IVY MARVEL
RG-MH-26989 · RERA P51800006856 · Last updated on MahaRERA portal: 25 Feb 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 16 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 30 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
IVY MARVEL is a Others project by NEUMEC REALITY in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800006856 on 16 Aug 2017. Possession was promised by 30 Jun 2025 and is now 16 months past that date. The completion date has moved by 30 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameIVY MARVEL
- TypeOthers
- Location
- Andheri
- Mumbai Suburban
- 400057
- Pincode400057
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800006856
- ReraGenie IDRG-MH-26989
Builder
- NameNEUMEC REALITY
- Entity typePartnership
- PartnerNILESH GUNJAL
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on16 Aug 2017
- Promised completion30 Jun 2025
- Revised completionRevised to 30 Jun 2025 (originally 30 Dec 2022)
- Buildings2 building records
- Documents filed177 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A WIng | NA | 15 | 0 | 0 | 0 | 0 |
| B WIng | NA | 15 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 25 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
13 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 90%.
A WIng93%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 86% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 65% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
B WIng94%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 65% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Progress on shared amenities15
As on 25 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 90% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 90% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 90% |
| Solid Waste Management And Disposal | Yes | 90% |
| Water conservation /Rain water harvesting | Yes | 90% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 90% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed39
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A WIng | 16 | 3 | 19 |
| B WIng | 16 | 4 | 20 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| IVY REALTORS & VALUERS LLP | Navi Mumbai (M Corp.) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MF Associates |
| Engineer | Structwel Designers & Consultants Pvt Ltd. |
| Engineer | SK Consultants & Engineers |
| Chartered Accountant | Rutuja Narsingh & Associates |
| Chartered Accountant | Pratiksha Tulshyan & Associates |
| Partner | Role in project |
|---|---|
| NEUMEC REALITY | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and liquidity crunch in the market. Various private and Government offices have not been working at full strength and the complete supply chain has broken down. It appears that it is going to take a lot of time to normalize the real estate industry.
Reason as filed by the promoterAs per Order No. 40 Dated 27/12/2022 we are applying for Extension without majority consents of the allottees. I seek extension of the project till 30/06/2025 and we have received the Order for the same from MahaRERA
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| SM12400009 | Amolika Bandiwadekar | NEUMEC REALITY | 23/09/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Jul 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 24 Jul 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed177
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 177 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 3)File: Form 3-Ivy Marvel as on 30-06-2024.pdf | 25 Feb 2025 |
| Certificates of CA (Form 3)File: Form 3-Ivy Marvel as on 30-09-2024.pdf | 25 Feb 2025 |
| Certificates of CA (Form 3)File: Form 3-Ivy Marvel as on 31-12-2024.pdf | 25 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Ivy Marvel as on June 2024.pdf | 25 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Ivy Marvel as on Sep 2024.pdf | 25 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Ivy Marvel as on Dec 2024.pdf | 25 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Ivy Marvel as on December 2024.pdf | 10 Jan 2025 |
| Building plan approvalFile: 8.pdf | 24 Jul 2024 |
| Building plan approvalFile: 9.pdf | 24 Jul 2024 |
| Building plan approvalFile: 10.pdf | 24 Jul 2024 |
| Building plan approvalFile: 11.pdf | 24 Jul 2024 |
| Building plan approvalFile: 12.pdf | 24 Jul 2024 |
| Building plan approvalFile: 13_rotated.pdf | 24 Jul 2024 |
| Layout approvalFile: 1A.pdf | 24 Jul 2024 |
| Building plan approvalFile: 1_rotated_rotated.pdf | 24 Jul 2024 |
| Building plan approvalFile: 2.pdf | 24 Jul 2024 |
| Building plan approvalFile: 3_rotated_rotated.pdf | 24 Jul 2024 |
| Building plan approvalFile: 4.pdf | 24 Jul 2024 |
| Building plan approvalFile: 5.pdf | 24 Jul 2024 |
| Building plan approvalFile: 6.pdf | 24 Jul 2024 |
| Building plan approvalFile: 7.pdf | 24 Jul 2024 |
| Copy of Layout Approval (in case of layout)File: 1A.pdf | 24 Jul 2024 |
| Building Plan Approval (IOD)File: 1_rotated_rotated.pdf | 24 Jul 2024 |
| Building Plan Approval (IOD)File: 2.pdf | 24 Jul 2024 |
| Building Plan Approval (IOD)File: 3_rotated_rotated.pdf | 24 Jul 2024 |
| Building Plan Approval (IOD)File: 4.pdf | 24 Jul 2024 |
| Building Plan Approval (IOD)File: 5.pdf | 24 Jul 2024 |
| Building Plan Approval (IOD)File: 6.pdf | 24 Jul 2024 |
| Building Plan Approval (IOD)File: 7.pdf | 24 Jul 2024 |
| Building Plan Approval (IOD)File: 8.pdf | 24 Jul 2024 |
| Building Plan Approval (IOD)File: 9.pdf | 24 Jul 2024 |
| Building Plan Approval (IOD)File: 10.pdf | 24 Jul 2024 |
