Home / Browse projects / Pune, Maharashtra / Jaigad

Registration lapsed No litigation declared Residential / Group Housing project

Jaigad

By Deepak Chintamani Dhavale

RG-MH-27440 · RERA P52100034674 · Last updated on MahaRERA portal: 11 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 19 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2025Possession promised19 months past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 60 documents Report an error

Jaigad is a Residential / Group Housing project by Deepak Chintamani Dhavale in Pune, Maharashtra, registered with MahaRERA as P52100034674 on 20 Apr 2022. Possession was promised by 31 Mar 2025 and is now 19 months past that date.

At a glance

Project

  • NameJaigad
  • TypeResidential / Group Housing
  • Location
    • Lane No 14
    • Prabhat Road
    • Erandawane
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411004
  • Pincode411004
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100034674
  • ReraGenie IDRG-MH-27440

Builder

  • NameDeepak Chintamani Dhavale
  • Entity typeIndividual
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

19 months past promisethis monthRegisteredApr 2022PromisedMar 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on20 Apr 2022
  • Promised completion31 Mar 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed60 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
JaigadNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Jaigad: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 11 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed21

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots21
Closed/Covered21

Land and ownership9

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area520 sq m
Land owned byThe promoter, with other names on the file
Named landowners9
LandownerVillageDistrict
Geeta JoshiPune (M Corp.)Pune
Jaideep JoshiPune (M Corp.)Pune
Sandeep JoshiPune (M Corp.)Pune
Amarendra SathePune (M Corp.)Pune
Amit SathePune (M Corp.)Pune
Anagha ThombrePune (M Corp.)Pune
Shilpa SomanPune (M Corp.)Pune
Sujata TambePune (M Corp.)Pune
Suchitra MujumdarPune (M Corp.)Pune

Approvals and building plan

Permissible FSI1794.67
Proposed, not sanctioned1,501 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch8/3, Erandawne, Karve Road, Pune 411004

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMangesh Bhandekar
EngineerYogesh Kolekar
Chartered AccountantSachin Amdekar
PartnerRole in project
Deepak Chintamani Dhavale-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Apr 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Mar 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Apr 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 11 Apr 2025

Documents filed60

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Jaygad full Complition-1.pdf11 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: jaigad ca cert 30june24.pdf16 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: jaigad ca cert 30sept24.pdf16 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: jaigad eng cert 30june24.pdf16 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Jaigad eng cert 30sept24.pdf16 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Jaigad annual ca cert 23 24.pdf16 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Jaigad eng cert 23 24.pdf16 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch cert mar 24.pdf14 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arc certificate june 24.pdf14 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch cert sept 24.pdf14 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23).pdf14 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ikon Engi cert 31march 2024.pdf14 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Jaygad OC 01.pdf14 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ikon archi certi 31mar24.pdf7 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Ikon Engi cert 31march 2024.pdf7 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ikon CA certi 31March 2024.pdf7 May 2024
Building plan approvalFile: Plan 01.pdf28 Apr 2024
Building plan approvalFile: Plan 02.pdf28 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: Plan 01.pdf28 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: Plan 02.pdf28 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: doc05115520230324162447.pdf28 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Jaigad Rera.pdf17 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Jaigad - Engineer's Certificate - 2023.pdf17 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Jaigad - CA Cetificate - 2024.pdf17 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Ikon realty annual engi certificate Dec 2023.pdf15 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Ikon Realty Annual CA cert Dec 2023.pdf15 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect cert sept 23.pdf2 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Realty Engi Certificate.pdf28 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Realty CA certi.pdf28 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect cert june 23.pdf27 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ikon Realty Engineers Certificate 30june23.pdf19 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Cert June 23.pdf14 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 30sept22.pdf11 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 31dec22.pdf11 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 20mar23.pdf11 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate 30sept22.pdf11 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate 31dec22.pdf11 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate 20mar23.pdf11 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate 30sept22.pdf11 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate 31dec22.pdf11 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate 20mar23.pdf11 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: rera certificate- Architect.pdf27 Aug 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: I R Certificate.pdf27 Aug 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ikon Realty CA Certificate.pdf27 Aug 2022
Copy of the legal title reportFile: Legal Title Search Report - Jaigad.pdf12 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf6 Apr 2022
Proforma of Allotment letterFile: Allotment Letter.pdf6 Apr 2022
Proforma of Allotment letterFile: Agreement to Sale.pdf6 Apr 2022
Declaration in FORM BFile: Affidavit Cum Declaration Form B.pdf4 Apr 2022
Layout approvalFile: Plan 01.pdf22 Mar 2022
Building plan approvalFile: Plan 01.pdf22 Mar 2022
Building plan approvalFile: Plan 02.pdf22 Mar 2022
PAN CardFile: Pan Card.pdf22 Mar 2022
Copy of Layout Approval (in case of layout)File: Plan 01.pdf22 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: Plan 01.pdf22 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: Plan 02.pdf22 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement.pdf22 Mar 2022
Declaration about Commencement CertificateFile: declaration about commencement.pdf22 Mar 2022
CERSAI detailsFile: CERSAI Report - Jaigad.pdf22 Mar 2022
Details of encumbrancesFile: Non Encumbrance Certificate.pdf16 Mar 2022

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Jaigad on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Erandawane13,700+ in Pune

2 kmJaigadCompleted 84Lapsed / revoked 32Other 158Dot size: filed unitsN

Filed coordinates, straight-line distance. 274 registered projects within 2 km.

Builder: Deepak Chintamani Dhavale

Deepak Chintamani Dhavale has 2 registrations on MahaRERA, including Jaigad and Ikon Hiplex. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Jaigad shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Jaigad is delayed beyond 31 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Jaigad?

The registered promoter entity is Deepak Chintamani Dhavale, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Jaigad?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Jaigad?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Jaigad?

The professionals named in the filing: Architect: Mangesh Bhandekar; Engineer: Yogesh Kolekar; Chartered Accountant: Sachin Amdekar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Jaigad?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Jaigad. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Jaigad to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.