JAGDEEP
RG-MH-79210 · RERA P52100052446 · Last updated on MahaRERA portal: 17 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 10 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
JAGDEEP is a Residential / Group Housing project by Ranjekar Realty LLP in Pune, Maharashtra, registered with MahaRERA as P52100052446 on 28 Aug 2023. Possession is promised by 25 Nov 2026. The completion date has moved by 10 months from the original filing. 6 of the 20 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.
At a glance
Project
- NameJAGDEEP
- TypeResidential / Group Housing
- Location
- Bhakti Marg
- Law College Road
- Erandwane
- Erandwana
- Haveli
- Pune
- 411004
- Pincode411004
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100052446
- ReraGenie IDRG-MH-79210
Builder
- NameRanjekar Realty LLP
- Entity typePartnership
- LLPINAAQ-0493
- GSTIN27ABAFR0621D1ZS
- LLPIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- PartnersHarish Raoji Patil, Rohan Harish Patil
- Other registrations14 more →
- Completed4 of 15
- No longer live2 lapsed, de-registered or revoked
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on28 Aug 2023
- Promised completion25 Nov 2026
- Revised completionRevised to 25 Nov 2026 (originally 31 Jan 2026)
- Buildings1 building record
- Documents filed96 files
Current status
Figures as on 17 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| JAGDEEP | NA | 8 | 7 | 20 | 0 | 20 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 17 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
JAGDEEP: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 17 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed34
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Jagdeep Co-Operative Housing Society | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| JAGDEEP | NA | Rs 10.50 cr | Rs 10.50 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Pranay Chandratreya |
| Engineer | Aniruddha Ranjekar |
| Chartered Accountant | Kishor R Joshi and Associates |
| Chartered Accountant | Phule Wagh and Associates LLP |
| Partner | Role in project |
|---|---|
| Ranjekar Realty LLP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe have already obtained the Full Occupancy Certificate (Full OC) for the aforesaid registered project from the competent authority. However, prior to submitting the application under the Completion Module on the MahaRERA Portal, we observed that certain fields of Builtup Area Floor Space Index (FSI)/ Inventory/ Floors related corrections are required to be carried out in the project details. SInce presently the status of the above-mentioned project on the MahaRERA Portal is reflected as "Lapsed." Owing to such status, the system does not permit the filing of the requisite Project Correction A
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Aug 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 6 Sep 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 Sep 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 Jul 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 25 Nov 2026
Documents filed96
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 96 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: last form 1.pdf | 17 Sep 2026 |
| Withdrawal Update Form 2File: last Form 2.pdf | 17 Sep 2026 |
| Withdrawal Update Form 3File: last Form 3 Chartered Accountant Certificate Jagdeep.pdf | 17 Sep 2026 |
| Form 1File: Form 1 J.pdf | 6 Aug 2026 |
| Form 2File: form 2 J.pdf | 6 Aug 2026 |
| Form 3File: form 3 J.pdf | 6 Aug 2026 |
| Disclosure of Sold and Booked InventoryFile: sold unsold J.pdf | 6 Aug 2026 |
| Form 1File: Form 1 J.pdf | 6 Aug 2026 |
| Form 2File: form 2 J.pdf | 6 Aug 2026 |
| Form 3File: form 3 J.pdf | 6 Aug 2026 |
| Disclosure of Sold and Booked InventoryFile: sold unsold J.pdf | 6 Aug 2026 |
| Form 2A (FY 2025-2026)File: 2A form.pdf | 6 Aug 2026 |
| Form 5 (FY 2023-2024)File: FORM 5 JAGDEEP 31032024.pdf | 6 Aug 2026 |
| Form 5 (FY 2024-2025)File: FORM 5 JAGDEEP 31032025.pdf | 6 Aug 2026 |
| Form 5 (FY 2025-2026)File: FORM 5 JAGDEEP 31032025.pdf | 6 Aug 2026 |
| Form 1File: form 1 q3 fy 2425.pdf | 12 Mar 2026 |
| Form 2File: form 2 q3 fy 2425.pdf | 12 Mar 2026 |
| Form 3File: form 3 q3 fy 2425.pdf | 12 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: sold unsold.pdf | 12 Mar 2026 |
| OthersFile: jagdeep Full Complition Certificate.pdf | 12 Mar 2026 |
| Self-declaration of Quarterly ProgressFile: Form 4 Architect Certificate JAGDEEP.pdf | 12 Mar 2026 |
| Withdrawal Update Form 1File: Form 1 Architects Certificate 31122025.pdf | 5 Mar 2026 |
| Withdrawal Update Form 1File: Form 1 Architects Certificate 31122025.pdf | 5 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer Certificate 31122025.pdf | 5 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer Certificate 31122025.pdf | 5 Mar 2026 |
| Withdrawal Update Form 3File: Q3 Form 3 Chartered Accountant Certificate 31122025 Jagdeep (1).pdf | 5 Mar 2026 |
| Withdrawal Update Form 3File: Q3 Form 3 Chartered Accountant Certificate 31122025 Jagdeep (1).pdf | 5 Mar 2026 |
| Form 1File: Form 1 Architect Certificate 30092025.pdf | 15 Dec 2025 |
| Form 2File: Form 2 Engineer Certificate 30092025.pdf | 15 Dec 2025 |
| Form 3File: Form 3 Chartered Accountant Certificate 30092025.pdf | 15 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold Inventory 30092025.pdf | 15 Dec 2025 |
| Form 1File: Form 1 Architect Certificate 30062025.pdf | 15 Dec 2025 |
| Form 2File: Form 2 Engineer Certificate- Updated 30062025 Jagdeep.pdf | 15 Dec 2025 |