| Building Plan Approval (IOD)File: 11.pdf | 24 Jul 2024 |
| Building Plan Approval (IOD)File: 12.pdf | 24 Jul 2024 |
| Building Plan Approval (IOD)File: 13_rotated.pdf | 24 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 26 Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf | 20 Jul 2024 |
| Certificates of CA (Form 3)File: 29 Certificates of CA (Form 3).pdf | 20 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Ivy Marvel as on June 2024.pdf | 15 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Ivy Marvel as on March 2024.pdf | 15 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 - Ivy Marvel as on March 2024.pdf | 15 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 June 2017.pdf | 30 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Dec 2022.pdf | 30 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 March 2023.pdf | 30 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 July 2023.pdf | 30 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Ivy Marvel June 2021.pdf | 30 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Ivy Marvel Sepember 2021.pdf | 30 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Ivy Marvel Dec 2021.pdf | 30 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Ivy Marvel March 2022.pdf | 30 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Ivy Marvel June 2022.pdf | 30 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Ivy Marvel September 2022.pdf | 30 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Ivy Marvel as on December 2022.pdf | 30 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Ivy Marvel as on March 2023.pdf | 30 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Ivy Marvel as on June 2023.pdf | 30 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Ivy Marvel as on Sept 2023.pdf | 30 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Ivy Marvel as on Dec 2023.pdf | 30 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3 Ivy Marvel 30th June 2021.pdf | 30 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3 Ivy Marvel 30th Sept 2021.pdf | 30 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3 Ivy Marvel 31st Dec 2021.pdf | 30 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3-IVY Marvel-March 2022_compressed.pdf | 30 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3-IVY Marvel-June 2022_compressed.pdf | 30 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3-IVY Marvel-Sept 22_compressed.pdf | 30 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3- Ivy Marvel as on December 2022_compressed.pdf | 30 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3- Ivy Marvel as on March 2023.pdf | 30 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3- Ivy Marvel as on 30-06-2023.pdf | 30 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3-Ivy Marvel as on 30-09-2023.pdf | 30 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3 - Ivy Marvel as on Dec 2023.pdf | 30 Apr 2024 |
| Declaration in FORM BFile: Form B.pdf | 29 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Feb 24.pdf | 29 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Dec 23.pdf | 29 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A - FY 2019-20.pdf | 29 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A - FY 2020-21.pdf | 29 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A - FY 2021-22.pdf | 29 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A - FY 2022-23.pdf | 29 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Ivy MArvel Cir 29 D23.pdf | 29 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3 Dec 23.pdf | 29 Apr 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf | 29 Apr 2024 |
| Certificates of CA (Form 5)File: Form 5 17-18.pdf | 29 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 18-19.pdf | 29 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 19-20.pdf | 29 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21.pdf | 29 Apr 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 177 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep IVY MARVEL on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Andheri6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 379 registered projects within 2 km.
Vijayraj Residency
Vijayraj Realtors
ZEE HAPPY VEENA
ZEE LIFESPACES
Romell Espalier
ROMELL REAL ESTATE PRIVATE LIMITED
ZEE SHAAN
TRISUL DEVELOPERS
SALE BUILDING 1 - CHAMUNDA CROWN AND SALE BUIL
Chamunda Builders & Developers
ARKADE PEARL 1
ARKADE DEVELOPERS LIMITED
See every Mumbai Suburban project, with the district possession charts
Builder: NEUMEC REALITY
NEUMEC REALITY has 1 registration on MahaRERA, including IVY MARVEL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that IVY MARVEL shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if IVY MARVEL is delayed beyond 30 Jun 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of IVY MARVEL?
The registered promoter entity is NEUMEC REALITY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in IVY MARVEL?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against IVY MARVEL?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for IVY MARVEL?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at IVY MARVEL?
The professionals named in the filing: Architect: MF Associates; Engineer: Structwel Designers & Consultants Pvt Ltd.; Engineer: SK Consultants & Engineers; Chartered Accountant: Rutuja Narsingh & Associates; Chartered Accountant: Pratiksha Tulshyan & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in IVY MARVEL?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.