Home / Browse projects / Nagpur, Maharashtra / JAINAM HEIGHTS

Registration lapsed No litigation declared Residential / Group Housing project

JAINAM HEIGHTS

By LATESH RAMNIKLAL VORA AND OTHERS

RG-MH-03562 · RERA P50500028257 · Last updated on MahaRERA portal: 7 Nov 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 28 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Jun 2024Possession promised28 months past this date
8 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 98%
0Complaints at MahaRERAon this registration
Jump to the 77 documents Report an error

JAINAM HEIGHTS is a Residential / Group Housing project by LATESH RAMNIKLAL VORA AND OTHERS in Nagpur, Maharashtra, registered with MahaRERA as P50500028257 on 18 Feb 2021. Possession was promised by 30 Jun 2024 and is now 28 months past that date.

At a glance

Project

  • NameJAINAM HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • BHANDARA ROAD
    • WARDHAMAN NAGAR
    • Nagpur (M Corp.)
    • Nagpur (Urban)
    • Nagpur
    • 440008
  • Pincode440008
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500028257
  • ReraGenie IDRG-MH-03562

Builder

  • NameLATESH RAMNIKLAL VORA AND OTHERS
  • Entity typeOthers
  • Named personsVANITA ANANTRAI VORA, PRAFUL ANANTRAI VORA, TARUN ANANTRAI VORA, LALIT ANANTRAI VORA, JIGNA LALIT VORA, LATESH RAMNIKLAL VORA, KAVITA LATESH VORA, PRERIT KIRTIKUMAR VORA, JITENDRA CHANDRAKANT SAVADIA, PARAS VIPINCHANDRA MEHTA, ASHOK NAVALCHAND BHAYANI, PRAVINA ASHOK BHAYANI and 2 more

Key dates

28 months past promisethis monthRegisteredFeb 2021PromisedJun 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on18 Feb 2021
  • Promised completion30 Jun 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed77 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
JAINAM HEIGHTSNA150000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 7 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 98%.

JAINAM HEIGHTS: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 7 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed252

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots252
Closed/Covered252

Land and ownership14

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,884 sq m
Land owned byThe promoter, with other names on the file
Named landowners14
LandownerVillageDistrict
PRAFUL ANANTRAI VORANagpur (M Corp.)Nagpur
JIGNA LALIT VORANagpur (M Corp.)Nagpur
LATESH RAMNIKLAL VORANagpur (M Corp.)Nagpur
KAVITA LATESH VORANagpur (M Corp.)Nagpur
PRERIT KIRTIKUMAR VORANagpur (M Corp.)Nagpur
JITENDRA CHANDRAKANT SAVADIANagpur (M Corp.)Nagpur
PARAS VIPINCHANDRA MEHTANagpur (M Corp.)Nagpur
ASHOK NAVALCHAND BHAYANINagpur (M Corp.)Nagpur
PRAVINA ASHOK BHAYANINagpur (M Corp.)Nagpur
TEJAS ASHOK BHAYANINagpur (M Corp.)Nagpur
KHUSHBU TEJAS BHAYANINagpur (M Corp.)Nagpur
VANITA ANATRAI VORANagpur (M Corp.)Nagpur
LALIT ANANTRAI VORANagpur (M Corp.)Nagpur
TARUN ANANTRAI VORANagpur (M Corp.)Nagpur

Approvals and building plan

Permissible FSI10368.29
Proposed, not sanctioned10,368 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCHAPRU SQUARE NAGPUR

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDESIGN CELL
EngineerASPECT DESIGN
Chartered AccountantCA UTSAV JASAPARA
PartnerRole in project
LATESH RAMNIKLAL VORA AND OTHERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Feb 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Jan 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Jan 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Jan 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Nov 2024