| Form 3File: Form 3 Charterd Accountant Certificate 30062025 Jagdeep.pdf | 15 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold Inventory 30062025 Jagdeep.pdf | 15 Dec 2025 |
| Form 2A (FY 2023-2024)File: Form 2A 2023-24.pdf | 4 Jun 2025 |
| Form 2A (FY 2024-2025)File: Form 2A 2024-25.pdf | 4 Jun 2025 |
| Form 1File: Form 1 Architect Certificate.pdf | 23 May 2025 |
| Form 2File: Form 2 Engineer Certificate Q4 updated.pdf | 23 May 2025 |
| Form 3File: Form 3 Charterd Accountant Certificate.pdf | 23 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Inventory Sold unsold Q4.pdf | 23 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 JAGDEEP as on 31 DEC 24.pdf | 25 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: JAGDEEP FORM 3 as on 30 JUN 24.pdf | 29 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 JAGDEEP as on 30 09 24.pdf | 29 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: JAGDEEP Form 3 FINAL as on 31 MAR 24.pdf | 29 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory_Declaration_-31032024(1).pdf | 6 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A-FY 2022-23.pdf | 3 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A-FY 2023-24.pdf | 3 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate 31122023.pdf | 30 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate 31032024.pdf | 30 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer Certificate 30092023.pdf | 30 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer Certificate 31122023.pdf | 30 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Jagdeep engineer's certificate Q7.pdf | 12 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: JAGDEEP FORM 3 as on 31 DEC 23.pdf | 12 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: JAGDEEP FORM 3 30092023.pdf | 12 Jan 2024 |
| Layout approvalFile: 1.pdf | 6 Sep 2023 |
| Building plan approvalFile: 2.pdf | 6 Sep 2023 |
| Building plan approvalFile: 3.pdf | 6 Sep 2023 |
| Copy of Layout Approval (in case of layout)File: 1.pdf | 6 Sep 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 2.pdf | 6 Sep 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 3.pdf | 6 Sep 2023 |
| Declaration about Commencement CertificateFile: Format D-Commencement and Plan.pdf | 6 Sep 2023 |
| Copy of the legal title reportFile: main search.pdf | 5 Aug 2023 |
| Declaration about Commencement CertificateFile: Format D-Commencement and Plan.pdf | 5 Aug 2023 |
| Copy of the legal title reportFile: Format A .pdf | 4 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: JAGDEEP FORM 3 Chartered Accountant Certificate 07072023.pdf | 11 Jul 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about seperate bank account as per order 34.pdf | 10 Jul 2023 |
| Layout approvalFile: Jagdeep POA 1 compressed.pdf | 7 Jul 2023 |
| Layout approvalFile: Jagdeep POA 2 compressed.pdf | 7 Jul 2023 |
| Copy of Layout Approval (in case of layout)File: Jagdeep POA 1 compressed.pdf | 7 Jul 2023 |
| Copy of Layout Approval (in case of layout)File: Jagdeep POA 2 compressed.pdf | 7 Jul 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Jagdeep POA 1 compressed.pdf | 7 Jul 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Jagdeep POA 2 compressed.pdf | 7 Jul 2023 |
| Declaration in FORM BFile: form b ranjekar.pdf | 7 Jul 2023 |
| Layout approvalFile: Jagdeep Plan 1.pdf | 6 Jul 2023 |
| Building plan approvalFile: Jagdeep Plan 2.pdf | 6 Jul 2023 |
| Building plan approvalFile: Jagdeep Plan 3.pdf | 6 Jul 2023 |
| PAN CardFile: RR LLP PAN Card.pdf | 6 Jul 2023 |
| Details of encumbrances concerned to FinanceFile: Declaration of no Encumbrance - Finance.pdf | 6 Jul 2023 |
| Details of encumbrances concerned to FinanceFile: Declaration of no Encumbrance - Legal DONE.pdf | 6 Jul 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| OMKARP52100052757 | Karve Nagar, Pune | 13 | Sep 2023 | Completed | Dec 2025 | Oct 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 14 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 96 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep JAGDEEP on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Erandwane13,700+ in Pune
Filed coordinates, straight-line distance. 285 registered projects within 2 km.
VENKATESH ERANDWANE CENTRAL - BUILDING-B1 - PH
SHREE VENKATESH BUILDCON PVT LTD
One Place-F.C. Road Phase 3
PALASH REALTORS LLP
45 NIRVAANA HILL - C2 WING
SINEW DEVELOPERS PRIVATE LIMITED
VENKATESH ERANDWANE CENTRAL - BUILDING-B2 - PH
SHREE VENKATESH BUILDCON PVT LTD
VENKATESH ERANDWANE CENTRAL - BUILDING-B3 - PH
SHREE VENKATESH BUILDCON PVT LTD
One Place-F.C Road Phase 2
PALASH REALTORS LLP
Builder: Ranjekar Realty LLP
Ranjekar Realty LLP has 15 registrations on MahaRERA, including ANANT and DRUMADAL. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if JAGDEEP is delayed beyond 25 Nov 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of JAGDEEP?
The registered promoter entity is Ranjekar Realty LLP, a partnership as per the filing. Its LLPIN AAQ-0493 and GSTIN 27ABAFR0621D1ZS can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in JAGDEEP?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for JAGDEEP?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at JAGDEEP?
The professionals named in the filing: Architect: Pranay Chandratreya; Engineer: Aniruddha Ranjekar; Chartered Accountant: Kishor R Joshi and Associates; Chartered Accountant: Phule Wagh and Associates LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in JAGDEEP?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback