Home / Browse projects / Mumbai Suburban, Maharashtra / IVY MARVEL

Registration lapsed No litigation declared Others project

IVY MARVEL

By NEUMEC REALITY

RG-MH-26989 · RERA P51800006856 · Last updated on MahaRERA portal: 25 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 30 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
13 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 90%
1Complaints at MahaRERAon this registration
Jump to the 177 documents Report an error

IVY MARVEL is a Others project by NEUMEC REALITY in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800006856 on 16 Aug 2017. Possession was promised by 30 Jun 2025 and is now 16 months past that date. The completion date has moved by 30 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameIVY MARVEL
  • TypeOthers
  • Location
    • Andheri
    • Mumbai Suburban
    • 400057
  • Pincode400057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800006856
  • ReraGenie IDRG-MH-26989

Builder

  • NameNEUMEC REALITY
  • Entity typePartnership
  • PartnerNILESH GUNJAL

Key dates

16 months past promisethis monthRegisteredAug 2017First promiseDec 2022Revised toJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on16 Aug 2017
  • Promised completion30 Jun 2025
  • Revised completionRevised to 30 Jun 2025 (originally 30 Dec 2022)
  • Buildings2 building records
  • Documents filed177 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WIngNA150000
B WIngNA150000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 25 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

13 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 90%.

A WIng93%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure86%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
B WIng94%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 25 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes90%
Solid Waste Management And DisposalYes90%
Water conservation /Rain water harvestingYes90%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed39

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots39
Closed/Covered32
Open Space7
BuildingClosed/CoveredOpen SpaceTotal
A WIng16319
B WIng16420

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,164 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
IVY REALTORS & VALUERS LLPNavi Mumbai (M Corp.)Thane

Approvals and building plan

Permissible FSI5287.9
Proposed, not sanctioned1,206 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround floor, Usha Niketan CHS, Hanuman Cross Road no 1, Vile Parle East, Mumbai

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMF Associates
EngineerStructwel Designers & Consultants Pvt Ltd.
EngineerSK Consultants & Engineers
Chartered AccountantRutuja Narsingh & Associates
Chartered AccountantPratiksha Tulshyan & Associates
PartnerRole in project
NEUMEC REALITY-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800008843Dec 2022 → Dec 2023

Reason as filed by the promoterThe Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and liquidity crunch in the market. Various private and Government offices have not been working at full strength and the complete supply chain has broken down. It appears that it is going to take a lot of time to normalize the real estate industry.

EXT51800019375Dec 2022 → Jun 2025

Reason as filed by the promoterAs per Order No. 40 Dated 27/12/2022 we are applying for Extension without majority consents of the allottees. I seek extension of the project till 30/06/2025 and we have received the Order for the same from MahaRERA

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
SM12400009Amolika BandiwadekarNEUMEC REALITY23/09/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Jul 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Jul 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed177