Documents filed77

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: LRV RERA FORM B (CORRECTED).PDF7 Nov 2024
Declaration in FORM BFile: LRV RERA FORM B (CORRECTED).PDF7 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LRV RERA FORM B (CORRECTED).PDF7 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LRV FORM NO 1ARCH CERT Q1 24-25.PDF7 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: LRVFORM NO 2 Q1 24-25.PDF7 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: JAINAM HEIGHTS OC PDF.pdf7 Nov 2024
Disclosure of sold/ booked inventoryFile: LRV SOLD UNSOLD DETAILS.PDF7 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: LRV FORM NO 2A 24-25.PDF7 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: LRV ENGG CERTIFICATE IN FORM NO 2.PDF10 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: LRV ENGINEER'S CERTIFICATE FOR QUALITY ASSURANCE Q1 24-25.PDF10 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE IN FORM NO 3 ALONG CERTIFIED DETAILS OF INVENTORY SOLD AND UNSOLD.pdf10 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch - Form 1.pdf4 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LRV-1-3.pdf4 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Form 2.pdf4 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate.pdf4 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: LRV-7-9.pdf4 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final ceritificate - Form 3 - Q3.pdf4 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Adobe Scan 03-Jun-2024 (2).pdf4 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARC_FORM1_310323.PDF11 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARC_FORM1_Q1_2324.pdf11 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH_FORM1_Q2_2324.pdf11 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG_FOR2_310323.PDF11 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2_Q1_2324.PDF11 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2_Q2_2324.pdf11 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ENGG_2A_310323.PDF11 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3_Q1_2324.pdf11 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3_Q2_2324.pdf11 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form No 5.pdf7 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FINAL Q4 FORM 3 JAINAM.pdf11 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q1 MAIN.pdf10 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 final.pdf10 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q1 MAIN.pdf10 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q2 MAIN.pdf10 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: LRV FORM 5 21-22.PDF4 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: LRV (Disclosure of Interest in Other Projects).PDF3 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form -5 20-21_compressed.pdf3 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q1 ARCH.pdf21 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q2 - 1.pdf21 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q3 - 1.pdf21 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q1 2.pdf21 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q2 - 2.pdf21 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q3 - 2.pdf21 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Q1 2A.pdf21 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH_CERT_3112.PDF9 Jun 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LRV ARCH 3103.PDF9 Jun 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG 3112.PDF9 Jun 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG 3103.PDF9 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM - 3 CA Certificate Updation PU.pdf9 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RECEIVABLE CALC 3112.pdf9 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Unsold Inventory Valuation3112.pdf9 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: rera cert jainam_compressed.pdf9 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: ENGG QUALITY 3009.PDF9 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGG QUALITY 3009.PDF9 Nov 2021
Disclosure of sold/ booked inventoryFile: disclosure of inventory.pdf9 Nov 2021
OtherFile: LRV1.PDF9 Nov 2021
Declaration about Commencement CertificateFile: BUILDING PERMIT AND COMMENCEMENT CERT.pdf7 Sep 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH_3006.pdf7 Sep 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG_CERT_3006.pdf7 Sep 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_CERT.pdf7 Sep 2021
Copy of the legal title reportFile: TITLE_REPORT_compressed.pdf11 Feb 2021
Details of encumbrancesFile: TITLE_REPORT_compressed.pdf11 Feb 2021
Declaration in FORM BFile: TEJAS.PDF11 Feb 2021
Declaration in FORM BFile: LALITA.PDF11 Feb 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERT.PDF11 Feb 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG CERT.PDF11 Feb 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERT_compressed.pdf11 Feb 2021
Building plan approvalFile: BUILDING PERMIT AND COMMENCEMENT CERT.pdf18 Jan 2021
Building plan approvalFile: MAP 1.pdf18 Jan 2021
Layout approvalFile: MAP 1.pdf18 Jan 2021
PAN CardFile: PAN_AOP.pdf18 Jan 2021
Copy of Layout Approval (in case of layout)File: MAP 1.pdf18 Jan 2021
Building Plan Approval / NA Order for plotted developmentFile: BUILDING PERMIT AND COMMENCEMENT CERT.pdf18 Jan 2021
Building Plan Approval / NA Order for plotted developmentFile: MAP 1.pdf18 Jan 2021
Commencement Certificates / NA Order for plotted developmentFile: BUILDING PERMIT AND COMMENCEMENT CERT.pdf18 Jan 2021
Proforma of Allotment letterFile: DRAFT Agr TO SALE.pdf18 Jan 2021
Proforma of Allotment letterFile: Allotment_letter_-_Jainam_height.pdf18 Jan 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: JAIN HEIGHTS DOD COMPRESSED.pdf18 Jan 2021

How this compares with Nagpur

13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is among them

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep JAINAM HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near WARDHAMAN NAGAR2,800+ in Nagpur

2 kmJAINAM HEIGHTSCompleted 23Lapsed / revoked 8Other 42Dot size: filed unitsN

Filed coordinates, straight-line distance. 73 registered projects within 2 km.

Builder: LATESH RAMNIKLAL VORA AND OTHERS

LATESH RAMNIKLAL VORA AND OTHERS has 1 registration on MahaRERA, including JAINAM HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What does it mean that JAINAM HEIGHTS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if JAINAM HEIGHTS is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of JAINAM HEIGHTS?

The registered promoter entity is LATESH RAMNIKLAL VORA AND OTHERS, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in JAINAM HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for JAINAM HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at JAINAM HEIGHTS?

The professionals named in the filing: Architect: DESIGN CELL; Engineer: ASPECT DESIGN; Chartered Accountant: CA UTSAV JASAPARA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in JAINAM HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About JAINAM HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save JAINAM HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.