ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / JAI GANESH CO-OPERATIVE HOUSING SOCIETY LTD

Registered No litigation declared Residential / Group Housing project

JAI GANESH CO-OPERATIVE HOUSING SOCIETY LTD

By DEEPALI LANDSCAPE

RG-MH-06339 · RERA P51700052606 · Last updated on MahaRERA portal: 20 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
20 of 44Construction stages doneacross 4 buildings; furthest along: Internal walls, 85%
40 of 48Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 63 documents Report an error

JAI GANESH CO-OPERATIVE HOUSING SOCIETY LTD is a Residential / Group Housing project by DEEPALI LANDSCAPE in Thane, Maharashtra, registered with MahaRERA as P51700052606 on 11 Sep 2023. Possession is promised by 31 Dec 2026. 8 of the 48 units on this registration are recorded sold or booked, and 20 of 44 construction stages are filed complete.

At a glance

Project

  • NameJAI GANESH CO-OPERATIVE HOUSING SOCIETY LTD
  • TypeResidential / Group Housing
  • Location
    • Survey No 42(P) Plot No H-1 (9 to 16 and 17 to 22)
    • Kulgaon
    • Badlapur (East)
    • Badlapur (M Cl)
    • Ambarnath
    • Thane
    • 421503
  • Pincode421503
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700052606
  • ReraGenie IDRG-MH-06339

Builder

  • NameDEEPALI LANDSCAPE
  • Entity typePartnership
  • PartnersSUREKHA HARISH CHOUDHARY, RAMASWAMI MALLAYA DARWIN, VIRAJ RAVINDRA PATIL, SIDDHESH RAVINDRA PATIL

Key dates

this monthRegisteredSep 2023PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Sep 2023
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings4 building records
  • Documents filed63 files

Current status

17%8 of 48 units booked
74.0%Work done, per cost certificate

Figures as on 20 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA6612012
WING BNA6612012
WING CNA7612012
WING DNA6612012

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 20 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Internal walls, at 85%.

WING A48%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING B48%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING C64%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING D64%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 20 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed86

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots86
Open Space86
BuildingOpen SpaceTotal
WING A2424
WING B2424
WING C1919
WING D1919

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,207 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
JAI GANESH CO-OPERATIVE HOUSING SOCIETY LTDBadlapur (M Cl)Thane

Approvals and building plan

Sanctioning authorityKulgaon Badlapur Nagar Parishad
Permissible FSI2691.47
Proposed, not sanctioned2,691 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKESHAV KOSH STATION ROAD OPP HOTEL ATITHI, KULGAON E, BADLAPUR, 421503
Estimated costRs 9.75 cr
Cost incurredRs 7.21 cr
Work done73.96%
BuildingWingEstimatedIncurred
WING ANARs 2.48 crRs 1.98 cr
WING BNARs 2.48 crRs 1.98 cr
WING CNARs 1.91 crRs 1.63 cr
WING DNARs 1.91 crRs 1.63 cr
-NARs 97.50 lakh-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARCHITECTS INC
EngineerATUL KUDTARKAR AND ASSOCIATES PVT LTD
Chartered AccountantMukesh Gurnani
Chartered AccountantVRP & Associates
PartnerRole in project
DEEPALI LANDSCAPE-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Jul 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Jul 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Jul 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Jul 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed63

