Janki Rainbow

By MAHESH BHAGWAT

RG-MH-73505 · RERA P52100017014 · Last updated on MahaRERA portal: 22 May 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 46 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2022Possession promised46 months past this date
33 of 33Construction stages doneacross 3 buildings; every applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 42 documents Report an error

Janki Rainbow is a Others project by MAHESH BHAGWAT in Pune, Maharashtra, registered with MahaRERA as P52100017014 on 2 Jul 2018. Possession was promised by 30 Dec 2022 and is now 46 months past that date.

At a glance

Project

  • NameJanki Rainbow
  • TypeOthers
  • Location
    • Baner Road
    • Baner Gaon
    • Baner
    • Haveli
    • Pune
    • 411045
  • Pincode411045
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100017014
  • ReraGenie IDRG-MH-73505

Builder

  • NameMAHESH BHAGWAT
  • Entity typeIndividual
  • Named personMAHESH BHAGWAT
  • Declared earlier projects1 →

Key dates

46 months past promisethis monthRegisteredJul 2018PromisedDec 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on2 Jul 2018
  • Promised completion30 Dec 2022
  • Revised completionNone
  • Buildings3 building records
  • Documents filed42 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A - 1NA40000
A - 2NA10000
A - 3NA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 22 May 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

33 of 33 construction stages are filed complete across 3 buildings.

A - 1100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A - 2100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A - 3100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities20

As on 22 May 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%
Water PumpsYes100%
Underground Water TanksYes100%
Compound WallYes100%
Entrance GateYes100%
Paving of areas appurtenant to BuildingYes100%

Parking filed22

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots22
Open Space22
BuildingOpen SpaceTotal
A - 11414
A - 222
A - 366

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,500 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI5910.5
Proposed, not sanctioned4,586 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchFERGUSSON COLLEGE ROAD PUNE MAHARASHTRA

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVKa architecture
PartnerRole in project
MAHESH BHAGWAT-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Jun 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Jun 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Jun 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 1 Apr 2023

Documents filed42

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Maharera Form - 2_updated engineer certificate 31-03-2020.pdf22 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Maharera Form - 2_updated engineer certificate 31-03-2020.pdf22 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Maharera Form - 2_updated engineer certificate 31-03-2021.pdf22 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Maharera Form - 2_updated engineer certificate 31-03-2022.pdf22 May 2023
Certificates of CA (Form 3)File: MAHARERA form 3 CA certificate 31-03-2020.PDF22 May 2023
Certificates of CA (Form 3)File: MAHARERA form 3 CA certificate 31-03-2021.PDF22 May 2023
Certificates of CA (Form 3)File: MAHARERA form 3 CA certificate 31-03-2022.PDF22 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CA certificate form 5 MAHARERA 31-03-2019.PDF22 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: CA certificate form 5 MAHARERA 31-03-2020.PDF22 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA certificate form 5 MAHARERA 31-03-2021.PDF22 May 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate Janki Rainbow 2019.pdf12 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate 2021 Janki Rainbow.PDF12 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_janki construction.pdf12 Apr 2023
Proforma of Agreement for saleFile: Agreement - Janki Rainbow - A3 - Blank Draft.pdf12 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Janki Rainbow Baner S No - 165 Full Occupancy Certificate Full Completion Certificate.pdf1 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate - Baner.PDF2 Nov 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1826_compressed (1).pdf28 Jan 2020
Layout approvalFile: sanctioned drawing final.pdf15 Jun 2018
Copy of Layout Approval (in case of layout)File: sanctioned drawing final.pdf15 Jun 2018
Declaration in FORM BFile: Declaration in form B.pdf15 Jun 2018
Certificates of CA (Form 3)File: CA certificate pdf.pdf15 Jun 2018
Proforma of Allotment letterFile: Agreement to sell Janki Rainbow.pdf14 Jun 2018
Building plan approvalFile: Sanction Plans .pdf12 Jun 2018
Building plan approvalFile: Sanction Plans .pdf12 Jun 2018
Building Plan Approval (IOD)File: Sanction Plans .pdf12 Jun 2018
Building Plan Approval (IOD)File: Sanction Plans .pdf12 Jun 2018
Commencement Certificates / NA Order for plotted developmentFile: baner commensement.pdf6 Jun 2018
PAN CardFile: pan card.pdf2 Jun 2018
Copy of the legal title reportFile: PIC-min.pdf2 Jun 2018
Copy of the legal title reportFile: PIC0001-min.pdf2 Jun 2018
Copy of the legal title reportFile: PIC0002-min.pdf2 Jun 2018
Copy of the legal title reportFile: PIC0003-min.pdf2 Jun 2018
Copy of the legal title reportFile: PIC0004-min.pdf2 Jun 2018
Copy of the legal title reportFile: PIC0005-min.pdf2 Jun 2018
Copy of the legal title reportFile: PIC0006-min.pdf2 Jun 2018
Copy of the legal title reportFile: PIC0007-min.pdf2 Jun 2018
Copy of the legal title reportFile: PIC0008-min.pdf2 Jun 2018
Copy of the legal title reportFile: PIC0010-min.pdf2 Jun 2018
Copy of the legal title reportFile: PIC0012-min.pdf2 Jun 2018
Copy of the legal title reportFile: PIC0013-min.pdf2 Jun 2018
Copy of the legal title reportFile: PIC0013-min.pdf2 Jun 2018
Details of encumbrancesFile: ilovepdf_jpg_to_pdf (1).pdf2 Jun 2018

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
GOLDEN NEST A WINGGOLDEN NEST A1 BUILDING HANDEWADI ROAD NEAR MAYURI WAZAN KATA HANDEWADI PUNE 41102847CompletedMar 2018Mar 2018

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Janki Rainbow on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Baner Gaon13,700+ in Pune

2 kmJanki RainbowCompleted 8Lapsed / revoked 13Other 28Dot size: filed unitsN

Filed coordinates, straight-line distance. 49 registered projects within 2 km.

Builder: MAHESH BHAGWAT

MAHESH BHAGWAT has 1 registration on MahaRERA, including Janki Rainbow. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Janki Rainbow shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Janki Rainbow is delayed beyond 30 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Janki Rainbow?

The registered promoter entity is MAHESH BHAGWAT, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Janki Rainbow?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Janki Rainbow?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Janki Rainbow?

The professionals named in the filing: Architect: VKa architecture. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Janki Rainbow?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Janki Rainbow. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Janki Rainbow to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.