE & ASSOCIATES
ArchitectDIMENSIONS INFRA PVT LTD
ArchitectSQUARE ARCHITECTS
EngineerPRO TECH CONSULTANTS
Chartered AccountantA D B & ASSOCIATES CHARTERED ACCOUNTANTS
Chartered AccountantRAVI B GUPTA & CO CHARTERED ACCOUNTANTS
Chartered AccountantA.S.KANCHWALA & Co.
PartnerRole in project
A.A.CORP.-

Litigation declared2

CaseCourtStatus
1450/2022HIGH COURT OF JUDICATURE AT BOMBAYIN PROGRESS
593/2024HIGH COURT OF JUDICATURE AT BOMBAYIN PROGRESS

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Jun 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 May 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 May 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 May 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed79

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 1_ SEP 25_ JASMINE RESIDENCY.pdf14 May 2026
Form 2File: FORM 2_ SEP 25_ JASMINE RESIDENCY.pdf14 May 2026
Form 3File: FORM 3_ SEP 25_ JASMINE RESIDENCY.pdf14 May 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ SEP 25_ JASMINE RESIDENCY.pdf14 May 2026
Form 1File: FORM 1_JUNE 25_JASMINE RESIDENCY.pdf7 Aug 2025
Form 2File: FORM 2_JUNE 25_JASMINE RESIDENCY.pdf7 Aug 2025
Form 3File: FORM 3_JUNE 25_JASMINE RESIDENCY.pdf7 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_JUNE 25_JASMINE RESIDENCY.pdf7 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_ MARCH 25.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_ MARCH 25.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_ MARCH 25.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_ MARCH 25.pdf19 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM -2A Jasmine Residency.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1(Architect ) -31-12-2024.pdf28 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form -3 (CA) -31-12-2024.pdf28 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM -2 (Engineers)-31-12-2024.pdf28 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold -31-12-2024 Jasmine Residency001.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 FORM 1_ SEP 24.pdf20 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 FORM 3_ SEP 24_compressed.pdf20 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 FORM 2_ SEP 24.pdf20 Oct 2024
Disclosure of sold/ booked inventoryFile: 4 SOLD UNSOLD_ SEP 24.pdf20 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM -2A Jasmine Residency.pdf20 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 FORM 1_ JUNE 24.pdf29 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 FORM2_ JUNE 24 (1).pdf29 Jul 2024
Disclosure of sold/ booked inventoryFile: 4 SOLD UNSOLD_ JUNE 24.pdf29 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 FORM 3_ JUNE 24.pdf29 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf22 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM -2 Jasmine Residency.pdf22 Apr 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf22 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf22 Apr 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD-JASMINE RESIDENCY_DEC 23.pdf20 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-JASMINE RESIDENCY_DEC 23.pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-JASMINE RESIDENCY_DEC 23.pdf19 Jan 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD-JASMINE RESIDENCY_DEC 23.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-JASMINE RESIDENCY_DEC 23_compressed.pdf19 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 (20-21) AA Corp.pdf22 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 (21-22) AA Corp.pdf18 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 (22-23) AA Corp.pdf18 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM -2A (Quality Assurance Certificate).pdf9 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-JASMINE RESIDENCY_JUN 23.pdf2 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-JASMINE RESIDENCY_SEP 23.pdf2 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-JASMINE RESIDENCY_SEP 23.pdf2 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A-JASMINE RESIDENCY_21-22.pdf2 Nov 2023
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD-JASMINE RESIDENCY_JUN 23.pdf2 Nov 2023
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD-JASMINE RESIDENCY_SEP 23.pdf2 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-JASMINE RESIDENCY_JUN 23_compressed.pdf2 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-JASMINE RESIDENCY_SEP 23_compressed.pdf2 Nov 2023
Declaration about Commencement CertificateFile: CC DECLARATION .pdf21 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A.pdf21 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A.pdf21 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A.pdf21 May 2022
Details of encumbrancesFile: Search Report.pdf19 Jun 2020
Status of ConveyanceFile: DEED OF CONVEYANCE (Aslam) (Index II).pdf19 Jun 2020
Status of ConveyanceFile: DEVELOPMENT AGREEMENT KASHI NOOR (Index II).pdf19 Jun 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate.pdf18 Jun 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate.pdf17 Jun 2020
Proforma of Allotment letterFile: AA CORP RERA DRAFT - Agreement for Sale (Final).pdf17 Jun 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate (Signed Copy).pdf15 Jun 2020
Copy of the legal title reportFile: Certificate of Title.pdf6 Jun 2020
Copy of the legal title reportFile: Search Report.pdf6 Jun 2020
Copy of the legal title reportFile: No Claim Newspaper.pdf6 Jun 2020
Declaration in FORM BFile: FORM B-ARA.pdf6 Jun 2020
Declaration in FORM BFile: FORM B-JSP.pdf6 Jun 2020
Layout approvalFile: LAYOUT PLAN 2.pdf16 May 2020
Layout approvalFile: LAYOUT PLAN 1.pdf16 May 2020
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN 2.pdf16 May 2020
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN 1.pdf16 May 2020
Commencement Certificates / NA Order for plotted developmentFile: Conversation Tax.pdf16 May 2020
Proforma of Allotment letterFile: Allotment Letter.pdf16 May 2020
Building plan approval or NA orderFile: BUILDING PLAN 1.pdf11 May 2020
Building plan approval or NA orderFile: BUILDING PLAN 2.pdf11 May 2020
Building plan approval or NA orderFile: BUILDING PLAN 3.pdf11 May 2020
Building plan approval or NA orderFile: BUILDING PLAN 4.pdf11 May 2020
PAN CardFile: PAN CARD.pdf11 May 2020
Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN 1.pdf11 May 2020
Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN 2.pdf11 May 2020
Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN 3.pdf11 May 2020
Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN 4.pdf11 May 2020
Commencement Certificates / NA Order for plotted developmentFile: CC COPY.pdf11 May 2020