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: DL Q3 Form 1.pdf20 Apr 2026
Withdrawal Update Form 1File: DL Q3 Form 1.pdf20 Apr 2026
Withdrawal Update Form 1File: DL Q4 Form 1.pdf20 Apr 2026
Withdrawal Update Form 2File: DL Q3 Form 2.pdf20 Apr 2026
Withdrawal Update Form 2File: DL Q3 Form 2.pdf20 Apr 2026
Withdrawal Update Form 2File: DL Q4 Form 2.pdf20 Apr 2026
Withdrawal Update Form 3File: Form 3 Deepali Landscape 31122023.pdf20 Apr 2026
Withdrawal Update Form 3File: Form 3 Deepali Landscape 31122023.pdf20 Apr 2026
Withdrawal Update Form 3File: Form 3 Deepali Landscape 31122023.pdf20 Apr 2026
Withdrawal Update Form 1File: Form 1 Deepali Landscape 30062025.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2 Deepali Landscape 30062025.pdf20 Jan 2026
Withdrawal Update Form 3File: Form 3 Deepali Landscape 31122023.pdf20 Jan 2026
Form 5 (FY 2024-2025)File: Form 5 Deepali landscape Signed.pdf27 Sep 2025
Withdrawal Update Form 1File: Form 1 Deepali Landscape 30062025.pdf19 Jul 2025
Withdrawal Update Form 2File: Form 2 Deepali Landscape 30062025.pdf19 Jul 2025
Withdrawal Update Form 3File: Form 3 Deepali Landscape 31122023.pdf19 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Deepali Landscape Q4.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Deepali Landscape Q4.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Deepali Landscape 31122024.pdf22 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: From 2.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf18 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: signed-Form 5 Deepali Landscape.pdf29 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf14 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4.pdf14 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q1.pdf14 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Deepali Landscape 30092024.pdf14 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Deepali Landscape- Sep 24.pdf14 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q4.pdf14 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q1.pdf14 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_11zon.pdf21 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf21 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Deepali Landscape 31122023.pdf21 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Deepali Landscape Form 1_11zon.pdf21 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Deepali Landscape Form 2_11zon.pdf21 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Deepali Landscape.pdf2 Aug 2023
Proforma of Agreement for saleFile: AFS.pdf2 Aug 2023
Layout approvalFile: Blue Print 1_11zon_11zon.pdf18 Jul 2023
Layout approvalFile: Blue Print 2_11zon.pdf18 Jul 2023
Building plan approvalFile: Blue Print 1_11zon_11zon.pdf18 Jul 2023
Building plan approvalFile: Blue Print 2_11zon.pdf18 Jul 2023
Copy of Layout Approval (in case of layout)File: Blue Print 1_11zon_11zon.pdf18 Jul 2023
Copy of Layout Approval (in case of layout)File: Blue Print 2_11zon.pdf18 Jul 2023
Building Plan Approval / NA Order for plotted developmentFile: Blue Print 1_11zon_11zon.pdf18 Jul 2023
Building Plan Approval / NA Order for plotted developmentFile: Blue Print 2_11zon.pdf18 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert_11zon.pdf18 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Cert.pdf18 Jul 2023
CERSAI detailsFile: CERSAI_Search_Report_200274702669_For_Asset_Based_Search_18_07_2023_11_36_11_479.pdf18 Jul 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Viraj Patil.pdf18 Jul 2023
Proforma of Allotment letterFile: Annexure 1 - Model form of Allotment Letter_11zon.pdf18 Jul 2023
PAN CardFile: Pan.pdf15 Jul 2023
Copy of the legal title reportFile: Legal Tittle Certificate as per RERA_11zon.pdf15 Jul 2023
Details of encumbrances concerned to FinanceFile: No Encumbrances.pdf15 Jul 2023
Details of encumbrances concerned to LegalFile: No Encumbrances.pdf15 Jul 2023
Commencement Certificates / NA Order for plotted developmentFile: 4 Commencement Certificate_11zon.pdf15 Jul 2023
Declaration about Commencement CertificateFile: Format D.pdf15 Jul 2023
Declaration in FORM BFile: Affidavit Cum Declaration - Surekha Chaoudhary_11zon (1).pdf15 Jul 2023
CERSAI detailsFile: Cresai Creation.pdf15 Jul 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A - Ramaswami Darwin.pdf15 Jul 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A - Siddhesh Patil.pdf15 Jul 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A - Surekha Choudhary.pdf15 Jul 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf15 Jul 2023
Deviation Report with respect to Allotment letterFile: Allotment Letter.pdf15 Jul 2023
Deviation Report with respect to model copy of AgreementFile: Model Copy of Agreement.pdf15 Jul 2023

How this compares with Thane

17%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep JAI GANESH CO-OPERATIVE HOUSING SOCIETY LTD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kulgaon, Badlapur (East)7,600+ in Thane

2 kmJAI GANESH CO-OPERATIVE Completed 201Lapsed / revoked 74Other 125Dot size: filed unitsN

Filed coordinates, straight-line distance. 400 registered projects within 2 km.

Builder: DEEPALI LANDSCAPE

DEEPALI LANDSCAPE has 1 registration on MahaRERA, including JAI GANESH CO-OPERATIVE HOUSING SOCIETY LTD. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if JAI GANESH CO-OPERATIVE HOUSING SOCIETY LTD is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of JAI GANESH CO-OPERATIVE HOUSING SOCIETY LTD?

The registered promoter entity is DEEPALI LANDSCAPE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in JAI GANESH CO-OPERATIVE HOUSING SOCIETY LTD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for JAI GANESH CO-OPERATIVE HOUSING SOCIETY LTD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at JAI GANESH CO-OPERATIVE HOUSING SOCIETY LTD?

The professionals named in the filing: Architect: ARCHITECTS INC; Engineer: ATUL KUDTARKAR AND ASSOCIATES PVT LTD; Chartered Accountant: Mukesh Gurnani; Chartered Accountant: VRP & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in JAI GANESH CO-OPERATIVE HOUSING SOCIETY LTD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About JAI GANESH CO-OPERATIVE HOUSING SOCIETY LTD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save JAI GANESH CO-OPERATIVE HOUSING SOCIETY LTD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.