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 177 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: Form 3-Ivy Marvel as on 30-06-2024.pdf25 Feb 2025
Certificates of CA (Form 3)File: Form 3-Ivy Marvel as on 30-09-2024.pdf25 Feb 2025
Certificates of CA (Form 3)File: Form 3-Ivy Marvel as on 31-12-2024.pdf25 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Ivy Marvel as on June 2024.pdf25 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Ivy Marvel as on Sep 2024.pdf25 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Ivy Marvel as on Dec 2024.pdf25 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Ivy Marvel as on December 2024.pdf10 Jan 2025
Building plan approvalFile: 8.pdf24 Jul 2024
Building plan approvalFile: 9.pdf24 Jul 2024
Building plan approvalFile: 10.pdf24 Jul 2024
Building plan approvalFile: 11.pdf24 Jul 2024
Building plan approvalFile: 12.pdf24 Jul 2024
Building plan approvalFile: 13_rotated.pdf24 Jul 2024
Layout approvalFile: 1A.pdf24 Jul 2024
Building plan approvalFile: 1_rotated_rotated.pdf24 Jul 2024
Building plan approvalFile: 2.pdf24 Jul 2024
Building plan approvalFile: 3_rotated_rotated.pdf24 Jul 2024
Building plan approvalFile: 4.pdf24 Jul 2024
Building plan approvalFile: 5.pdf24 Jul 2024
Building plan approvalFile: 6.pdf24 Jul 2024
Building plan approvalFile: 7.pdf24 Jul 2024
Copy of Layout Approval (in case of layout)File: 1A.pdf24 Jul 2024
Building Plan Approval (IOD)File: 1_rotated_rotated.pdf24 Jul 2024
Building Plan Approval (IOD)File: 2.pdf24 Jul 2024
Building Plan Approval (IOD)File: 3_rotated_rotated.pdf24 Jul 2024
Building Plan Approval (IOD)File: 4.pdf24 Jul 2024
Building Plan Approval (IOD)File: 5.pdf24 Jul 2024
Building Plan Approval (IOD)File: 6.pdf24 Jul 2024
Building Plan Approval (IOD)File: 7.pdf24 Jul 2024
Building Plan Approval (IOD)File: 8.pdf24 Jul 2024
Building Plan Approval (IOD)File: 9.pdf24 Jul 2024
Building Plan Approval (IOD)File: 10.pdf24 Jul 2024
Building Plan Approval (IOD)File: 11.pdf24 Jul 2024
Building Plan Approval (IOD)File: 12.pdf24 Jul 2024
Building Plan Approval (IOD)File: 13_rotated.pdf24 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 26 Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf20 Jul 2024
Certificates of CA (Form 3)File: 29 Certificates of CA (Form 3).pdf20 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Ivy Marvel as on June 2024.pdf15 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Ivy Marvel as on March 2024.pdf15 Jul 2024
Certificates of CA (Form 3)File: Form 3 - Ivy Marvel as on March 2024.pdf15 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 June 2017.pdf30 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Dec 2022.pdf30 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 March 2023.pdf30 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 July 2023.pdf30 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Ivy Marvel June 2021.pdf30 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Ivy Marvel Sepember 2021.pdf30 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Ivy Marvel Dec 2021.pdf30 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Ivy Marvel March 2022.pdf30 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Ivy Marvel June 2022.pdf30 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Ivy Marvel September 2022.pdf30 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Ivy Marvel as on December 2022.pdf30 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Ivy Marvel as on March 2023.pdf30 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Ivy Marvel as on June 2023.pdf30 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Ivy Marvel as on Sept 2023.pdf30 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Ivy Marvel as on Dec 2023.pdf30 Apr 2024
Certificates of CA (Form 3)File: Form 3 Ivy Marvel 30th June 2021.pdf30 Apr 2024
Certificates of CA (Form 3)File: Form 3 Ivy Marvel 30th Sept 2021.pdf30 Apr 2024
Certificates of CA (Form 3)File: Form 3 Ivy Marvel 31st Dec 2021.pdf30 Apr 2024
Certificates of CA (Form 3)File: Form 3-IVY Marvel-March 2022_compressed.pdf30 Apr 2024
Certificates of CA (Form 3)File: Form 3-IVY Marvel-June 2022_compressed.pdf30 Apr 2024
Certificates of CA (Form 3)File: Form 3-IVY Marvel-Sept 22_compressed.pdf30 Apr 2024
Certificates of CA (Form 3)File: Form 3- Ivy Marvel as on December 2022_compressed.pdf30 Apr 2024
Certificates of CA (Form 3)File: Form 3- Ivy Marvel as on March 2023.pdf30 Apr 2024
Certificates of CA (Form 3)File: Form 3- Ivy Marvel as on 30-06-2023.pdf30 Apr 2024
Certificates of CA (Form 3)File: Form 3-Ivy Marvel as on 30-09-2023.pdf30 Apr 2024
Certificates of CA (Form 3)File: Form 3 - Ivy Marvel as on Dec 2023.pdf30 Apr 2024
Declaration in FORM BFile: Form B.pdf29 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Feb 24.pdf29 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Dec 23.pdf29 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A - FY 2019-20.pdf29 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A - FY 2020-21.pdf29 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A - FY 2021-22.pdf29 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A - FY 2022-23.pdf29 Apr 2024
Disclosure of sold/ booked inventoryFile: Ivy MArvel Cir 29 D23.pdf29 Apr 2024
Certificates of CA (Form 3)File: Form 3 Dec 23.pdf29 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf29 Apr 2024
Certificates of CA (Form 5)File: Form 5 17-18.pdf29 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 18-19.pdf29 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 19-20.pdf29 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21.pdf29 Apr 2024

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 30 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep IVY MARVEL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Andheri6,700+ in Mumbai Suburban

2 kmIVY MARVELCompleted 155Lapsed / revoked 71Other 153Dot size: filed unitsN

Filed coordinates, straight-line distance. 379 registered projects within 2 km.

Builder: NEUMEC REALITY

NEUMEC REALITY has 1 registration on MahaRERA, including IVY MARVEL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that IVY MARVEL shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if IVY MARVEL is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of IVY MARVEL?

The registered promoter entity is NEUMEC REALITY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in IVY MARVEL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against IVY MARVEL?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for IVY MARVEL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at IVY MARVEL?

The professionals named in the filing: Architect: MF Associates; Engineer: Structwel Designers & Consultants Pvt Ltd.; Engineer: SK Consultants & Engineers; Chartered Accountant: Rutuja Narsingh & Associates; Chartered Accountant: Pratiksha Tulshyan & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in IVY MARVEL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About IVY MARVEL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save IVY MARVEL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.