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
SALASAR WOODS - SALASAR ESTATE DEVELOPERS LLPNEW SURVEY NO 180 HISSA NO 4 NEAR RAMDEV PARK NEAR RAUNAK HOTEL VILLAGE NAVGHAR KANAKIA ROAD MIRA ROAD EAST TALUKA & DISTRICT THANE 401107144CompletedDec 2020Late, Dec 2020
RADHA RAMAN - SALASAR ASSOCIATESOPPOSITE D'MART 150 FEET ROAD NEAR TO MAXUS MALL BHAYANDER WEST THANE - 40110178CompletedFeb 2015Late, May 2015

How this compares with Thane

100%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep JASMINE RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR WESTERN EXPRESS HIGHWAY, KASHI GAON,7,600+ in Thane

2 kmJASMINE RESIDENCYCompleted 44Lapsed / revoked 22Other 62Dot size: filed unitsN

Filed coordinates, straight-line distance. 128 registered projects within 2 km.

Builder: A.A.CORP.

A.A.CORP. has 1 registration on MahaRERA, including JASMINE RESIDENCY. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that JASMINE RESIDENCY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if JASMINE RESIDENCY is delayed beyond 24 Nov 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of JASMINE RESIDENCY?

The registered promoter entity is A.A.CORP., a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in JASMINE RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for JASMINE RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at JASMINE RESIDENCY?

The professionals named in the filing: Architect: AVINASH MHATRE & ASSOCIATES; Architect: DIMENSIONS INFRA PVT LTD; Architect: SQUARE ARCHITECTS; Engineer: PRO TECH CONSULTANTS; Chartered Accountant: A D B & ASSOCIATES CHARTERED ACCOUNTANTS; Chartered Accountant: RAVI B GUPTA & CO CHARTERED ACCOUNTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in JASMINE RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About JASMINE RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save JASMINE RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.